Professional Documents
Culture Documents
Dhamanapalli ESTIMATE
Dhamanapalli ESTIMATE
Project Client:Improvement to road from Doddametikere to Holalakere Cross road Jn via D.M.k Gollarahatti and H.Thandya in Arasikere Taluk Hassan
P = P1A1+P2A2+P3A3
A1+A2+A3
= 2593.75 0.32
=
8187.50
= 100.00 = 133.333 S
0.75
133.33 2.22 M
= =
60
Q = 0.028 P A Ic
Where
Q = Discharge in Cum/Sec
P = Coefficient of runoff for the catchment characteristics 0.32
A = Area of Catchment in hectares 0.82
d= 0.38
0.07
0.45
0.38
0.45
DESIGN FOR BED SLOPE
Q=AV
V=(1/n)R2/3S1/2
Q Discharge in cum/sec
V mean velocity in M/sec
n Mannings Roughness Co-ef
R Hydraulic radious in M which is area of flow crossection divided by wetted perimeter
S Energy slope of the channel, which is roughly taken as slope of the drain
A Area of flow cross section in Sqm
s=(vn/r2/3)2
s 0.01274
Bed slope: 1 in 79
Executive Engineer
Project Division,
Hassan
0.40 m
3.00 m
LBL
0.15 m
1.80 m
0.30 m
2.00 m
Eccentricity = b/2 - x
(=2/2)-0.77 0.23 m
< b/6 ie 0.330
0.40m
2.10m
GL
0.60m 0.20m
1.10m
0.30m
1.50m
3) Pressure Distribution
Net Moment ЄM = Mr - Mo
=128.98 - 29.7 99.279
x = ЄM / ЄW
= 99.279 / 131.04 0.76
Eccentricity = b/2 - x
= 1.70 /2 - 0.76 0.09 m
Kn-m Kn-m
24 18
-
2 3 1
1/3 2/3 6
Name of the work : Road from Dhamanapalli to Katchuluru ( Up to Peddanoothulu)
0.40 m
1.80 m
LBL
0.15 m
1.05 m
0.30 m
1.35 m
Eccentricity = b/2 - x
(=1.35/2)-0.57 0.11 m
< b/6 ie 0.230
0.40m
2.10m
GL
0.60m 0.20m
1.10m
0.30m
1.50m
3) Pressure Distribution
Net Moment ЄM = Mr - Mo
=128.98 - 29.7 99.279
x = ЄM / ЄW
= 99.279 / 131.04 0.76
Eccentricity = b/2 - x
= 1.70 /2 - 0.76 0.09 m
Kn-m Kn-m
24 18
-
2 3 1
1/3 2/3 6
Sub Estimate
Road from Dhamanapalli to Katchuluru ( Up to Peddanoothulu)
Name of the sub Work : Construction of Retaining Wall.
Measurments
S.No Description No Quantity Rate Amount
L B D
1 Earthwork in excavation for structures as per drawing and
technical specifications Clause 305.1 including setting out,
removal of stumps and other deleterious material and disposal
upto a lead of 50 m, dressing of sides and bottom and backfilling
in trenches with excavated suitable material as per Technical
Specification 305 MORD / 304 MORTH ,including overhead
charges & Contractors profit but excluding VAT and seigniorage
charges etc., complete for Foundations
Superintending Engineer,
PR Cirlce,Visakhapatnam
Sub Estimate
Name of the work Road from Dhamanapalli to Katchuluru ( Up to Peddanoothulu)
Name of the sub Work : Providing CC Drains in Village portion and Ghat section
Length Of Drain 100 m
S.N Measurements
Description of work Nos Quantity Rate Amount
o L B D
1 2 3 4 5 6 7 8 10
1 Earth work in excavation for structures as per drawing and Technical Specification
Clause 305.1 including setting out, construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a lead of 50m, dressing of
sides
From 4/3 to 4/4 2 1 100.00 0.75 0.60 90.00
From 1/0 to 2/5 2 1 1000.00 0.75 0.60 900.00
990.00 92.25 91328
2 Sand filling in drain portion including all cost and labour charges etc complete
From 4/3 to 4/4 2 1 100.00 0.75 0.15 22.50
From 1/0 to 2/5 2 1 1000.00 0.75 0.15 225.00
2. Package No:-
Yes NO
6. Estimated Cost Rs :
Item Total Cost in Average Cost per Km.
