Professional Documents
Culture Documents
Contract Number
XXXXXX
Project Number
xxxxxx
Project Title
xxxxxxxxxx
Document Title:
Generic Health, Safety &
Environment Plan
05.01.2020
08.03.2018
Prepared
By
HSE
Approved
By GM
Review
By
QHSEE
Approved
Date Rev Description By Client
STREAM J jL iJI
j , j jlj a fl , .JI
Document Title
Health, Safety & Environment
Plan
INDEX
1.
Purpose ......................................................................................................................
...................... 4
2.
Policy ..........................................................................................................................
...................... 4
2.1 Quality, Health, Safety & Environment
Policy........................................................................... 4
2.2 Alcohol & Drugs
Policy .................................................................................................................. 5
3. Abbreviation and
Definitions ....................................................................................................... 5
4.
Reference ...................................................................................................................
..................... 6
5. Project
Objective .......................................................................................................... 6
6. Project Organization and
Responsibilities .................................................................................. 6
6.1 Project
Manager.....................................................................................................................
........ 6
6.2 Construction/ Commissioning
Manager .................................................................................... 7
6.3 Discipline Engineer’s........................................................
............................................................. 7
6.4 HSE Engineers/
Officer.................................................................................................................... 8
6.5 Work
Supervisor...................................................................................................................
.......... 8
6.6 All
Personnel ...................................................................................................................
................ 8
7. HSE
Communication .........................................................................................................
............. 9
8. HSE Meeting Program
.................................................................................................................... 9
9. HSE
Induction/Training .....................................................................................................
............ 10
10. Tool Box Meeting
........................................................................................................................... 10
11. HSE
Procedure ..................................................................................................................
.............. 10
12. Work Permit
System ......................................................................................................................
11
13. Area
Barricading .................................................................................................................
............ 11
13.1 Type of
Barricade ....................................................................................................................
....... 12
13.1.1 Soft
Barricade ....................................................................................................................
............ 12
13.1.2 Solid
Barricade ....................................................................................................................
........... 13
13.1.3 Restricted Area
Barricade............................................................................................................. 13
14. PPE
Requirement ..............................................................................................................
............. 14
15. Emergency Preparedness and
Response ................................................................................... 14
15.1 Emergency coordinator Selection &
Training ............................................................................ 15
15.1.1 Selection Criteria for Emergency
Coordinator .......................................................................... 15
15.1.2 Emergency coordinator
duties ..................................................................................................... 15
15.1.3 Emergency Reporting
.................................................................................................................... 16
15.2 Emergency Preparedness
Facility ................................................................................................ 16
15.3 Emergency Response Procedure .......................... 17
15.3.1
Fire .............................................................................................................................
..................... 17
15.3.2 Personal
Injury/lllness ..............................................................................................................
... 17
15.3.3 Heat Stress Management
............................................................................................................. 18
15.3.4
Electrocution ..............................................................................................................
.................... 21
15.3.5 Road
Accident .....................................................................................................................
........... 22
15.3.6 Natural
Disaster ......................................................................................................................
....... 22
GIIZ/MR/GHSEP/01 Page 2 01 28 .S5ue Dace: 3x 3.2022
Document Title
STREAM Health, Safety & Environment
Plan
15.3.6.1
Earthquakes ...............................................................................................................
................. 22
15.4
Evacuation .................................................................................................................
..................... 23
15.4.1 Evacuation Rout Assignments and Assembly
Points ............................................................... 23
15.4.2 Evacuation
Procedure ..................................................................................................................
23
15.4.3 Post Evacuation
Personnel ......................................................................................................... 23
15.4.4 Critical
Operations .................................................................................................................
....... 23
15.4.5 Rescue and Medical Duties of
Employees ................................................................................. 23
15.4.6 Housekeeping
Task ....................................................................................................................... 24
15.5 Simulation
Exercise ......................................................................................................................
. 24
15.6
Investigation ..............................................................................................................
