Professional Documents
Culture Documents
FIRE SUPPRESSION
MB1908 – VILLA (G+1+R+SB+GARAGE)
DIVISION 21 – SPECIFICATIONS
SECTION 21 05 00
FIRE SUPPRESSION SCOPE OF WORKS
TABLE OF CONTENTS
1.1. INTRODUCTION
1.2. GENERAL
A. WORK INCLUDED
5. The Contractor shall carry out the works as described herein and as
6. This specification covers the provision and installation of all the Fire
Suppression services for the project, including supervision of the
mechanical works.
7. The Contractor shall include for the whole of the work involved and
the supply of materials necessary for the satisfactory completion of the
Fire Suppression installation, as set down in this specification, schedules
of accompanying drawings and for the supply, delivery to site,
offloading, storing, protecting, taking out of store, putting into position,
installation, fixing, including any fixings brackets, plinths and builders
work for items of Fire Suppression equipment, inspecting, testing,
attendance on other trades, commissioning of the system and
removal from the site of waste material, described in detail herein, and
as specified on the accompanying drawings.
C. The Contractor shall ensure that items forming part of the mechanical
services installation are installed to the manufacturer’s
recommendations, relevant local authority regulations, American and
NFPA recommendations.
B. Ensure that all notices are adhered to with respect to down time or
disruption to existing services and provide all necessary temporary
works to ensure that operational areas continue to function normally.
C. Read this part of the specification in conjunction with the rest of the
specification and all associated documents and drawings.
D. The Contractor shall design where requested, supply, install, test and
commission the mechanical services, as outlined within this Specification
unless otherwise stated.
A. The Villa (Ground Floor, First Floor, Roof Floor, Service Block, Covered
Garage)
2. NFPA
sections
1.8. COORDINATION
B. The scope of work shall comprise but not be limited to the following:
6. Test drains
7. Standpipe connections
9. Fire Extinguishers
C. All materials and equipment shall be new, clean and free from
corrosion.
Fire Protection
NFPA (Various)
The contractor is to ensure that the maximum load bearing weight (live
and static weights) of the structural slab, roadways, etc. is taken into
consideration when transporting, installing, etc. all MEP systems and
ancillary supporting equipment.
The following design criteria has been used for the design of the
Mechanical, Plumbing and Drainage Engineering Services.
External Conditions
A. A Fire Department connection for the use of the local Civil Defence shall
be provided for the private fire services mains.
B. The connection shall be located at the front of the building where the
agreed fire appliance firefighting location has been identified by the
Fire Consultant. At the location shown the breaching connection shall
be used for tank filling with the remaining connection utilised for
charging the fire main.
B. The system shall be a Class I system providing 65mm hose valves with
hose connections.
A. The Contractor shall provide all fire extinguishers. The installation shall
comply with the requirements of the standard specification.
B. Fire extinguishers shall be provided, but not limited to, the following
areas:
C. Fire extinguishers shall comply with NBC and NFPA 10 for listing and
labelling.
A. All Fire Protection systems will be installed in accordance with the seismic
zone classification of Dubai which is UBC Zone 2B.
B. All life safety fire protection systems will be installed on seismically rated
supports with necessary support cross bracing to ensure these systems
will not be damaged in a seismic event.
C. All life safety fire protection systems will be designed and installed with
seismic considerations relevant to the acceleration rates and forces
imposed on the life safety fire protection systems during a zone 2b
seismic event to reduce the risk that the life safety fire protection systems
will be damaged by a seismic event.
2.10. COMMISSIONING
commissioning representatives.
A. The Contractor shall include for onsite and class training of the
employers Engineering and maintenance staff on the complete
mechanical and electrical Engineering systems including associated
cause and effect on all systems. The Contractor shall submit his
proposed training procedures with his Tender offer including all
necessary attendance of specialist commissioning Engineers and
specialist suppliers.
2. Arrange with the Employer the most suitable time for instructions to
their operating and maintenance personnel.
B. Make joints with parent and filter metal fully bonded throughout with no
inclusions, holes porosity or cracks.
A. Butt joints which will be visible in completed work to be smooth, flush with
adjacent surfaces.
A. Apply after fabrication is complete and all fixing holes have been drilled
unless otherwise specified. Before applying coating remove all paint,
grease, flux, rust, burrs and sharp arises. Make good all defects which
would show after application of coating and finish surfaces smooth.
2.18. WARRANTEES/GUARANTEES
A. The contractor will be liable for all systems and equipment for a period
of 1 year from TOC (i.e. the Defects and Liability Period, DLP).
