Zubair New Degassing Project Task Method Statement

Company MSK Ref:


Work JPR 8 – Lay Down Area Start Date:23/04/2016
location Start Time: 07:00am
Description End Date: 29/04/2016
of the task steel structure assembly and erection End Time: 17:00hrs

Personnel Name Position Tel


SECL Ahmed Ali SIV
Issuing Authority
SUBCON Tawfeeq A Alrhida Site Eng.
Performing Authority
Tools & Crane /Hand Tools
Equipment:

Sequence of Minimum Personnel Protective Equipment (PPE) to be worn on site is as follows:


Operations Overalls,
(Specifying Hard Hat,
methods of
working, tools, Safety Footwear,
materials and
equipment
Eye Protection,
utilised) Gloves,
Reflective Vest
Full Safety Harnesses (where necessary).

1. Start assembly structure in ground using 100 ton and but wood under H-beam
2. The H-beam is bed together and brace with bolts
3. Weight of H-beam is 1.5 ton
4. Work Preparation: Arranging Work equipments in work area for the lifting job.
5. Clear area for working afforded at all times by client.
6. Ground preparatory work to be carried out prior to arrival of crane and to be able to
withstand the loadings imposed during this operation.
7. Centre of gravity to be clearly marked on the Items to be lifted.
8. Daily coordination meetings carried out as per site standard procedures, with owner’s
Representative and other contractors during Heavy Lift schedule.
On the days that the lifting and installation are taking place there will be a ‘toolbox’ meeting
prior to the start of activities that will review.
9. All equipment within this procedure is to have current certification at the time of installation
and colour tagged to indicate correlation. All the equipment is to be inspected prior to
mobilization by a Heavy Equipment Inspector and signed off fit for purpose. At site the
equipment will be inspected by the HL Supervisor and owner representative and when
correlated to the certification it will be colour tagged.
10. Prior to commencement of work, work areas and exclusion zones will be set up and
demarcated using hazard bunting tape.
11. Dressing to be held as required to prevent interference with lifting tackle, lifting equipment
or structures along lift path where required. Any protrusions from item that may interfere
with the same are to be removed to avoid possible interference during the lift.
12. House Keeping before and after job for any combustible material or any inflammable
material.

1
Task specific Are barricades in place prior to the lift: yes
information Are suitable outrigger pads in place prior to the lift: yes
(Any task specific
information e.g. Is there a qualified rigger controlling the lift: yes
hydro-test max
pressure, piping
Is the crane operator qualified: yes
length or types of Is there a qualified Flag-Man / Signalman to assist the operator / rigger: yes
chemicals)
Does the Flagman / Signalman have the correct communication devices yes
Has all lifting equipment and rigging been inspected and colour coded: yes
Is the correct type of sling, shackle, chains or rigging being used: yes
Is the wind speed over 30kph (8.3m/s): No
Has a lifting plan been submitted: yes
Has the lifting area been checked for underground or overhead facilities: yes
Are there any limitations on radius / movement: yes

Task
Diagram
(Draw diagram of
excavation, lifting
plan or other
relevant task
information)

PPE

Safety Boots Gloves Eye Protection Respiratory Hard Hats Hearing PPE Face Shield
Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No Yes/No
Other PPE
Emergency

Procedures

First Aid (e.g. first aid box or clinic) FirstAider: (24 x 7) – 078.0648.7625
Facilities
Tel No:

All work will be undertaken by qualified competent persons with experience of the type of work described above, and in all cases in
full accordance with safety procedures specified in the SECL Health and Safety Policy.

Prepared by: Tawfeeq A Alrhida Reviewed by: SECL: Ahmed Ali


Position: Site Eng. Position (SECL): S/V

Signed: Signed: