BILL OF MEP WORKS SUMARY

Nama Pekerjaan : BD 04 - QC LAB 2 & OFFICE BUILDING OF LEGO REBOOT PROJECT


Pemilik : PT. INTEGRATED HEALTHCARE INDONESIA (IHI)

No. Item Pekerjaan Jumlah Harga

1 BILL NO.4.1. FIRE FIGHTING INSTALLATION Rp 117,366,000.00

2 BILL NO.4.2. ELECTRICAL INSTALLATION Rp 434,482,000.00

3 BILL NO.4.3. ELECTRONIC INSTALLATION Rp 632,912,000.00

4 BILL NO.4.4 HVAC INSTALLATION Rp 634,298,000.00

5 BILL NO.4.5. COLD, WASTE WATER & VENT INSTALLTION Rp 15,626,000.00

6 BILL N0.4.6 TESTING AND COMMISSIONING Rp 200,000,000.00

JUMLAH : Rp 1,917,318,000.00
PPN 10 % : Rp 191,731,800.00
JUMLAH TOTAL : Rp 2,109,049,800.00
DIBULATKAN : Rp 2,109,000,000.00
TERBILANG :
DUA MILYAR SERATUS SEMBILAN JUTA RUPIAH

Cikarang, 07 Oktober 2020


PT. JAVA NAYLA KONTRAKTOR

Novi Efendi
Direktur Utama
TeamworX

JNJ-IHI LEGO REBOOT


MECHANICAL, ELECTRICAL, AND PLUMBING WORKS BD 04, QC & LAB
PT. INTEGRATED HEALTHCARE INDONESIA (IHI)
FINAL SUMMARY

741086191.xlsx Bill No. 4 MEP


TeamworX
FINSUM U
Item n
BILL NO. 4. MEP WORKS FINAL SUMMARY Qty Unit Rate Rupiahs
No. i
t
BILL OF QUANTITY

to the proposed

BD - 04, QC & LAB BUILDING

for INTEGRATED HEALTHCARE INDONESIA, at CIBUBUR - JAKARTA

BILL NO. 4 - MEP SUMARY Rp.

BILL NO.4.1. FIRE FIGHTING INSTALLATION Rp. 117,366,000

BILL NO.4.2. ELECTRICAL INSTALLATION Rp. 434,482,000

BILL NO.4.3. ELECTRONIC INSTALLATION Rp. 632,912,000

BILL NO.4.4 HVAC INSTALLATION Rp. 634,298,000Rp.

BILL NO.4.5. COLD, WASTE WATER & VENT INSTALLTION Rp. 15,626,000Rp.

BILL N0.4.6 TESTING AND COMMISSIONING Rp. 200,000,000

Rp.

Rp.

Rp.

Rp.

TOTAL FINAL SUMMARY 2,034,684,000


Rp.
PPN 10% 203,468,400
Rp.
CARRIED TO GRAND SUMMARY 2,238,152,400

Rp.

741086191.xlsx Bill No. 4 MEP


TeamworX
4.1/1
Item BILL 4 MECHANICAL and 4.1. FIRE FIGHTING
Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

BUILDING 04 - QC LAB & OFFICE BUILDING

Supply and install the following fire protection equipment, fixed


fixed in position jointed with approved method including all
necessary accessories, all in accordance with the technical
specification and shown on drawings

A Head Sprinkler, Standart Response, K-5-6 (GF) 15 nr 120,000 1,800,000

B Head Sprinkler, Standart Response, K-5-6 (1st) 32 nr 120,000 3,840,000

Supply and install the following sprinklers pipes and fittings comply with ASTM
A 53 Grade A SCH 40 , fixed in position jointed with approved method including
all support, hanger, brecket painting and all necessary accessories all in
accordance to the technical specification dan drawings

