Professional Documents
Culture Documents
net/publication/236029962
CITATIONS READS
0 116
2 authors, including:
Paul Reynolds
University of Exeter
170 PUBLICATIONS 2,206 CITATIONS
SEE PROFILE
All content following this page was uploaded by Paul Reynolds on 18 January 2014.
Superstructure
‘A stadium of two halves’
The asymmetric bowl form of the stadium effectively results in
‘a stadium of two halves’, with single tier terracing to the
narrow plan north, south and east stands, and two tier terrac-
ing to the deep plan west stand. Unlike other stadia, the junc-
tion between the single tier (north and south) stands and the
two tier (west) stand is created by a steady increase in roof level,
as opposed to a sudden vertical step. Each half of the stadium
is made up from 36 steel frames, each one of which is struc-
turally different.
The difference between the single tier and two tier stands
was further emphasised by Birse’s decision (essentially due to
the programme) to employ Watson Steel to fabricate the two-
concourse (which has been described as ‘Cathedral like’) at first Fig 4: Isometric view tier west stand frame, whilst Wescol fabricated the three,
floor level, thereby freeing up commercially valuable space at of typical A-frame single ties stands. To simplify the situation both practically
ground floor level. Further space has been freed up by locating support to roof of and contractually, the junctions of the north and south stands
the four stair towers that serve the upper floors of the West West stand with the west stand were made as structurally independent
stand outside the footprint of the stadium. This maximises the as possible.
space available for public amenities and catering facilities, as In total, approximately 3500t of structural steelwork were
well as enabling fans to walk fully around the stadium at events used in the construction of the stadium.
where segregation is not necessary (such as pop concerts).
Orientation of the stadium
Structural concept/design The orientation of the stadium shown on the original concept
Ground conditions drawings was rotated through 180° at scheme design stage so
The ground conditions are heavily influenced by the site’s prox- that the prevailing winds from the southwest acted on the rear
imity to the Humber estuary; it is underlain by estuarine allu- elevation of the main west stand. This minimised the wind
vial drift deposits (comprising inter-bedded granular and uplift forces on the west stand roof, where the roof overhang is
cohesive strata) which in turn are underlain by the chalk the most onerous.
bedrock at depths of between 13 and 16.5m.
The uniformity and stiffness of the alluvial drift deposits Setting out and geometry
varies considerably. A relatively thin ‘stiff crust’ of clay close to For reasons described above, the principal structural elements,
ground level is typically underlain by soft to very soft clays. including the terracing, the steel frame, the roofs and the
Having been a public park since 1883, the site is essentially cladding are all set out to a complex arrangement of plan
a true green-field site. Consequently, made ground and contam- curves, with different radii and setting out points defining each
ination were not significant issues here. element.
To assist construction therefore, easting and northing coor-
Foundations dinates were calculated for critical elements, some of which
The combination of the significant foundation loads and the were expressed as ‘global positioning system’ (GPS) coordi-
aforementioned soft alluvial drift deposits immediately nates.
suggested a piled foundation solution, with suspended precast
units spanning up to 7.5m onto in situ reinforced concrete Fig 5: Layout for Superstructure to the north, south and east stands
groundbeams. These in turn span onto pile caps. 850 CFA piles putting A-frames The superstructure to the north, south and east stands is rela-
with a diameter of 450mm and an average length of 16.3m together at ground tively straightforward, comprising steel frames at 7.5m centres,
were installed to the stadium, giving a total length of piles level (to rear of West supporting single tier terracing that is accessed from the
equal to almost 14km. stand) suspended floor at lower concourse level.
Indeed, the superstructure to the lower concourse areas
consists of 130mm thick composite slabs (incorporating trape-
zoidal profile metal decking) spanning up to 3.0m onto compos-
ite mild steel secondary beams. In turn, these span onto
primary composite steel beams at 7.5m centres, which are typi-
cally supported by UC section columns. The shallow depth of the
composite slab and beam construction ensured that integration
of services was not a significant issue.
Meanwhile, the superstructure to the terracing areas
consists of L-shaped precast concrete terracing units, spanning
up to 7.9m onto mild steel raker beams, which in turn span onto
UC section columns. The structure to vomitories and disabled
access decks also utilises precast concrete elements.
The roof is made up of 1350mm deep cellular steel beams
which are supported on two columns, one at the rear of the
terracing and one along the external perimeter. The cantilever
portion of the roof beams exceeds 25m at its maximum, with a
strip of polycarbonate sheeting to the leading edges of both the
north and south stands.