..................... 24
15.7 Client Emergency
Number ........................................................................................................... 24
15.8 Assembly
Point ...........................................................................................................................
.... 24
15.9 Emergency Evacuation
Drill ......................................................................................................... 25
16. Equipment
Inspection...................................................................................................................
. 25
17. Environment
Management ..........................................................................................................
25
17.1 Waste Management
...................................................................................................................... 26
18. Welfare Facility
Provision ............................................................................................................
26
19. Management & Supervision of Sub Contractors and
Supplier ............................................... 27
20. Accident/ Incident
Management................................................................................................. 28
21. Audits and
Inspections...................................... ...........................................................................
. 29
22. Performance Monitoring and
Measurement ............................................................................ 29
23. Hazard Identification, Risk Assessment and
Control ................................................................ 29
24.
Attachments ..............................................................................................................
...................... 30
Document Title
Health, Safety & Environment
Plan
1. PURPOSE
The prime purpose of this plan is to provide a comprehensive document, which
describes the
implementation of responsibilities, standards, and correct working practices for
the management
of the safety, health and environmental risks associated with (Project Name
/Title)
This project shall execute in complete compliance with this plan and as per the
guidelines
mentioned in the procedure attached. As an evidence of compliance, all relevant
checklists,
formats, safety reports shall be visible and made available upon client request.
The plan makes use of Qatar laws, QCS 2014, HSE regulations and existing SIE
Working Procedures.
2. POLICY
It is the policy of the SIE team to develop a safe and healthy working
environment, not only to
comply with health and safety legislation, but also to act responsibly in preventing
injury, ill health,
damage, losses and environmental pollutions arising from its activities during the
all phases of the
project.
2.1 Quality, Health, Safety & Environment Policy
We STREAM Industrial & Engineering (SIE) are committed to:
Understand and meeting the highest standard of Quality, Health, Safety and
Environment,
incorporating the principles of sustainable development and follows all QHSE
rules and
regulations conducting all business activities.
Recognizes and accepts its responsibility as an employer providing a safe, healthy
workplace
and work environment for its employees and interested parties that may be
affected by our
work.
We are committed to environmental leadership in all of our business activities.
We as the
employer undertake to comply with all statutory health and safety requirements.
Adopting Management system in line with the requirements of ISO 9001:2015,
ISO
14001:2015 and ISO 45001:2018 Standards.
The satisfaction of its customers, the protection of the employees and the
development of the
communities where it has its operations are the main organizational goals.
We provide policies to provide a safe, healthful workplace, protecting the
environment,
conserving energy and natural resources.
Quality, Health and Safety management and Risk Assessment fundamentals are
integrated in
all business processes. Management is responsible and accountable for achieving
excellence in
Quality, Health and Safety performance for successful business results.
SIE is committed to training all its employees in the appropriate use of its Quality,
Health and
Safety management systems, strengthening its management through updating of
professional
and managerial skills, emphasizing employee evaluation and motivation, and
complying with
the ethical principles established in its Code of Conduct.
Document Title
Health, Safety & Environment
Plan
Client Logo
(WuMTui fojfltiffj
Management and employees will lead by example in all QHSE related issues.
Management
reviews the QHSE policy during management review meetings to determine the
policy's
continuing suitability for our organization.
We ensure that our QHSE policy is communicated and understood at all levels of
the
organization through documented training, regular communication, and
reinforcement during
annual employee performance reviews.
Establish and strive to achieve measurable objectives to demonstrate the
commitment to
continually improve the performance of management system;
Document Title
Health, Safety & Environment Client Logo
Plan
IMS: Integrated Management System
GHSEP: Generic Health, Safety, Environment Plan
4. REFERENCE
SIE is fully committed in ensuring health & safety of all site personnel & in the
preservation of
environment & natural resources. For this project, SIE shall ensure compliance to
state of Qatar
and client specifications, guidelines, permit to work system.