C 80 mm diameter pipe 27 m 550,000 14,850,000

D 50 mm diameter pipe and fittings 173 m 350,000 60,550,000

E 32 mm diameter pipe and fittings 113 m 260,000 29,406,000

Extra over pipework

F Tee, 80 x 80 mm diameter 1 nr 450,000 450,000

G Tee, 80 x 50 mm diameter 8 nr 420,000 3,360,000

H Flange End, 80 mm diameter 1 nr 1,200,000 1,200,000

I Seismic Longitudinal brace 80 mm 1 nr 120,000 120,000

J Seismic Lateral brace 80 mm 2 nr 120,000 240,000

K Connection to existing pipe 80 mm diameter 1 nr 450,000 450,000

L Connection to existing pipe 50 mm diameter 1 nr 300,000 300,000

Valves and ancillaries, jointed to pipe works; all as described

M Test drain Valve 50 mm diameter 1 nr 600,000 600,000

N AAV c/w Ball valve 1 nr 200,000 200,000

4.1. FIRE FIGHTING INSTALLATION Rp. 117,366,000

741086191.xlsx | 4.1 FF Page 4 of 20


TeamworX
Carried to final Summary

741086191.xlsx | 4.1 FF Page 5 of 20


TeamworX
4.2/1

Item BILL 4 MECHANICAL and BILL NO.4.2. ELECTRICAL Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.2.1 DISTRIBUTION BOARDS (DB)

Supply and install the following Distribution board fix in position


includes circuit breakers, panel box,busbar, interconection wiring and
all necessary fixing accessories,as shown on dwg;

A PP - NEW AC BD-04 1 nr 55,000,000 55,000,000

Modification the following Distribution board fix in position includes


circuit breakers, panel box,busbar, interconection wiring and all
necessary fixing accessories,as shown on dwg;

B DP QC 1 nr 35,000,000 35,000,000

C P-PQC 1/3 1 nr 20,000,000 20,000,000

D SPL - OFF 1 nr 21,000,000 21,000,000

E SDP 2, Add. MCCB 3P 200 AT/250 AF 36 kA 1 nr 8,500,000 8,500,000

4.2.1DISTRIBUTION BOARDS (DB) Rp. 139,500,000


Carried to Summary at end of section 4.2

741086191.xlsx | 4.2 Elec. Page 6 of 20


TeamworX
4.2/2
Item BILL 4 MECHANICAL and BILL NO.4.2. ELECTRICAL Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.2.2 DISTRIBUTION CABLE

Supply and Install the following Distribution Cables run and fixed on
cable ladders / tray including gland, termination, erthing,supporting
and all necessary fixing accessories, acordan to the technical
specification and as shown on drawings

From SDP EXISTING

A NYY 4c x 120 mm2 + NYA 1 x 70 mm2 to DP - QC 62 m 600,000 37,200,000

From DP - QC

B NYY 4c x 25 mm2 + NYA16 mm2 to PP - NEW AC BD.04 50 m 450,000 22,500,000

From PP - NEW AC BD.04

C NYY 3 x 4 mm2 + PVC HI conduit 20 mm to IU GF 7 nr 400,000 2,800,000

D NYY 3 x 4 mm2 + PVC HI conduit 20 mm to IU 1st 11 nr 400,000 4,400,000

E NYY 3 x 6 mm2 PVC HI conduit 20 mm to IU 1st 1 nr 430,000 430,000

F NYY 3 x 4 mm2 + PVC HI conduit 20 mm to EF 1st 1 nr 430,000 430,000

4.2.2 DISTRIBUTION CABLE Rp. 67,760,000


Carried to Summary at end of section 4.2

741086191.xlsx | 4.2 Elec. Page 7 of 20


TeamworX
4.2./3
Item BILL 4 MECHANICAL and BILL NO.4.2. ELECTRICAL Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.2.3 LIGHTING & SMALL POWER INSTALLATION

Dismentling and re install the following light fittings, assemble , termination


including all associated tube and or lamps, fixed in position including
provision of hangers and fixing devices and accessories

GROUNDFLOOR
A FL LED 2 x 18 W 18 nr 2,700,000 48,600,000

B FL LED 2 x 18 W c/w battery 5 nr 2,200,000 11,000,000

C Surfaced Mounted LED 2 x 18 W 4 nr 1,800,000 7,200,000

D Downlight LED 12 W 3 nr 450,000 1,350,000

E Single switch 6 nr 120,000 720,000

F Double switch 1 nr 168,000 168,000

G General Socket outlet 1P 220V 21 nr 250,000 5,250,000

H Ceilling Socket outlet 1P 220V 2 nr 250,000 500,000

Supply and install the following light fittings, assemble , termination


including all associated tube and or lamps, fixed in position including
provision of hangers and fixing devices and accessories

1ST FLOOR
I FL LED 2 x 18 W 11 nr 2,700,000 29,700,000

J FL LED 2 x 18 W c/w battery 6 nr 2,200,000 13,200,000

K Downlight LED 12 W 13 nr 450,000 5,850,000

L Single switch 5 nr 120,000 600,000

M Double switch 1 nr 168,000 168,000

N General Socket outlet 1P 220V 21 nr 250,000 5,250,000

O Ceilling Socket outlet 1P 220V 1 nr 250,000 250,000

Supply and install the final sub circuit cabe to lighting, NYM 3 x 2,5 mm²
in PVC high impact conduit lay on tray including connection, termination kit
and all necessary accessories, all in acoding to the technical specification and
and shown on drawings.

