The Head of the team responsible for construction work or the work supervisor is required to attend S-PCM or
the meeting needs to be held at site.
ITEM No DESCRIPTION OF DISCUSSION
1. Activity: scaffolding erection and dismantling inside the intermediate produce water tank A+B
Page: /1
ITEM No DESCRIPTION OF DISCUSSION
7. Work Sequence;
1. Conduct to TBM before start job.
2. Start erection as per design.
3. Erection proper light inside and outside the tank.
4. Inside tank 10 light and outside 1 light
5. Provide stand for cable hanging inside the tank.
6. Erection ventilation inside the tank.
7. provide a trained hole watcher with log entry sheet and gas test sheet.
8. Provide fan and exat and fire extinguisher
9. All person who go inside the tank use ear pludge.
10. First aid facility and emergency response will prepare.
11. A trained rescue team will be stay inside tank consist of 4 member
Name rescue team
Yousaf hasan
Jasem Mohammad
Moslem aqeel
Alaa tahseen
12.Full time job supervision bt HSE supervisor and work supervisor.
13.Check the co , H2O, LEL and conduct TMB then go inside the tank
14
14.Provide suitable equipment for shifting materials to work side
15.Use tag line when loading and unloading materials.
16. Barricade the lifting area.
17.Scaffolding materials should be as per standard and will not use damage material
18.HSE supervisor and supervisor will monitor the activity .
19.Small quantity of material put inside the tank not stock huge quantity.
20.Wear full body harness while working at height and 100% tie off.
21.Erection scaffolding step by step erection stair case for access
22.use pulley and rope off 16mm to raise the materials to top level during scaffolding
erection
23. all person come out from tank after one hour one by one
HSE Requirements/Precautions: