You are on page 1of 2

CONCRETE

FOOTING
FOOTING LOCATION MIXTURE FACTOR LENGTH WIDTH THICK QUANTITY VOLUME CEMENT SAND GRAVEL
Mark Elevation Class Bags m m m unit 3 bags m³ m³
m
F-1 Elev. - 2.50m A 9.00 1.00 1.00 0.25 12.00 3.00 27.00 1.50 3.00
NOTES: 10% ALLOWANCE TOTAL: 3.00 27.00 1.50 3.00
10% ALLOWANCE : 2.70 0.15 0.30
ORDER: 30.00 2.00 4.00

BEAMS
TIE BEAM LOCATION MIXTURE FACTOR BASE DEPTH LENGTH QUANTITY VOLUME CEMENT SAND GRAVEL
Mark Elevation Class Bags m m m unit m
3 bags m³ m³
FTB-1a Elev. - 2.50m A 9.00 0.20 0.30 4.00 16.00 3.84 34.56 1.92 3.84
NOTES: 5% ALLOWANCE total 3.84 34.56 1.92 3.84
5% ALLOWANCE : 1.73 0.10 0.19
ORDER: 37.00 3.00 5.00

COLUMNS
MARK LOCATION MIXTURE FACTOR BASE DEPTH HEIGHT QTY/FLR VOLUME CEMENT SAND GRAVEL
Elevation Class Bags m m m m unit 3 bags m³ m³
m
C1 FTG TO CEILING A 9.00 0.35 0.45 1.50 3.00 12.00 8.51 76.55 4.25 8.51

NOTES: 5% ALLOWANCE REFER TO FOUNDATION PLAN FOR QUANTITIES ELEVATION HEIGHTS TOTAL: 8.51 76.55 4.25 8.51
5% ALLOWANCE: 3.83 0.21 0.43
ORDER: 81.00 5.00 9.00

COLUMNS
SLAB LOCATION MIXTURE FACTOR LENGTH WIDTH THICK QTY/FLR VOLUME CEMENT SAND GRAVEL
Elevation Class Bags m m m m unit 3 bags m³ m³
m
SLAB GF A 9.00 8.00 12.00 0.15 1.00 1.00 14.40 129.60 7.20 14.40
NOTES: 5% ALLOWANCE REFER TO FRAMING PLAN FOR ELEVATED HEIGHTS TOTAL: 14.40 129.60 7.20 14.40
5% ALLOWANCE: 6.48 0.36 0.72
ORDER: 137.00 8.00 16.00