Rs. Lakhs
Flexible Pavement
Rigid Pavement
Others ( CD Works, Protective works & Misc items)
MoRD Share
State Share
Total weight
b) Indicate the actual widths of the following for the proposed road In the Built Up Area (m) In the Open Area (m)
i) Carriageway -
ii) Roadway -
iii) Road Land Width -
H1 H2 H2
MDR-42
MSH-6
ROAD
Day 1
Day 2
Day 3
Average
A= Intitial traffic in the year of completion of construction in terms of the number of commericial
vehicles per day
D= Lane distribution factor
F= Vehicle damage factor
n= Design life in years
r= growth rate adopted %
N= The cumulative number of standard axles to be catered for the design in terms of msa
CVPD
A. Pavement Components
Description of layer Thickness in mm Quantity Rate Rs Cost Rs. Cost/ km
(Rs)
WBM Gr -I I
WBM Gr -I I I
Prime Coat
Tack Coat
Seal Coat
Surface Dressing
Total cost of Flexible pavement
Cement Concrete Road
IRCSP 62:2004 IRC 58
GSB
WBM
C. Protection works
Chainage
D. Pucca Side Drains (if Provided) Chainage Length( Cost in Rs Average cost / m
m)
From To
II
III
IV
G/ Total of maintenance
Yes NO
13. Whether the road has Geometrics as per Rural Roads Manual RRM / Latest Circulars of NRRDA.
Yes No
14.Whether C.D.works / Protection works are provided as per RRM / Latest Circulars of NRRDA/ Respective Codes of IRC.
15.Does the Estimation Conform to Standard Rate Analysis and SSR generated for the current Phase Vetted at
NRRDA Year
Yes No
Counter Signatures of
Co-ordinator STA :
To be filled by State Technical Agency
Name of the STA:
( Catchment for structures with more than 2 Vents to be verified from topo sheet. Location and requirement of all CD
structures to be verified from L section )
20 In case , Traffic is projected beyond T 7 Category and road designed using IRC 37 are you satisfied with the
reason given by PIU
21 In case, sub grade CBR is less than 5; has Soil Stabilisation etc. been proposed
22 Is the design of the following elements as per Rural Roads Manul / Circulars of NRRDA:
Is the design of flexible Pavement as per IRC 37 2001 and design of Rigid Pavement as per IRC SP:58- 1998.
Certified that the Design and Estimation for the Proposed Road work are based on the data and SSR provided by PIU Engineers . The Proposal after final Correction is entered on the
OMMS.The Propasal may be considered for clearance.
Date
869768
1162659
292891
25.19148
1143100
870076
273024
0.313793
INDEX MAP (not to scale ) :
Attached saperately
Rampachodavaram R &
Peddanotthulu
0/0 Dhamanapalli to 4/6 to 6/2 8/720
Devipatnam to
MDR-42
B road
MSH-6
Prop.widening of embankment
Name of the Work : Road from Dhamanapalli to Katchuluru ( Up to Peddanoothulu)
Estimate Cost :
Name of the District : East Godavari
Name of the Circle : Kakinada
Name of the Division : PR (PIU), Kakinada
Name of the Sub Division : PR (PIU), Rampachodavaram
Name of the Mandal : Devipatnam
Type of Proposal : Up gradation.