SIE shall adhere to the following documents of client & Qatar National Standards:
• Civil Defense Dept. (Qatar) - Fire Safety Handbook - Part 1
• Civil Defense Dept. (Qatar) - Fire Safety Handbook - Part 2
• QCS 2014
• Qatar Labor Law
• Qatar Ministry of Environment
5. PROJECT OBJECTIVES
SIE project objectives are to provide safe and healthy working conditions for all
employees and the
surrounding community and to maintain the highest safety standards in relation
to safe systems of
work and equipment operations.
• The Senior Management supports the formal HSE management of the project;
• There are sufficient managerial resources to support the Project HSE processes;
• There are sufficient specialist resources to co-ordinate the implementation of
the HSE Plan;
• All members of Project Management have their clearly defined responsibilities
in terms of
the implementation of the HSE Plan; and
• Ail workers play an active role in the HSE process.
Specifically, he shall:
STREAM jLjJJI
tiwisiiwl i injjinetiing . ..... j
Document Title
Health, Safety & Environment Client Logo
Plan
• Be familiar with and demonstrate his commitment to implement Company
QHSE Policy and
promote a continual improvement in HSE performance.
• Ensure that all personnel for whom he is responsible are aware of this Policy
and
implement relevant procedures as per requirement
• Manage the effective implementation of the Project HSE Plan and ensure
corrective action
is taken where found necessary.
• Ensure that Risk Assessments carried out at the earliest practicable opportunity.
• Ensure that all potential incidents involving injury to persons, damage to
property or the
environment are thoroughly considered to identify causes and propose mitigation
measures;
• Monitor HSE performance of the personnel and activities under his control.
• Establish a consultation and communication system with all employees and
subcontractors.
• Ensure sufficient induction training for all employees and workers before
commencement
of work at site and subsequently for new inductees.
• Formulate a safety committee.
• Arrange and chair safety meetings.
6.2 Construction/Commissioning Manager
He shall be report to Project Manager
He shall be responsible for direct control, Plan and schedule of construction
activities and
meeting the scheduled dates for completion of job.
Responsible to advise necessary inputs during preparation of micro schedule by
the planning
department,
Responsible for finalize Construction Mobilization Plan and temporary facilities
requirements &
allocation of work force and equipment to meet the project schedules.
Responsible to monitor the performance of the project from a construction
perspective &
complete the job on or before schedule without compromising the project quality
and safety
requirements
6.3 Discipline Engineer's
The Discipline Engineer's is responsible for ensuring that the activities under the
contractual work
scope completed in accordance with the relevant approved criteria, standards
and procedures.
Specifically, he shall:
• Ensure that work under his control is conducted with due regard to safety
considerations.
• Be familiar with the Company SIE IMS policy and the Site HSE Plan.
• Liaise and cooperate with HSE Engineer and ensure that defects brought to
attention
corrected.
• Establish and maintain proper communication with all workers with regard to
safety
aspects.
• Provide proper supervision for the work.
6.4 HSE Engineer / Officer
Accountable to the Project Manager for fulfilling the duties assigned to him in the
QHSE policy
and ensure implementation of HSE plan. HSE Engineer/Officer is also responsible
to the Project
S1E/MR/GHSEP/C] Pdge 7 Ji' 23 i ;,.,ueJdLa 31 3 2022
k Document Title
STREAM f jL_ _JI Health, Safety & Environment Client Logo
Enjineei
STREAM (
: Wifttriii 4 L'ljfleair:? ’
'l1
b j i fl i uiH
Document Title
Health, Safety & Environment Client Logo
Plan
• Maintain the workplace properly with good housekeeping, free of hazards.
• Report any accident/incident or near miss to his immediate supervisor or HSE
representative.
7 HSE COMMUNICATION
Effective communication is essential for the development of a HSE culture within
the organisation,
as well as to ensure that the objectives, HSE performance requirements,
responsibilities are clearly
understood. This be implemented through:
• Dissemination of SIE QHSE Policy to all personnel, and instruction on its use;
• Distribution of Memos, periodic health and safety briefing notes, Safety alerts
etc on a
regular basis;
• Promoting open communications between project management and workforce
on safety
matters.