P to lighting Points 30 nr 58,000 1,740,000

Q to power outlet 1Ph points 22 nr 68,000 1,496,000

4.2.3 LIGHTING & SMALL POWER INSTALLATION Rp. 133,042,000


Carried to Summary at end of section 4.2

741086191.xlsx | 4.2 Elec. Page 8 of 20


TeamworX
4.2./4
Item BILL 4 MECHANICAL and BILL NO.4.2. ELECTRICAL Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.2.4 CABLE TRAY and LADDER

Suplly and Install Galvanized cable ladder / tray; including elbows,


riser, hangers, brackets and support, as described in specification
all as described and as shown on dwg

1ST floor

A Cable Mesh Tray 200 x 50 mm 150 m 500,000 75,000,000

B Cable Duct 100 x 100 mm 50 m 350,000 17,500,000

C Cable underfloor Duct 100 x 50 mm 6 m 280,000 1,680,000

4.2.4 CABLE TRAY Rp. 94,180,000


Carried to Summary at end of section 4.2

741086191.xlsx | 4.2 Elec. Page 9 of 20


TeamworX
4.2./5
Item Qty Unit Rate Rupiahs
BILL NO.4. MEP WORKS SUMMARY ELECTRICAL
No.

SUMMARY

4.2.1 DISTRIBUTION BOARDS (DB) Rp. 139,500,000

4.2.2 DISTRIBUTION CABLE Rp. 67,760,000

4.2.3 LIGHTING & SMALL POWER INSTALLATION Rp. 133,042,000

4.2.4 CABLE TRAY Rp. 94,180,000

BILL 4.2 ELECTRICAL INSTALLATION Rp. 434,482,000


Carried to final Summary

741086191.xlsx | 4.2 Elec. Page 10 of 20


TeamworX
4.3/1
Item BILL 4 MECHANICAL and 4.3. ELECTRONIC Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.3.1 FIRE ALARM INSTALLATION

Supply and Install the following fire alarm equipment, fixed in


position jointed with approved method including all necessary fixing
accessories, all in accordance with the technical specification and
shown on the drawings.

A Modification TBFA LAB c/w Control module, monitor module 1 nr 80,000,000 80,000,000

B Addressable Photo Electric Smoke Detector 20 nr 9,700,000 194,000,000

C Smoke duct detector 2 nr 850,000 1,700,000

D Manual call point 2 nr 800,000 1,600,000

E Alarm Bell 2 nr 850,000 1,700,000

Supply and install the following final sub circuit cable in high impact conduit
lay on tray includng termination and all necessary accessories, all in
acordance to the technical specification and shown on drawings

F to detector 20 nr 650,000 13,000,000

G to manual call point 2 nr 250,000 500,000

H to alarm point 2 nr 250,000 500,000

I to smoke duct detector 2 nr 256,000 512,000

4.3.2 Telephone, data and CCTV

Dismentling and re install the following telephone, data, CCTV outlet


including cabling, conduit and all necessary accessories, all shown
on the drawing and site condition (All provisional qty)

J outlet telepone and cabling 25 nr 2,600,000 65,000,000

K outlet Data and cabling 25 nr 2,600,000 65,000,000

L access point and cabling 2 nr 2,600,000 5,200,000

M CCTV point and cabling 2 nr 2,600,000 5,200,000

to collection Rp. 433,912,000

741086191.xlsx | 4.3 Electro Page 11 of 20


TeamworX
4.3/2
Item BILL 4 MECHANICAL and 4.3. ELECTRONIC Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION INSTALLATION
No.