At the north-east and south-east corners, aesthetically pleas-
ing ‘wishbone’ floodlights in tubular steelwork sit onto the cellu-
lar roof beams, with cable stays providing lateral stability.
Fig 6: Site welding the stadium from a structural (and possibly even architectural)
406mm diameter point of view. Due to the significant overhang of the west stand
CHS stays to typical roof (approximately 45m in the centre of the stand) and the
A-frame presence of the upper tier of terracing, the cantilever solution
adopted for the other stands was not appropriate here.
Consequently, a stayed solution was adopted, using relatively
slender 406mm diameter CHS stays to support tapered box
section beams that extend from the external perimeter to the
tip of the roof. These box section beams are fabricated out of
steel plate, and range from 1350mm deep at their supports,
down to 600mm at the roof edge.
The CHS stays are up to 40m long, and resist axial tensions
of up to 10 000kN (ultimate). In order to minimise the second-
ary bending moments caused by P-delta effects (i.e. due to the
product of the axial tension in the CHS stays and their self-
weight deflection), the stays were cranked upwards at third
points such that their deflected shape approximates to a
straight line.
Fig 7: Starting to lift The stays rise gently in pairs up to the back edge of the roof,
a typical A-frame – where they meet one of the six. ‘A-frames’ that essentially hold
watch that tree! up the west stand roof. These ‘A-frames’ are also made up of
CHS struts and ties (ranging from 323mm to 457mm in diam-
eter) that effectively transfer the vertical loads from the roof
into 1200mm diameter concrete encased perimeter columns.
See fig 4.
Meanwhile, the significant overturning moments at the back
edge of the roof are resisted by the coupling action of horizon-
tal forces at upper tier terracing and hospitality (second floor)
levels. However, in order for these horizontal forces to get from
roof level down to upper tier terracing raker beams, the perime-
ter columns must be capable of resisting significant bending
moments. Hence, for both structural and aesthetic reasons,
relatively small UC section steel columns (which were only
designed to resist the construction loads from the accommoda-
tion and terracing) are encased by 1200mm diameter rein-
forced concrete section to give a very stiff composite column. The
Fig 8: First two A- horizontal forces ultimately find their way down to the piled
frames in position foundations via the terracing raker beams to both the upper and
lower tiers of the west stand, with the assistance of diagonal
bracing between hospitality and upper concourse levels (typi-
cally hidden within the partition walls between hospitality
boxes).
For ease of transportation and temporary stability, it was
decided to fabricate each of the six A-frames at the rear of the
west stand and lift them into place as complete frames. This
resulted in six lifts of approximately 100t/lift, each one lasting
up to 8h. In order to minimise out of balance forces in the roof,
it was necessary to build the west stand roof in a symmetric
manner from the centre outwards. Hence, the two central ‘A-
Dynamic behaviour
In addition to football and rugby, the stadium is intended to be
used as a venue for pop concerts, which has a significant impact
in terms of dynamics. Dynamically, the structure was designed
in accordance with a report produced by the
IStructE/DTLR/DCMS working group in November 2001,
Dynamic performance requirements for permanent grandstands
subject to crowd action: Interim guidance on assessment and
design1.
The report essentially recommends that, if the vertical
frequency of the empty stands is equal to or exceeds 6Hz, then
no further assessment is required. This threshold ensures that
significant resonant excitation from the first and second
harmonics is avoided. Significant vibration in either of the two
horizontal directions must also be avoided and this is achieved Fig 11: View to rear of West stand from the park
by compliance with rules which give horizontal loads equal to
7.5% of the imposed vertical load applied in the two horizontal
directions (i.e. along the length of the stand, and also from front
to back).
Initially, a series of 2D computer models was created in order
to determine approximate sizes for the precast terracing units,
steel terrace raker beams and vertical bracing in the ‘front to
back’ direction.
Subsequent to this, detailed advice regarding dynamic
modelling was taken from two members of the aforementioned
IStructE/DTLR/DCMS working group (namely, Phil Cooper of
K W Consultants Ltd and Prof. Aleksandar Pavic at the
University of Sheffield). A key piece of advice was that it is
essential to model the mass and stiffness of the whole structure
(including their distribution) as accurately as possible. This
resulted in several 3D computer models being created, which
enabled both the local and the global dynamic response of the
structure to be determined in the three principal axes (i.e. in the
vertical, side to side and front to back directions) as well as
confirming the member sizes obtained from the 2D analysis.
The analysis was carried out using the ROBOT finite
element analysis software. In the case of the two-tier west Fig 12: 'Wishbone' floodlights to North-East corner
stand, symmetry allowed just half of the stand to be modelled,
REFERENCES