Warranty
Piping Accessories and all 5 Years Complete Unit
Duration
Mechanical
Fire FightingValve'sEquipment
not listed above 2 Years Complete Unit
DIVISION 21 – SPECIFICATIONS
SECTION 21 05 01
COMMON WORK RESULTS FOR FIRE SUPPRESSION
TABLE OF CONTENTS:
PART 1 | GENERAL ............................................................................................................1
1.1. SECTION INCLUDES ...................................................................................................1
1.2. RELATED SECTIONS ....................................................................................................1
1.3. REFERENCE STANDARDS ...........................................................................................1
1.4. PERFORMANCE REQUIREMENTS ..............................................................................2
1.5. SUBMITTALS ................................................................................................................4
1.6. QUALITY ASSURANCE................................................................................................5
1.7. DELIVERY, STORAGE, AND HANDLING ....................................................................5
1.8. PROJECT / SITE CONDITIONS ...................................................................................5
1.9. WARRANTY ................................................................................................................5
PART 2 | PRODUCTS .........................................................................................................6
2.1. GENERAL....................................................................................................................6
2.2. STAND PIPE SYSTEM DESIGN .....................................................................................7
2.3. STRESS ANALYSIS ........................................................................................................7
PART 3 | EXECUTION ........................................................................................................8
3.1. EXAMINATION ...........................................................................................................8
3.2. PREPARATION ............................................................................................................8
3.3. INSTALLATION ............................................................................................................8
3.4. PROTECTION ..............................................................................................................9
3.5. TESTING ......................................................................................................................9
3.6. DEMONSTRATION ......................................................................................................9
3.7. CLIENT TRAINING .......................................................................................................9
PART 1 | GENERAL
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of Practice - 2011 and the latest NFPA standards
relative to the system component or installation. The more stringent
requirement between UAE Fire and Life Safety Code and the relevant
NFPA codes will always apply.
B. The following are reference standards that form part of this specification
(latest edition). Associated regulations and guidelines should be
incorporated into the requirements for the installations
B. The scope of work shall include, but not be limited to the following:
1. Supply, install, test and commission all fire protection piping, etc. to
make a complete installation as indicated on the drawings.
3. This Contractor shall allow a min. of 3 weeks for the return of reviewed
shop drawings.
E. All installations shall be installed and tested in accordance with the best
International Standards and Codes of Practice specifically with the
current issue of NFPA standards and the requirements of the local Civil
defence.
I. The Contractor is responsible for all final co-ordination. This shall include
the assessment of any thermal insulation required to protect the system
from damage or operational risk as a result of excessive heat or cold
within the area served. Thermal insulation shall be provided where
pipework or equipment is exposed to these risks. This may also include
trace heating in extreme conditions.
1.5. SUBMITTALS
A. The following shall be submitted for review within 21 days of award and
prior to delivery of materials:
c. Breeching Inlets
f. Piping isometrics
g. Flow calculations
1.9. WARRANTY
A. This warranty shall further provide that in the event of the failure of any
system or its component equipment items or the improper functioning
thereof, during the period of the warranty, the Contractor shall have
available and "on call", within eight hours or less, competent service
personnel for the restoration of all systems and equipment for complete
operation. Should the nature of the failure be such as to present an
emergency in the opinion of the Client, such personnel shall be promptly
available. Regardless of the hour of the day of the week, should the
failure be such as to fall under this warranty, the cost of the services shall
be borne by the Contractor.
B. If service personnel are not promptly available "on call" within eight
hours or less, the Client may employ such personnel as are available to
him, at the expense of the Contractor.
PART 2 | PRODUCTS
2.1. GENERAL
F. Shop Drawings shall show type and location of hangers, pipe sizes and
location, details of alarm valve and trim, control valves, and all
additional information required for approval by the Authorities and
Factory Mutual.
H. Submit six (6) copies of shop drawings and hydraulic calculations which
shall bear the stamp of a fire protection professional Engineer.
D. Hydraulic calculation shall include and identify the pressure drop from
the water tank to the pump and through the loop main to the risers, in
addition to the overhead piping.
B. All stress analysis will take into account but not be limited to the
following:
2. Pressure thrust
3. Surge pressures
C. Stress Analysis will be carried out by 3rd party Stress Analysis specialist
employed by the Contractor. The appointment of the Stress Analysis
specialist will be subject to client approval based on the submission of
documentation indicating the proposed specialists experience in this
field.
D. The results of the Stress Analysis will be used to detail main risers and
horizontal distribution pipe work systems with regard to final pipe
routing, material selection and the location and sizing of supports,
guides and anchors all in relation to selected expansion/contraction
and pipework movement compensation devices.