4.3.2 Telephone, data and CCTV

Dismentling and re install the following telephone, data, CCTV outlet


including cabling, conduit and all necessary accessories, all shown
on the drawing and site condition (All provisional qty)

A outlet telepone 10 nr 2,600,000 26,000,000

B outlet Data 10 nr 2,600,000 26,000,000

C access point 2 nr 2,600,000 5,200,000

D CCTV 2 nr 2,600,000 5,200,000

Supply and install the following final sub circuit cable in high impact conduit
lay on tray including termination and all necessary accessories, all in
accordance to the technical specification and shown on drawings

E to outlet tlp/data 20 nr 2,600,000 52,000,000

F to access point 2 nr 2,600,000 5,200,000

G to CCTV 2 nr 2,600,000 5,200,000

CABLE TRAY

Supply and Install Galvanized cable tray; including elbows,


riser, hangers, brackets and support, as described in specification
all as described and as shown on dwg

H Cable Mesh Tray 200 x 50 mm 114 m 450,000 51,300,000

I Cable Duct 100 x 100 mm 50 m 250,000 12,500,000

J Cable Duct 200 x 100 mm 32 m 325,000 10,400,000

to collection Rp. 199,000,000

Collection

Page 4.3/1 Rp. 433,912,000

Page 4.3/2 Rp. 199,000,000

BILL 4.3 ELECTRONICAL INSTALLATION Rp. 632,912,000


Carried to final Summary

741086191.xlsx | 4.3 Electro Page 12 of 20


TeamworX

741086191.xlsx | 4.3 Electro Page 13 of 20


TeamworX
4.4/1
Item BILL 4 MECHANICAL and
4.4 HVAC INSTALLATION Qty. Unit Rate Rupiahs
ELECTRICAL INSTALLATION
No.

4.4.1 EQUIPMENT

Supply and install the following equipment HVAC, including supports,


anti vibration springs, wiring and accessories all in accordance with
technical specification and shown on drawings.

A IU 4-1-01/02 - OU 4-1-01/02 (Wallmounted - Multisplit ) 1 nr 24,000,000 24,000,000


IU 01 cooling cap 2.7 kW
IU 02 cooling cap 2.3 kW

B IU 4-1-03/04 - OU 4-1-03/04 (Wallmounted - Multisplit ) 1 nr 18,000,000 18,000,000


IU 03 cooling cap 2.4 kW
IU 04 cooling cap 1.9 kW

C IU 4-1-05 - OU 4-1-05 ( Split Wallmounted ) 1 nr 15,000,000 15,000,000


Cooling Cap : 5.4 kW

D IU 4-1-06A - OU 4-1-06A ( Ceilling cassette ) 1 nr 18,000,000 18,000,000


Cooling Cap : 9.3 kW

E IU 4-1-06B/C - OU 4-1-06B/C ( Ceilling cassette ) 2 nr 18,000,000 36,000,000


Cooling Cap : 9.3 kW

F IU 4-1-07 - OU 4-1-07 ( Ceilling cassette ) 1 nr 17,000,000 17,000,000


Cooling Cap : 6.4 kW

G IU 4-1-08 - OU 4-1-08 ( Split Wallmounted ) 1 nr 8,000,000 8,000,000


Cooling Cap : 2.9 kW

H FCU 4-1-01 - CU 01 ( Duct Type ) 1 nr 18,000,000 18,000,000


Cooling Cap : 11.7 Kw

I FCU 4-1-02 - CU 02 ( Duct Type ) 1 nr 12,000,000 12,000,000


Cooling Cap : 5.0 Kw

J IU 4-1-09 - OU 4-1-09 ( Ceilling cassette ) 1 nr 18,000,000 18,000,000


Cooling Cap : 7.1 kW

K IU 4-1-010 - OU 4-1-010 ( Ceilling cassette ) 1 nr 12,000,000 12,000,000


Cooling Cap : 10 kW

L IU 4-1-011/012 - OU 4-1-011/012 (Wallmounted - Multisplit ) 1 nr 14,000,000 14,000,000


IU 011 cooling cap 1.5 kW
IU 012 cooling cap 3.6 kW

M IU 4-1-013/014 - OU 4-1-013/014 (Wallmounted - Multisplit ) 1 nr 18,000,000 18,000,000


IU 013 cooling cap 3.6 kW
IU 014 cooling cap 3.6 kW

N EF -4-1-01 cap : 600 cmh 1 nr 7,500,000 7,500,000

3.4.1 EQUIPMENT Rp. 235,500,000


Carried to Summary Bill 3.4

741086191.xlsx | 4.4 HVAC Page 14 of 20


TeamworX
4.4/2
Item BILL 3 MECHANICAL and
4.4 HVAC INSTALLATION Qty. Unit Rate Rupiahs
ELECTRICAL INSTALLATION
No.

