MICRO PROJECT REPORT
Submitted By
Awari Mayuri Rajendra.
Mr Vighe S.T.
S.R.E.I’s
SAMARTH POLYTECHNIC,BELHE.
TAL-JUNNAR, DIST-PUNE 412410
(2022– 2023)
MAHARASHTRA STATE BOARD OF
TECHNICAL EDUCATION,
MUMBAI S.R.E.I’s
SAMARTH POLYTECHNIC,
BELHE. TAL-JUNNAR, DIST-PUNE
412410
CERTIFICATE
This is to certify that
Awari Mayuri Rajendra.
This project is done as a semester project, as a part course titled “PREPARE RATE ANALYSIS OF
PAINTING WORK USING OBD , PLASTIC EMULSION OIL PAINT, LUSTER PAINT.”
We are really thankful to our course the Principal Prof. Kapile A.S and The HOD Prof. Kamble
V.P ,Civil Department, Samarth Polytechnic, Belhe for his invaluable guidance and assistance, without
which the accomplishment of the task would have never been possible.We also thanks Mr.Vighe sir For
giving this opportunity to explore into the real world and realize the interrelation without which a
Project can never progress.
In my present project I have chosen the topic “Prepare rate analysis of painting work using obd , plastic
emulsion oil paint, luster paint.”
I also thankful to parents, friend and all staff of Civil engineering department, for providing me relevant
information and Necessary clarifications and great support.
The cost of materials in rate analysis is calculated as combination of cost of material at origin, its
transportation costs, taxes. The rate of labour is based on skill of the labour, such as skilled labour, semi-skilled
and unskilled labour. The cost of materials and labours vary from place to place. Thus, the cost of each
construction work varies from place to place.
The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is
known as the task work or out turn of the labour.
INDEX
Sr. Title Page
No No.
.
1 Certificate 2.
2 Acknowledgement 3.
3 Abstract 4.
4 Index 5.
5 Introduction 6.
6 Conclusion 17.
7 References 18.
8 Teacher evolution sheet 19.
9 Microproject evolution sheet 20.
.
INTRODUCTION
In order to determine the rate of a particular item, the factors affecting the rate of that item are studied
carefully and then finally a rate is decided for that item. This process of determining the rates of an item is
termed as analysis of rates or rate analysis.
The cost of materials in rate analysis is calculated as combination of cost of material at origin, its
transportation costs, taxes. The rate of labour is based on skill of the labour, such as skilled labour, semi-skilled
and unskilled labour. The cost of materials and labours vary from place to place. Thus, the cost of each
construction work varies from place to place.
The capacity of doing work by an artisan or skilled labour in the form of quantity of work per day is
known as the task work or out turn of the labour.
The cost of any construction project is calculated based on each works associated with every construction
activity. Thus it is essential to calculate cost of each small works.
Chapter 2 :
METHODOLOGY
REFERANCE
TEXTBOOK
WIKIPEDIA
FROM NEWSPAPERS
WWW.CIVILWORKS.COM
CONCLUSION
By making these micro project, We know the All information about rate analysis of painting works
containing internal wall, outer wall.
And we understood how to calculate rate analysis of painting works using plastic emulsion, oil
paint ,luster paint.
Actual Procedure Followed
Activity Sign of
Sr.
Start Subject
No. Activity
Date Teacher
Details of Activity Finish date
Select a project name with the help of a subject
1 teacher. Teacher guide the how to make a project.
CourseTitle: EAC
Sub.Code: 22503
Title of the MicroProject:- “Prepare rate analysis of painting work using obd , plastic emulsion oil paint,
luster paint.”
Evaluation as per Suggested Rubric for Assessment of Micro Project
(Please tick in appropriate cell for each characteristic)
Charact Poo Average Go Excellent
e r od
No ristic to ( Marks 1-3 ) ( Marks 4 - 5 ) ( Marks 6 - 8 ) ( Marks 9-
be 10 )
assessed
1 Relevanc Relate to very few Related to some Take care of at Take care
e to the LOs Los least one CO of more
course than one
CO
……………………….……………………….……………………………………………
………………………………………………………………………………………………
……………………….…………………………………………………………………….
Dated Signature………………………………………………………………………………