F. All Stress Analysis reports and results, including structural calculations, for
pipework system materials, supports, guides and anchors shall be
submitted for approval.
PART 3 | EXECUTION
3.1. EXAMINATION
3.2. PREPARATION
A. The Contractor shall ensure that all plant, materials and site conditions
are as required to ensure the works can be undertaken in accordance
with the design intent.
3.3. INSTALLATION
A. The Contractor shall be responsible to co-ordinate his work with all other
Trades and shall be completely familiar with and shall make allowance
B. The installation of the fire protection systems shall be carried out with due
regard for the space limitations of the building and for the space
requirements of other Trades.
3.4. PROTECTION
3.5. TESTING
3.6. DEMONSTRATION
3. Brief operating guides shall be provided for all systems as part of the
training package.
End of Section 21 05 01
DIVISION 21 – SPECIFICATIONS
SECTION 21 05 29
HANGERS AND SUPPORTS FOR FIRE FIGHTING PIPING EQUIPMENT
TABLE OF CONTENTS
PART 1 | GENERAL
A. This Section includes hangers and support systems for all Fire Suppression
and Extinguishing systems.
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of Practice - 2011 and the latest NFPA standards
relative to the system component or installation. The more stringent
requirement between UAE Fire and Life Safety Code and the relevant
NFPA codes will always apply.
B. The following are reference standards that form part of this specification
(latest edition). Associated
c. Appurtenances
A. To provide hangers and/or supports such that all Fire equipment which
is independently supported directly from the structure of the building or
Schedule of Approved Manufacturers Section 21 05 29 - 2
MB1908 – VILLA (G+1+R+SB+GARAGE)
C. All hangers & or supports shall be of appropriate Fire rating to match the
Fire rating of that items of Fire equipment.
(For example: If a duct has a one-hour 300C Fire rating the hanger
and/or support system for that duct shall have a rating which will
maintain that duct in position and allow it to operate for the same
period in the same Fire condition.)
1.5. SUBMITTALS
A. Calculations
B. Product Data: The following shall be submitted for all hangers and/or
supports in accordance with paragraph entitled, "General
Requirements," of this section.
D. Design Data: Design Analysis and Calculations shall be submitted for all
hangers and/or supports in accordance with paragraph entitled,
"General Requirements," of this section.
locations.
1. To manufacturer’s recommendations.
D. Protect against damage from sand, grit, and other foreign matter.
1.8. WARRANTY
PART 2 | PRODUCTS
2.1. GENERAL:
1. Galvanized, Metallic Coatings: For piping and equipment that will not
have field -applied finish.
field assembly.
4. For Clevis or Band Hanger: Insert and shield cover lower 180 degrees
of pipe.
PART 3 | EXECUTION
3.1. EXAMINATION
3.2. PREPARATION
A. Not applicable
3.3. INSTALLATION
B. For Fire pipes use a galvanized steel insulation protection shield between
the insulation and the hanger. The shield width shall be minimum 1/4 of
the pipe circumference. The length and gauge shall be as follows:
E. Provide plastic coated clevis hangers for copper piping. All horizontal
piping 50mm dia and larger shall be supported by adjustable
galvanized wrought iron clevis type hangers.
H. For pipe sizes of 200 dia and larger, pipe supports shall be designed and
installed of structural steel in accordance with section 5100 and
reviewed by the Engineer. All structural steel in contact with the pipes
shall then be insulated as the pipe. Submit details for review.
3.4. INSPECTION
3.5. COMMISSIONING
3.6. PROTECTION
3.7. TESTING
3.8. DEMONSTRATION
3. Brief operating guides shall be provided for all systems as part of the
training package.
End of Section 26 10 29
DIVISION 21 – SPECIFICATIONS
SECTION 21 05 29
SCHEDULE OF APPROVED MANUFACTURERS
TABLE OF CONTENTS
PART 1 | GENERAL
All the materials supplied under this contract shall be from one of the
manufacturers listed below. No alternative makes shall be accepted
unless all the listed makes are unavailable. Materials proposed from
listed makes also must fully comply with detailed specifications. Country
of origin, where listed, must be complied & material should be from main
distributors.