• Ensuring health and safety issues are included on the top of the agenda at
management
meetings;
• Promoting hygiene, health and safety awareness by disseminating information
such as
accident and injury statistics, and articles which have a direct impact upon the
health,
hygiene and safety of the workforce; sharing HSE experience and best practices;
• On the job instructions (Tool Box meeting);
• Effective signs indicating hazards and escape routes;
• Management visits to site.
8 HSE MEETING PROGRAM
Monthly HSE Meetings Programme convened to ensure that health, safety and
environmental
issues are formally presented and discussed collectively at all construction sites,
which be
convened and chaired by the Project Manager. All safety committee members
shall also attend the
meetings. SIE will report all types of HSE Meetings to client & the client
representative be invited
for the meeting.
Monthly Project HSE Review Meeting with client will be carry out every first
Sunday of the Month
if required.
9 HSE INDUCTION/TRAINING
Immediately after employment of all new personnel or assignment of personnel
to a project,
personnel will attend an HSE Induction training organised by SIE or Client.
SIE shall keep records showing that each employee has attended an HSE induction
session.
As required, all project personnel shall undergo client HSE induction before site
deployment.
Good safety awareness training is important for all employees, especially for
those learning a new
trade. It is also essential to keep Supervisors and skilled Operators up-to-date
with current safety
technology and practices. In addition to Safety Induction, SIE will ensure
specialised training to all
necessary employees during the course of project as per Client training
requirements.
SIE shall ensure that all personnel involved in high-risk activities such as confined
space entry,
work at height, heavy lifting, excavation, welding/grinding, heavy vehicles driving,
electrical work,
Sii'/faln/Ci'iSi-i-VC 1 ,toue Caie i L 3
STREAM
Kioiinl x
' jLuUl
Document Title
Health, Safety & Environment
Plan
chemical handling and scaffolding are trained and competent. The applicable
project HSE Training
matrix is given as Attachment no: 2
11 HSE PROCEDURE
A set of HSE Procedures are developed for the construction activities associated
with installation
operations and HSE personnel shall be employed for the project who will ensure
the relevant
implementation.
The HSE Construction Procedures represent good safe working practices to
implement at site level
by the supervisors and workforce. They formulated in a way that may be also
used as training tools
for the personnel and as reference for Tool Box meetings and Job Safety Analysis.
The HSE Procedures applies to all site activities directly performed or supervised
by SIE Project
Management.
The HSE procedures relevant to the project operations identified and listed
below:
1. Hazard identification and risk assessment SIE/MR/HSEP/01
2. Accident - Incident Investigation and reporting SIE/MR/HSEP/07
3. Waste management SIE/MR/OCP/14
4. Personal Protective Equipment (PPE) SIE/MR/OCP/07
5. Working at heights SIE/MR/OCP/12
6. Electricity SIE/MR/OCP/03
7. Safety Audit Procedure SIE/MR/IMSP/03
8. Emergency Preparedness & Response SIE/MR/HSEP/03
9. Confined Space SIE/MR/OCP/05
Document Title
Health, Safety & Environment
Plan
STREAM
Indwtiul i. Engineering
Client Logo
When required, application for Work Permit shall made in advance (as per Client
requirement)
before the commencement of the work activity.
Any activity will not start until all conditions on work permit a completely met
including approved
Method Statement & JSA.
Ensure all key Personnel, Supervisor & other relevant personnel will undergo
Client PTW training.
13 AREA BARRICADING
To protect personnel by preventing or controlling access to hazards / high-risk
work areas by the
installation and maintenance of barricades. This practice shall apply for all visitor
and employees
at site.