4.4.2 REFRIGERANT AND DRAIN INSTALLATION

Supply and install of refrigerant pipe, Copper pipe class K


including brackets, support, joint, insulation and all accessories
technical specification and show on drawings.

A Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-01 11 m 850,000 9,350,000

B Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-02 8 m 850,000 6,800,000

C Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-03 10 m 850,000 8,500,000

D Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-04 9 m 850,000 7,650,000

E Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-05 9 m 850,000 7,650,000

F Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-06A 13 m 1,250,000 16,250,000

G Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-06B 20 m 1,250,000 25,000,000

H Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-06C 15 m 1,250,000 18,750,000

I Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-07 12 m 1,250,000 15,000,000

J Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-8 14 m 850,000 11,900,000

L Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-9 12 m 1,250,000 15,000,000

M Liquid dia 9.5 mm + gas dia 15.9mm IU 4-1-10 17 m 1,250,000 21,250,000

N Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-11 14 m 850,000 11,900,000

O Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-12 10 m 850,000 8,500,000

P Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-13 11 m 850,000 9,350,000

Q Liquid dia 6.4 mm + gas dia 9.5mm IU 4-1-14 14 m 850,000 11,900,000

R Liquid dia 9.5 mm + gas dia 15.9mm FCU 4-1-1 15 m 1,250,000 18,750,000

S Liquid dia 9.5 mm + gas dia 15.9mm FCU 4-1-2 13 m 1,250,000 16,250,000

Supply and install of drain pipe, PVC class AW including insulation


support and all accessories

T Drain Pipe dia 16 mm 64 m 37,000 2,368,000

U Drain Pipe dia 26 mm 69 m 46,000 3,174,000

V Drain Pipe dia 32 mm 16 m 56,000 896,000

3.4.2 REFRIGERANT & DRAIN PIPE Rp. 246,188,000


Carried to Summary Bill 3.4

741086191.xlsx | 4.4 HVAC Page 15 of 20


TeamworX
4.4/3
Item BILL 3 MECHANICAL and
4.4 HVAC INSTALLATION Qty. Unit Rate Rupiahs
ELECTRICAL INSTALLATION
No.

4.4.3 DUCT WORKS

Supply and install sheet metal duct, including insulation ,


fabrication, support, hanger and brecket all in accordance with
technical specification and show on drawings.

FCU 4-1-01
Suplly Duct

A Overall size, 500 x 200 mm 4 m 550,000 2,200,000

B Overall size, 450 x 200 mm 7 m 500,000 3,500,000

C Overall size, 300 x 200 mm 13 m 475,000 6,175,000

D Overall size, 200 x 200 mm 10 m 375,000 3,750,000

Fresh Duct

E Overall size, 400 x 200 mm 5 m 475,000 2,375,000

F Overall size, 350 x 200 mm 8 m 480,000 3,840,000

G Overall size, 300 x 200 mm 8 m 475,000 3,800,000

H Overall size, 200 x 200 mm 3 m 375,000 1,125,000

I Overall size, 200 x 150 mm 5 m 300,000 1,500,000

FCU 4-1-02

Suplly Duct

J Overall size, 200 x 200 mm 3 m 375,000 1,125,000

K Overall size, 150 x 100 mm 6 m 280,000 1,680,000

L Overall size, 100 x 100 mm 33 m 220,000 7,260,000

Fresh Air Duct

M Overall size, 150 mm dia 30 m 300,000 9,000,000

EF 4 - 1 - 01
Exhaust Air Duct

N Overall size, 200 x 200 2 m 375,000 750,000

O Overall size, 250 x 150 3 m 400,000 1,200,000

P Overall size, 150 x 150 3 m 280,000 840,000

Q Overall size, 100 x 100 2 m 220,000 440,000

to collection Rp. 50,560,000

741086191.xlsx | 4.4 HVAC Page 16 of 20


TeamworX
4.4/4
Item BILL 3 MECHANICAL and
4.4 HVAC INSTALLATION Qty. Unit Rate Rupiahs
ELECTRICAL INSTALLATION
No.