ITEM MANUFACTURER
GEBERIT – SWITZERLAND
7. ACCESSORIES CENTRAL
VIKING
RELIABLE
NITIN
DIVISION 21 – SPECIFICATIONS
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
Table of Contents
PART 1 |GENERAL ...................................................................................................................1
1.1. SECTION INCLUDES ...................................................................................................1
1.2. RELATED SECTIONS ....................................................................................................1
1.3. REFERENCE STANDARDS ...........................................................................................1
1.4. PERFORMANCE REQUIREMENTS ..............................................................................2
1.5. QUALITY ASSURANCE................................................................................................3
1.6. DELIVERY, STORAGE, AND HANDLING ....................................................................3
1.7. PROJECT / SITE CONDITIONS ...................................................................................3
1.8. WARRANTY ................................................................................................................3
PART 2 |PRODUCTS ................................................................................................................4
2.1. GENERAL....................................................................................................................4
2.2. COMMISSIONING PROGRAMME.............................................................................4
2.3. METHOD STATEMENT .................................................................................................4
2.4. DOCUMENTATION ....................................................................................................4
PART 3 |EXECUTION ...............................................................................................................5
3.1. TESTING ......................................................................................................................5
3.2. CLIENT TRAINING .......................................................................................................5
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of Practice - 2011 and the latest NFPA standards
relative to the system component or installation. The more stringent
requirement between UAE Fire and Life Safety Code and the relevant
NFPA codes will always apply.
B. The following are reference standards that form part of this specification
(latest edition). Associated regulations and guidelines should be
incorporated into the requirements for the installations.
1.8. WARRANTY
PART 2 | PRODUCTS
2.1. GENERAL
2.4. DOCUMENTATION
for the demonstration and approval of the systems by the local civil
defence
PART 3 | EXECUTION
3.1. TESTING
End of Section 21 08 00
DIVISION 21 – SPECIFICATIONS
SECTION 21 11 00
FACILITY FIRE SUPPRESSION WATER SERVICE PIPING
TABLE OF CONTENTS:
PART 1 | GENERAL
B. This section relates to the design and installation of all pipework and
fittings relative to the Division 1.2 21 Fire Suppression Systems.
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of Practice - 2011 and the latest NFPA standards
relative to the system component or installation. The more stringent
requirement between UAE Fire and Life Safety Code and the relevant
NFPA codes will always apply.
B. The following are reference standards that form part of this specification
(latest edition). Associated regulations and guidelines should be
incorporated into the requirements for the installations
Systems
b. NFPA 24, Standard for the Installation of Private Fire Service Mains
and Their Appurtenances
d. Protection Systems
A. All pipework and fittings shall be suitable for the conveyance of water
through the fire protection system, maintaining a live water supply
without degradation to the materials or leakage.
1.8. WARRANTY
PART 2 | PRODUCTS
1. Where working pressure in the piping is below 2000 kPa, pipes shall be
ERW factory galvanized steel to ASTM A 53 grade B, schedule 40.
2. Fittings for piping 50mm and smaller shall be UL listed and FM approved
threaded factory galvanized cast iron fitting, class 250 to ANSI B16.4.
3. Fittings for piping larger than 50mm shall be joined using factory
1. Where working pressures in the piping is 2000 kPa and above pipes
shall be ERW factory galvanized steel to ASTM A 53 grade B, schedule
80.
3. Fittings for piping larger than 50mm shall be extra heavy UL listed and
FM approved flanged and weld galvanized wrought steel fittings class
300 to ANSI B 16.9.
C. Welding:
D. Underground pipework:
2.2. PAINTING
B. Clevis hangers shall be adjustable, of yoke and lower U strap design with
cross bolt, and manufactured from galvanized steel. Cross bolt shall
have a double locking nut. Vertical adjustable supporting rod shall have
a load nut below the yoke and a locking a nut above the yoke. Vertical
inserts installed using power activated gun will not be accepted. 'C' type
beam clamps will not be accepted.
F. Riser clamps shall be galvanized steel bands shaped to tightly fit O.D. of
pipe, secured with bolts.
local fire department and a common 100mm outlet pipe c/w check
valve. Connections shall be complete with threaded caps, chained to
body. All parts including valve body, chain and caps shall be polished
and chrome plated bronze.
B. Wall Siamese shall be flush type with wording in and English as specified
below, cast into face plate.
E. NFPA and as shown on drawings. Provide one check valve for each
connection.
F. Locations of all fire department connections shall suit the agreed access
locations in accordance with the fire strategy for the project
3.1. EXAMINATION
3.2. PREPARATION
A. The Contractor shall ensure that all plant, materials and site conditions
are as required to ensure the works can be undertaken in accordance
with the design intent.
3.3. INSTALLATION
3.4. PROTECTION
3.5. TESTING
A. Make pressure tests on all fire protection piping included in the contract.
Tests shall be made after all sprinkler heads and water flow switches are
installed, but before piping is painted, covered or concealed. Furnish all
labour and equipment required for testing.
B. The Client shall be notified one week in advance of any testing so that
the tests can be witnessed.
C. Defects that develop during the tests shall be promptly remedied and
testing shall be reapplied to the satisfaction of the Client.
