Professional Documents
Culture Documents
Preparation of the Feasibility Study for the Khulna Water Supply Project (Phase 2)
Preliminary Cost Estimate of Works for Composite Option Update: 2024.01.09
Quantity for 2035 Incremntal Qty. for 2050 Cost (BDT) Unit Rates based on various sources
Compon Unit Rate Similar Project
S.N. Sub-Components Items Unit Incremental Cost KWSP-1 (As Direct Quotation From KWASA
ents No. Quantity No. Quantity (BDT) For 2035 LGED-23 PWD-23 DWASA/
for 2050 implemented) / Website (23.12.27)
CWASA
1 Existing Intake
Civil, Pipes, Valves,
Pre-settling Tank Sludge pump etc. all m2 1 600 2 600 71,163 42,697,800 85,395,600 77,961 71,546 71,163
inclusive
Bldg. Civil Works m2 1 324 55,000 17,820,000 47,353
Each pump
Pump House Additional Pumps,
Q=1600 m3/hr,
Header and Piping kW 3+1 19,500 67,392,000 63,685 19,500
H = 88m, 864
Works
kW
Electrical Switchgears,
Transformer, Surge
Miscellaneous Works LS 1 1 10,000,000 10,000,000
Tanks, Generator, Fuel
Tank etc.
Electrical Switchgears,
LS 1 1 5,000,000 5,000,000 10,000,000
Transformer etc.
Raw Water Pipeline DI 800 mm m 1 1608 76,040 122,272,320
Bldg. Civil Works m2 1 200 55,000 11,000,000
Each Pump
Pumps, Header and
Pump House at 5 kW 1+1 Q=2000 m3/hr, H 19,500 14,040,000
Piping Works
MLD WTP Location = 47m, 360 KW
Electrical Switchgears,
LS 1 1 5,000,000 5,000,000
Transformer etc.
DI 700 mm m 1 10660 62,710 668,488,600
DI 600 mm m 1 1907 50,980 97,218,860
Transmission DI 500 mm m 1 6537 39,746 259,819,602
Pipeline to MAR
Ponds DI 400 mm m 1 12790 29,295 374,683,050
Valves- 800 mm No. 1 5 500,000 2,500,000
Valves- 400 mm No 1 5 200,000 1,000,000
Drying, Dredging to
uniform depth, Filling
MAR Ponds
with Sand filter bed, m2 1 100000 5,000 500,000,000 4,065 4,268
Rehabilitation
embankment, Fencing
of Pond, Walkways
7 Clear Water Transmission Mains
1100 mm m 6071 119,577 0 725,951,967 119577 (for 1100 dia)
900 mm m 16637 88,054 1,464,954,398 0 88,054
800 mm m 4781 76,040 363,547,240 0 76,041
DI Pipeline 700 mm m 12549 4769 62,710 786,947,790 299,063,990 62,711
600 mm m 77 446 50,980 3,925,460 22,737,080 50,980
500 mm m 2181 449 39,746 86,686,026 17,845,954 39,746
400 mm m 1585 2303 29,295 46,432,575 29,295
Rupsa River
1100 mm (HDD
Crossing, underwater m 600 405,000 243,000,000 405,000
method), MS Pipe
crossing
Cathodic protection MS Pipe m 600 40,500 24,300,000 40,500
Quantity for 2035 Incremntal Qty. for 2050 Cost (BDT) Unit Rates based on various sources
Compon Unit Rate Similar Project
S.N. Sub-Components Items Unit Incremental Cost KWSP-1 (As Direct Quotation From KWASA
ents No. Quantity No. Quantity (BDT) For 2035 LGED-23 PWD-23 DWASA/
for 2050 implemented) / Website (23.12.27)
CWASA
MS Pipe encased by
RCC in water way,
Mayur River
Flanged DI Pipes on m 3 50 130,500 19,575,000 130,500
Crossing
both sides, bends,
Thrust block etc.
Quantity for 2035 Incremntal Qty. for 2050 Cost (BDT) Unit Rates based on various sources
Compon Unit Rate Similar Project
S.N. Sub-Components Items Unit Incremental Cost KWSP-1 (As Direct Quotation From KWASA
ents No. Quantity No. Quantity (BDT) For 2035 LGED-23 PWD-23 DWASA/
for 2050 implemented) / Website (23.12.27)
CWASA
MS Pipe encased by
RCC in water way,
Other Drain
Flanged DI Pipes on m 6 20 130,500 15,660,000
Crossings
both sides, bends,
Thrust block etc.