From : Damanapalli
To : Katchuluru Built up area Open Area
Length of the Road : 7.800 1.200 6.600
Starting KM : 0/000
From KM : 0/000
Gravel 3/300 Existing Gravel 75mm
To KM : 7/800
Total Length of the road : 7.800
Corenet Work No : L039
SSR : 2013-14
No of Habitations connected : 3
Transitio
Length of the LHS/ n curve
Curves : Degree curve Radius RHS length
Curve at KM 6/570 Err:540 Err:540 Err:540 LHS Err:540
Protection Works
KM 0/000 to 6/800 0/000 Mar-00
KM 0/000 to 6/800
0/000 to 6/800
B Murali Krishna
Assistant Engineer
PR (PIU), R Chodavaram
B.R.Tagore
Deputy Executive Engineer,
PR (PIU), R Chodavaram
A.V.Subrahamanayam
Executive Engineer,
PR (PIU), Kakinada
Venkateswara Rao
Superintending Engineer,
PR Circle, Kakinada
ddanoothulu)
Circular Total
curve length of Extra Super
length curve widening elevation Speed
Err:540 Err:540 Err:540 Err:540 Err:540
0 0 1 0
0 0 0 1
0 0 0 1
0 0 1 0
0 0 1 0
0 0 0 1
Soil
MDD
classifica
(gm/cc)
tion
1.72 CL 0/300
1.74 CL 0/750
1.73 CL 1/250
1.72 CL 1/800
1.76 CL 2/250
1.72 CL 2/750
1.75 CL 3/300
1.74 CL 3/800
1.70 CL 4/250
1.75 CL 4/750
1.73 CL 5/250
Silt Clay
53.8 CL 0/300
52 CL 0/750
53.6 CL 1/250
56.6 CL 1/800
53.4 CL 2/250
53.0 CL 2/750
53.6 CL 3/300
53.1 CL 3/800
52.2 CL 4/250
55.8 CL 4/750
54.7 CL 5/250
Existing
20 75 0 Gravel
xe Engineer Assistant Engineer
Dvn, R Chodavaram PR (PIU) R Chodavaram
Assistant Engineer
PR (PIU) R Chodavaram
0 0 0 0 0 0 0 0 1 1 0 0 0 0 0 0 0 0 2
0 2
Calculation of seionarage charges
Road from Dhamanapalli to Katchuluru ( Up to Peddanoothulu)
Quantity Qty
S.
Item (finished Unit Material (collecte Rate Seignorage Amount
No
item) d)
Construction of 1000 mm dia two rows Pipe Culverts
1 Earthwork for foundations 135.41 Cum Earth 135.41 22.00 2979.02
2 Sand filling in foundations 5.17 Cum Sand 5.17 40.00 206.80
3 PCC (1:3:6) for foundations 15.50 Cum Metal 13.95 50.00 697.50
Sand 6.98 40.00 279.20
4 PCC (1:2.50:5) for Side walls 59.84 Cum Metal 47.87 50.00 2393.50
Sand 28.72 40.00 1148.80
Construction of 1000 mm dia three rows Pipe Culverts
1 Earthwork for foundations 72.00 Cum Earth 72.00 22.00 1584.00
2 Sand filling in foundations 140.46 Cum Sand 140.46 40.00 5618.40
3 PCC (1:3:6) for foundations 5.85 Cum Metal 5.27 50.00 263.50
Sand 2.63 40.00 105.20
4 PCC (1:2.50:5) for Side walls 47.05 Cum Metal 37.64 50.00 1882.00
Sand 22.58 40.00 903.20
Construction of 600 mm dia three rows Pipe Culverts
1 Earthwork for foundations 57.60 Cum Earth 57.60 22.00 1267.20
2 Sand filling in foundations 90.80 Cum Sand 90.80 40.00 3632.00
3 PCC (1:3:6) for foundations 4.50 Cum Metal 4.05 50.00 202.50
Sand 2.03 40.00 81.20
4 PCC (1:2.50:5) for Side walls 17.54 Cum Metal 14.03 50.00 701.50
Sand 8.42 40.00 336.80
Construction of 600 mm dia five rows Pipe Culverts
1 Earthwork for foundations 28.80 Cum Earth 28.80 22.00 633.60
2 Sand filling in foundations 229.78 Cum Sand 229.78 40.00 9191.20
3 PCC (1:3:6) for foundations 7.50 Cum Metal 6.75 50.00 337.50
Sand 3.38 40.00 135.20
4 PCC (1:2.50:5) for Side walls 49.53 Cum Metal 39.62 50.00 1981.00
Sand 23.77 40.00 950.80
Construction of 600 mm dia single row Pipe Culverts
1 Earthwork for foundations 58.30 Cum Earth 58.30 22.00 1282.60
2 Sand filling in foundations 9.20 Cum Sand 9.20 40.00 368.00
3 PCC (1:3:6) for foundations 12.25 Cum Metal 11.03 50.00 551.50
Sand 5.51 40.00 220.40
4 PCC (1:2.50:5) for Side walls 61.55 Cum Metal 49.24 50.00 2462.00
Quantity Qty
S.