4.4.3 DUCT WORKS

DIFFUSER, GRILLE AND LOUVRE

A SAD 250 X 250 C/W VD 8 nr 2,500,000 20,000,000

B RAG 300 X 200 C/W VD 8 nr 3,000,000 24,000,000

C FAL 300 X 200 6 nr 3,000,000 18,000,000

D FAL 300 X 200 C/W VD 2 nr 3,000,000 6,000,000

E EAL 300 X 300 1 nr 3,250,000 3,250,000

F FAG 150 X 150 C/W VD 10 nr 2,000,000 20,000,000

G EAG 200 x 200 4 nr 2,200,000 8,800,000

H EAG 150 x 150 1 nr 2,000,000 2,000,000

to collection Rp. 102,050,000

Collection

Page 3.5/3 Rp. 50,560,000

Page 3.5/4 Rp. 102,050,000

4.4.3 DUCT WORKS Rp. 152,610,000


Carried to Summary Bill 4.3

741086191.xlsx | 4.4 HVAC Page 17 of 20


TeamworX
4.4/5
Item BILL 3 MECHANICAL and
4.4 HVAC INSTALLATION Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION
No.

SUMMARY HVAC INSTALLATION

EQUIPMENT Rp 235,500,000

REFRIGERANT AND DRAIN INSTALLATION Rp 246,188,000

DUCT WORKS Rp 152,610,000

3.4. HVAC INSTALLATION Rp. 634,298,000


Carried to final Summary

741086191.xlsx | 4.4 HVAC Page 18 of 20


TeamworX
3.5/1
Item BILL 4 MECHANICAL and 4.5. COLD, WASTE WATER
Qty Unit Rate Rupiahs
ELECTRICAL INSTALLATION & VENT INSTALLTION
No.

4.5.1 COLD WATER INSTALLATION

Supply and install the following cold water pipes and fittings, GIP medium
fixed in position jointed with approved method , including jacketing
insulation, brackets, hangers, support and all fixing accessories as
specified in the technical specification and shown on drawing.

A Conection to existing pipe, 25 mm diameter 1 nr 350,000 350,000

C 20 mm diameter pipe and fitting 5 m 300,000 1,500,000

D 15 mm diameter pipe and fitting 5 m 250,000 1,250,000

valve and ancillaries

E Foucet 2 nr 2,560,000 5,120,000

4.5.1 WASTE WATER & VENT INSTALLATION

Supply and install the following cold water pipes and fittings, PVC
fixed in position jointed with approved method , including jacketing
insulation, brackets, hangers, support and all fixing accessories as
specified in the technical specification and shown on drawing.

F Connection to exsisting pipe, 50 mm diameter 15 m 250,000 3,750,000

G 50 mm diameter pipe 10 m 320,000 3,200,000

Extra over pipework

H P Trap 50 mm diameter 2 nr 89,000 178,000

I Floor Drain, 50 mm diameter (SS 304) 1 nr 80,000 80,000

J Clean out, 50 mm diametr (SS 304) 1 nr 120,000 120,000

K Potable Grease Trap, SS 304 1 nr 78,000 78,000

4.5 COLD, WASTE WATER & VENT INSTALLTION Rp. 15,626,000


Carried to final Summary

741086191.xlsx | 4.5 CW-WW Page 19 of 20


TeamworX
3.6/1
Item BILL NO. 4.6 TESTING AND TESTING AND Qty Unit Rupiahs
COMMISIONING COMMISSIONING
No.

3.6 TESTING AND COMMISSIONING

A Allow for obtaining all necessary Government permits, 1 item 58,000,000 58,000,000
approvals and operating licences as specified

B Allow for providing identification,colour coding, labeling 1 item 25,000,000 25,000,000


and painting to MEP installation

C Allow for partial testing, pressure test for all pipes and purging 1 item 30,000,000 30,000,000

D Allow for testing, acceptance testing and commisioning 1 item 15,000,000 15,000,000

E Allow for training Employer's staff in operation and maintenence 1 item 60,000,000 60,000,000
procedures

F Allow for providing set of tools and service requirment as specified 1 item 12,000,000 12,000,000

4.6. TESTING AND COMMISIONING


Carried to Final Summary 200,000,000

741086191.xlsx | 4.6 Testcom Page 33 of 33