900 mm No. 8 540,000 4,320,000 540,000
800 mm No. 2 450,000 900,000 450,000
700 mm No. 9 360,000 3,240,000 360,000
Butterfly Valves
600 mm No. 3 270,000 810,000 270,000
500 mm No. 3 225,000 675,000 225,000
400 mm No. 3 180,000 540,000 180,000
Wash Out Valve 250 mm No. 15 135,000 2,025,000 135,000
Air Valve (Double
150 mm No. 10 135,000 1,350,000 135,000
Orifice)
8 Distribution Reservoir and Pump House
Zone 11 ML 2 31,267,000 62,534,000 22,752,666 25,210,999 24,427,023 31,267,000
Zone 12, 13 and 14 ML 7 31,267,000 218,869,000 22,752,666 25,210,999 24,427,023 31,267,000
Ground Level SR
Zone 15 ML 5 31,267,000 156,335,000 22,752,666 25,210,999 24,427,023 31,267,000
Zone 16 ML 7 31,267,000 218,869,000 22,752,666 25,210,999 24,427,023 31,267,000
Zone 11 (Circular) ML 0.3 96,653,000 28,995,900 85,961,429 77,979,043 75,457,033 96,653,000
Overhead Tank Zone 12, 13 and 14 ML 0.9 96,653,000 86,987,700 85,961,429 77,979,043 75,457,033 96,653,000
(OHT) (Rectangular)
Zone 15 (Circular) ML 0.5 96,653,000 48,326,500 85,961,429 77,979,043 75,457,033 96,653,000
Zone 16 (Circular) ML 0.5 96,653,000 48,326,500 85,961,429 77,979,043 75,457,033 96,653,000
Pump House Civil Works m2 3 300 55,000 49,500,000 - 76,406 73,907 55,000
Zone 11 kW 2 50 2 50 19,500 273,000 1,950,000 19,500
Pumps & associated Zone 12, 13 and 14 kW 6 50 6 50 19,500 1,170,000 5,850,000 19,500
Piping Works Zone 15 kW 2 50 2 60 19,500 1,287,000 2,340,000 19,500
Zone 16 kW 2 50 3 50 19,500 1,287,000 2,925,000 19,500
Electrical Panels, All 4 Distribution
LS 1 4 9,000,000 36,000,000 0 9,000,000
Guard House etc. Reservoir sites
Construction of
MAR Recharge
Injection Wells incl. No. 5 10,000,000 50,000,000 15,000,000
Wells
E/M works
18 Solar Power Generation
Floating Panels in
Solar Power
existing IPR only at kW 1 2100 165,000 346,500,000 - 132,426.00 121,500.00 165,000
Generation, 2.1 MW
WTP
Floating Panels on afil
Solar Power
gate IPR or on all 5 kW 1 1000 165,000 165,000,000 - 132,426.00 121,500.00 155,000
Generation, 1 MW
MAR ponds
At rooftop of all 11
Solar Power
Distribution Reservoir kW 1 1000 165,000 165,000,000 - 132,426.00 121,500.00 165,000
Generation, 1 MW
Sites
Total of Engineering Components in BDT, CAPEX 19,542,348,537 7,940,002,231
In Eqv. USD 177,657,714 72,181,838
19 Annual O&M Cost
Compon For year 2035 For year 2050 Unit Rate Cost (BDT)
S.N. Sub-Components Items
ents No. Quantity No. Quantity (BDT) Yr 2035 Yr 2050
20 Land Acquisition
Provision for New
All facilities m2 10000 13,182 131,820,000 0
Intake
Existing Intake Addl. Pre-settling tank m2 7500 13,182 98,865,000
WTP 110 MLD for 2050 m2 12800 13,183 168,742,400
Impounding (water area + 20%) -
m2 45000 138000 13,182 593,190,000 1,819,116,000
Reservoir available area
Zone 11 m 2
2700 42,711 115,319,700
SR&PS sites
Quantity for 2035 Incremntal Qty. for 2050 Cost (BDT) Unit Rates based on various sources
Compon Unit Rate Similar Project
S.N. Sub-Components Items Unit Incremental Cost KWSP-1 (As Direct Quotation From KWASA
ents No. Quantity No. Quantity (BDT) For 2035 LGED-23 PWD-23 DWASA/
for 2050 implemented) / Website (23.12.27)
CWASA
SR&PS sites
Zone 12, 13 & 14 m2 7500 42,711 320,332,500
Total of Land Acquisition in BDT 1,160,662,200 2,086,723,400
In Eqv. USD 10,551,475 18,970,213