Document Title
Health, Safety & Environment
Plan
Caution
Barricade
Tape
’ger
D/1
high
Restricted
Access
Barricade
Tape
Restricted
Access
Electrical
Work
Barricade
Tape
This restricted access tape is to be use to
barricade off and restrict access to
electrical hazards. This tape commonly
used for switchboard maintenance. Only
the work party and personnel authorized
by the person in charge of the barricaded
area (as indicated on the signage) are
permitted to access through the
barricade. (Electricity Procedure)
Restricted
Access
High
Voltage
Danger
Barricade
Tape
Document Title
Health, Safety & Environment
Plan
14 PPE REQUIREMENTS
PPE includes protective clothing with high visibility, head protection, eye
protection and foot
protection.
PPE is considered as only as a last line of defence and as a means of supporting
other, more
effective controls. PPE is supplied free of charge to those identified as at risk.
Document Title
Health, Safety & Environment
Plan
Additional job specific PPE shall enforce based on the Job Hazard Analysis.
15 EMERGENCY PREPAREDNESS AND RESPONSE
SIE shall fully comply with Client emergency procedure while working at site and
shall ensure
that all its employees are fully aware of the procedure through induction and
training.
However, SIE shall have emergency response plan, procedures and arrangements,
specific to the
location and activities carried out, which shall be applied when working in remote
area where
Client monitoring is not practicable.
The objective of the Emergency Procedures is to ensure that any emergency
affecting the place
of operational activities dealt with an efficient and professional manner so that
the safety of
personnel is not compromise in any way. The environmental pollution risks are
prevent or
minimised and that all other losses, which may arise from emergencies,
prevented or minimised.
A site specified emergency response plan would be developed in line with Client
procedures, to
detail the arrangements and measures, which specify the actions to take in the
event of an
emergency that may occur during the course of operational activities.
Each Section of the Specific Emergency Response Plan provides instructions and
relevant
checklists, which should be utilised to assist in incident management. Emergency
plans cover
most operations, i.e.
• Fire
• Personal Jnjuries/lllness
• Heat Stress
• Electrocution
• Road Accidents
• Natural Calamities (Earth Quake, Tornado, Cyclone, Water Storm) were exposed
• Structural/equipment failure.
• Medical emergency.
• Spillage/Leakage
Reference: emergency preparedness and response (sie/mr/hsep/03)
Document Title
• SIE shall provide the following emergency preparedness facilities at the project
site and
office.
15 23
STREAM f |LJJI
■ |i.i a:
...il
Document Title
Health, Safety & Environment Client Logo
Plan
• Sufficient number of fire extinguisher shall be position throughout the project
site
• Quick and efficient transport and communication facility shall be available.
• Smoking will be restricted throughout the premises except in designated areas.
• Sufficient number of project personnel shall be train for firefighting and first aid.
• Sufficient quantity of first aid kit shall be available.
• All key personnel shall be provided with communication means like land phone/
mobile
Phone to ease the communication during emergency.
• Periodic emergency response drill shall be conduct.
Concerned A map with the following information be found and posted at strategic
locations at the
facility
STREAM L| i
i,r > 4- P) J- *1 4
Client Logo
Treatment:
• Immediately call for emergency medical assistance
• Move the person to a cool and shady area. Do not leave the person alone
• Cool the person rapidly with running water, cold compresses and/or rapid
• fanning
• Provide cool water if they are alert. Avoid caffeine and alcohol.
• If the person is unconscious, do not give them water.
• Continue to cool their body temperature until medical assistance arrives and
they can be
taken to a medical facility for further cooling and monitoring of body temperature
and
functions.
Heat Exhaustion
Heat exhaustion is a condition caused by excessive fluid loss due to sweating,
resulting in the
depletion of body fluid volume, which creates an imbalance of the electrolytes in
the body.