3.6. COMMISSIONING
3.7. CLEANING
A. Contractor shall flush the fire protection system with clean water as
necessary to remove builder’s debris, dirt and corrosion before
commissioning system. Fire Protection system pipework will be
demonstrated to Consultant and Client as being clean internally before
system is commissioned.
3. Brief operating guides shall be provided for all systems as part of the
training package.
End of Section 21 11 00
DIVISION 21 – SPECIFICATIONS
SECTION 21 12 00
TABLE OF CONTENTS
PART 1 | GENERAL
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of Practice - 2011 and the latest NFPA standards
relative to the system component or installation. The more stringent
requirement between UAE Fire and Life Safety Code and the relevant
NFPA codes will always apply.
B. The following are reference standards that form part of this specification
(latest edition). Associated regulations and guidelines should be
incorporated into the requirements for the installations
Systems
b. NFPA 24, Standard for the Installation of Private Fire Service Mains
and Their Appurtenances
B. The scope of work shall include, but not be limited to the following:
1. Supply and install all piping, landing valves, etc. to make a complete
installation
1.8. WARRANTY
PART 2 | PRODUCTS
B. The class of the system shall be as detailed in the scope of works and
shall be in accordance with the fire strategy for the project.
D. These valves shall not close in less than 5 seconds when operated at
maximum possible speed from the fully open position unless stipulated
otherwise.
A. Fire extinguishers shall comply with NFPA-10 for listing and labeling.
1. Carbon dioxide: 5 kg
3. Clean Agent
D. to RAL 3001, the door shall incorporate a wired glass inspection window.
B. Wall Siamese shall be flush type with wording in Arabic and English as
specified below, cast into face plate.
B. Fire Hose cabinets shall be provided with indication signage. Local Civil
PART 3 | EXECUTION
3.1. EXAMINATION
3.2. PREPARATION
A. The Contractor shall ensure that all plant, materials and site conditions
are as required to ensure the works can be undertaken in accordance
with the design intent.
3.3. INSTALLATION
3.4. PROTECTION
3.5. TESTING
3.6. DEMONSTRATION
3. Brief operating guides shall be provided for all systems as part of the
training package.
End of Section 21 12 00
DIVISION 21 – SPECIFICATIONS
SECTION 21 20 00
FIRE EXTINGUISHING SYSTEMS
TABLE OF CONTENTS
PART 1 | GENERAL
C. This section relates to the design and installation of fire extinguishers and
stand-alone extinguishing systems not covered in other Division 21
Specifications.
A. All firefighting installations and equipment shall fully comply with UAE Fire
and life Safety Code of
B. Practice - 2011 and the latest NFPA standards relative to the system
component or installation. The more stringent requirement between UAE
Fire and Life Safety Code and the relevant NFPA codes will always
apply.
C. The following are reference standards that form part of this specification
(latest edition). Associated regulations and guidelines should be
incorporated into the requirements for the installations
Standards. In particular: -
Spray Systems
C. The scope of work shall include, but not be limited to the following:
1. Supply and install all piping, landing valves, etc. to make a complete
installation.
2. This section covers the minimum requirements for the installation of fire
extinguishers and standalone systems required to protect the building.
1.8. WARRANTY
PART 2 | PRODUCTS
A. Fire extinguishers shall comply with NFPA-10 for location, listing and
labeling.
B. Provide dry powder and CO2 fire extinguishers in each hose cabinet.
The pressure test on the extinguisher shall remain valid for 5 years.
1. Carbon dioxide: 5 kg
F. Unless otherwise stated, each fire hose cabinet shall be equipped with
a 5 kg ABC fire extinguisher and 5 kg CO2 fire extinguisher.
A. Fire blankets shall be provided in all kitchens and pantries together with
any other locations required by civil defence over and above locations
shown on the drawings. These shall be approved by the local civil
defence and should be mounted in accordance with manufacturers
requirements.
PART 3 | EXECUTION
3.1. EXAMINATION
3.2. PREPARATION
A. The Contractor shall ensure that all plant, materials and site conditions
are as required to ensure the works can be undertaken in accordance
with the design intent.
3.3. INSTALLATION
A. Provide fire extinguishers of type, size, and capacity for each cabinet
and other locations indicated.
thick, cold-rolled steel sheet lined with minimum 5/8-inch (16-mm) thick,
fire-barrier material. Provide factory drilled mounting holes.
3. Orientation: Vertical
3.4. PROTECTION
3.5. TESTING
3.6. DEMONSTRATION
3. Brief operating guides shall be provided for all systems as part of the
training package.
End of Section 21 20 00