A Document Title
STREAM f jLJJI Health, Safety & Environment
!>bdusrnal & Lngineenng 4 : il Plan
Symptoms:
• Heavy sweating
• Paleness of skin. Skin may be cool and moist
• Muscle cramps
• Tiredness
• Weakness. Pulse rate may be fast but weak. Breathing may be fast but shallow
• Dizziness
• Headache
• Nausea or vomiting
• Fainting
Treatment:
• Immediately call for emergency medical assistance
• Move the worker suffering from heat exhaustion to a cool and shady area. Do
not leave the
person alone.
• Cool the person rapidly with running water, cold compresses and/or rapid
fanning, if
possible.
• Provide cool drinking water, or electrolyte/ ion replacement drinks, if the
patient is awake.
Avoid caffeine and alcohol.
• Remove extra clothing when necessary and continue to coo their body
temperature until
medical assistance arrives.
Heat Craps
Heat cramps are painful spasms of the muscles generally thought to be cause by
an imbalance of
electrolytes (e.g., essential minerals, such as sodium, potassium, calcium and
magnesium) in the
body. This may occur when a person carries out strenuous physical activity, drinks
large quantities
of water, but fails to replace salts /electrolytes lost though sweating.
Cramps can occur during or after working hours and may be relieve by drinking
saline/ electrolyte
solutions. In more serious cases and if determined necessary by a doctor, a saline
solution should
be administered intravenously for quicker relief.
Symptoms:
• Muscle pains or spasm usually in the abdomen, arms or legs.
Treatment:
• Immediately call for emergency medical assistance
• Stop all activity and sit quietly in a cool and shady area. Inform nearby workers
of the
problems encountered.
• Drink clear juice or a liquid containing salt (e.g., electrolyte / ion replacement
drinks).
• Do not return to strenuous activity for at least for few hours after the cramps
subside. It
should be noted that further exertion might lead to heat exhaustion and/or heat
stroke.
• Seek medical attention if heat cramps do not subside within 1 hour.
SiE/MR/GHSii?/01 Page 18 ol 28 sue Date: 31 8 2022
Document Title
Health, Safety & Environment
Plan
Heat Rash
Heat rash, also known as prickly heat, may occur in hot and humid environments
where sweat is
not easily removed from the surface of the skin by evaporation.
ig.; 19 ii 28
STREAM f jL ill
i 1 / 'l.'l 1 1\, j id
Document Title
Health, Safety & Environment
Plan
• Control to be implemented
Buddy System
The buddy system is a procedure in which two people, the buddy, operate
together as a single unit
so that they are able to monitor and help each other. This system to be also use
as a part of the
training to the newcomer to the project. That is the less experienced buddy
become familiar with
experienced buddy. When working in areas of potential heat stress, consideration
shall be given to
work in pairs so that one person can observe the early symptoms of heat stress
on the other and
can assist him in taking necessary control measures.
Clothing and PPE
Clothing that are light in color, with loose fittings, lightweight shall be advice to all
SIE employees.
All workers to reduce exposure to direct sunlight wear full sleeve coverall. All
employees shall
wear mandatory PPE as per Client requirement and tinted safety goggles are
recommend
protecting eyes from harm.
Work Scheduling
Where ever possible SIE shall follow the approach of scheduling heavy, physical
jobs at coolest
part of the day. E.g., Early start of work
Work Rest Intervals
Breaks that are more frequent shall be plan by SIE supervisors for more heavy
physical work on
hot days.
Emergency
In the event of any heat related illness the victim shall be immediately taken to
the to the Client
medical Centre/ or nearest hospital by using the vehicle which is available as
standby or call
ambulance. All the heat related incidents will be report to Client and SIE
management as per the
accident incident investigation procedure and will be investigated thoroughly to
prevent
recurrence.
15.3.4 Electrocution
• Switch off the main supply.
• Raise an alarm
• Inform to the Section In-charge / Security/ On-site safety officer.
Document Title
Health, Safety & Environment
Plan
• In case your co passengers are injured, severely call the emergency numbers
and wait for
the paramedics to arrive.
15.3.6 Natural Disasters
In the event that a natural disaster occurs when the facility is not open for work,
employees will be
asked to call the emergency coordinator's cell phone for further instruction. If the
emergency
coordinator anticipates a large volume of calls, he/she will change their cell phone
message to
provide instruction for employees on the decision to report to work or stay home.
Listed are the
procedures to be follow depending on the type of natural disaster.
15.3.6.1 Earthquakes
• If an earthquake strikes, all employees working indoors are to seek immediate
shelter
underneath a reasonable covering that can withstand falling objects in the area
they
occupy such as desks and sturdy workbenches.
• Only if employees are next to exits or it is safe to do so should they exit the
building and
stand free of electrical lines, gas lines and/or possible falling objects.
• The employees should remain under the shelter until the shaking stops or until
it is safe to
move to the assigned evacuation area.
• If no shelter is available, employees should evacuate as quickly as possible,
being cautious
to avoid racks or electrical boxes.
• Once the shaking stops, supervisors are to assemble all employees in a safe area
to
perform a headcount.
• Prior to allowing any employees to return to work, an inspection of the facility
will occur to
verify structure integrity and the possibility of electrical, water, or gas line
damage.
• When any portion of the structure integrity or damaged is uncertain, the
supervisor or
designee will contact local responders to conduct a more thorough inspection.
• Only when the facility has been determined as safe to re-enter, will employees
be allowed
to return to work
15.4 Evacuations
15.4.1 Evacuation Route Assignments and Assembly Points
A site map showing evacuation routes and assembly points will found in the back
of this Plan and
post at strategic locations at the facility. The assembly points chosen will
accommodate all persons
being evacuate from the workplace and be out of the path of incoming
emergency vehicles.
15.4.2 Evacuation Procedure
When an evacuation of all or part of the workplace is announced, all personnel
are to follow the
evacuation routes to the evacuation assembly points. Personnel are not to
congregate around the
exit or go anywhere other than the evacuation assembly point. At the evacuation
assembly point,
all personnel are expected to remain calm and quiet in order to hear the roll call
and any further
rage 21 of 28 issue Dace: J 1 .3,2022
nvironment
Plan
instructions. Failure to report directly to the evacuation assembly point could
possibly endanger
the lives of the emergency responders who may sent into the workplace to look
for missing
employees.
15.4.3 Post Evacuation Personnel Accounting
• The emergency coordinator and others as assigned will be responsible for Post
evacuation
personnel accounting. The goal of post-evacuation personnel accounting is to
account for
all employees, contractors, and visitors during an emergency. A master employee
rooster
and sign-in/out logs for contractors and visitors will used to assist in this
determination.
• At the evacuation assembly, point the emergency coordinator will determine
which
personnel not account are. Personnel are not considered missing until it can be
verified
that the person actually reported to work that day and was at
• The facility at the time of the emergency.
• Emergency responders will be notified of people believed to be missing and
their
approximate location in the workplace.
15.4.4 Critical Operations
• Depending on the type and/or extent of the emergency, some processes and/or
operations
may require employees to remain in the workplace after an evacuation is
announce to
orderly and safely shut these operations down. Critical operations that may
require
shutdown can include; Water Mains; Electrical Mains, specialized machinery (as
applicable).
• This facility will identify any critical operations as applicable; and assign and
train personnel
on the proper shutdown procedure.
15.4.5 Rescue and Medical Duties of Employees
• It is the policy of SIE that local emergency responders handle all Emergency
Situations
except for incipient firefighting or minor First Aid injuries.
Document Title
STREAM jL_uJI Health, Safety & Environment
■anul A tnjnt-enriij Plan
• The Emergency Response Procedure shall be review at least once in a year as
minimum.
Working in Client operation area Client Assembly point shall be identified for
assembling in
emergencies.
15.9 Emergency Evacuation Drill
Emergency evacuation drills shall be conducted within the project members to
verify the
effectiveness of emergency preparedness and to monitor readiness of the
members to respond
to a real emergency. SIE shall conduct this drill once in every six months or in a
year. The
outcome of the drill shall be documented in Mock drill report form as given in
Attachment No: 4
and recorded.
16 EQUIPMENT INSPECTION
SIE is strongly committed to ensure the safe condition of the equipment to used
in the worksite
and those maintained for emergency preparedness. It applies to all equipment
used by SIE and
covers safe handling, maintenance, storage and use.
All equipment shall use only after Client Safety inspection and approval.
Following is the list of equipment, tools, instruments for which the requirements
apply but not
limited to,
Fire extinguisher
First aid kit
PPE
o
o
Pd&t? 23 J I* 23
Document Title
STREAM f
j d i i ll
Health, Safety & Environment
Plan
Client Logo
o Scaffolding
o Hand/power tools
o Vehicles
o Lifting tools and tackles (Slings, Shackles, belts, wire ropes etc)
The inspection and reporting system for the project is primarily design to ensure
that all tools
and equipment is maintain in safe condition and to minimise any down time. All
the tools and
equipment used by SIE shall be inspect by a competent person against the Client
requirement
before put into operation
17 ENVIRONMENT MANAGEMENT
SIE confirms its commitment in performing the Project scope of works with the
least possible
impact on the environment and in absolute compliance with all Client
requirements,
SIE shall pay due regard to the environment by acting to minimize any impact,
which may arise
from construction activities. This includes assessing the types of materials and
substances that
are currently in use and substituting them with more environmentally friendly
materials.
Environmental objectives are set and improvement programs are running, at SIE
corporate level
as a part of ISO 14001 compliance, which includes reduction in fuel, electricity and
paper
consumption.
17.1 Waste Management
SIE shall ensure that all the waste produced as result of SIE operations at site
identified as
hazardous and domestic wastes and shall be handled and disposed of in
accordance with the
Client Specifications for Waste Management and all related Qatar regulatory
standards related
to waste management
Ref: SIE/MR/OCP/14
• QCS 2014 Section 11: Health and Safety Part 2.1.01: Safety, Health and
Environment
Management System
• QCS 2014 Section 01: General Part 10: Occupational Health and Safety
SIE shall always comply with the Client waste management procedure.
2 24 28
Document Title
Health, Safety & Environment
Plan
• Water dispensers with potable drinking water and disposable cups should be
provided with
workers to prevent from dehydration.
• Rest facilities including facilities for preparing and eating are likewise provided
to workers.
• Provide designated smoking areas outside the work area/project site.
• Symptoms if illness shall be reported to the project/site engineer in order to
seek medical
attention, otherwise, the worker will ask to take the leave to prevent
contaminating other
workers.
The Construction Subcontractors will prepare and issue a project HS&E plan that
addresses all
necessary safety precautions related to, or arising out of the performance of the
work, and
which will ensure the protection of all employed personnel, third parties, the
general public,
plant, equipment, property and the environment. The plan must be submitted to
the SIE Project
Manager for approval prior to commencement of the work.
The methods employed by SIE to manage Safe Systems of Work. The purpose and
scope are to:
• Indicate responsibilities for the management of the Construction activities.
• Ensure project management assess and manage HSE performance of SIE
subcontractors.
• Ensure hazards to the health and safety of personnel, the public, the
environment and
project assets have been identified, assessed and controlled through formal
procedures
and planning methods.
• An in-depth safety assessment by means regular site visits; review of HSE issues
& by
having safety meetings.
jil/ Mil/ xjHSl J" / j. J 2S Ji 28 L-dlt 1 J J 3
Document Title
Health, Safety & Environment
Plan
Client Logo
teuwuiitnjiwwx
Document Title
Health, Safety & Environment
Plan
STREAM
Muslriai J, Engineering
Client Logo
24 ATTACHMENTS
Control of attachments:
The attachments of this document shall be update whenever required during the
course of the
project, and shall be submitted for Client approval; however, this HSE plan shall
be of the same
revision status.