Item (finished Unit Material (collecte Rate Seignorage Amount
No
item) d)
Sand 29.54 40.00 1181.60
Construction of 1000 mm dia single row Pipe Culverts
1 Earthwork for foundations 43.20 Cum Earth 43.20 22.00 950.40
2 Sand filling in foundations 75.46 Cum Sand 75.46 40.00 3018.40
3 PCC (1:3:6) for foundations 5.85 Cum Metal 5.27 50.00 263.50
Sand 2.63 40.00 105.20
4 PCC (1:2.50:5) for Side walls 27.55 Cum Metal 22.04 50.00 1102.00
Sand 13.22 40.00 528.80
Construction of retaing wall
1 Earthwork for foundations 272.40 Cum Earth 272.40 22.00 5992.80
2 Sand filling in foundations Cum Sand 0.00 40.00 0.00
3 PCC (1:3:6) for foundations 33.30 Cum Metal 29.97 50.00 1498.50
Sand 14.99 40.00 599.60
4 PCC (1:2.50:5) for Side walls 349.80 Cum Metal 279.84 50.00 13992.00
Sand 167.90 40.00 6716.00
Construction of 600 mm dia two rows Pipe Culverts
1 Earthwork for foundations 128.07 Cum Earth 128.07 22.00 2817.54
2 Sand filling in foundations 4.01 Cum Sand 4.01 40.00 160.40
3 PCC (1:3:6) for foundations 11.02 Cum Metal 9.92 50.00 496.00
3 PCC (1:3:6) for foundations 0.00 Cum Metal 0.00 50.00 0.00
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Body Walls upto 1 x 2 15.00 (1.05+ 0.75 21.94
sill level 0.90)/2
Body walls pipes 1 x 2 15.00 (0.90+ 1.20 27.00
portion 0.60)/2
Above pipes 1 x 2 15.00 (0.60+ 0.60 9.00
portion 0.40)/2
Parapets 1 x 2 15.00 0.40 0.30 3.60
S Rate
Description No. L B D Quantity Per Amount
No
Deduct pipes 2 x 3.142 1.20 1.20 (0.9+ -1.70
portion /4 0.6)/2
59.84 5253.10 cum 314346
5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design.
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in
head wall and parapets. Tech Specification Clause 1106 MORD ,including cost of pipe,
collar, overhead charges & Contractors profit but excluding VAT. & Seigniorage
charges
1000mm dia 2 x3 2.50 15.00
15.00 7,228.97 Rmt 108435
6 Construction of embankment with approved material obtained from borrow pits with all
lifts, transporting to site, spreading, grading to required slope and compacting to meet
requirement of Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical
Specification Clause 301.5 MORD/ 305 MORTH including overhead charges &
Contractor profit, But excluding VAT and seigiorage charges
530000
Superintending Engineer, Executive Engineer Deputy Exe Engineer Assistant Exe Engineer
PR Circle, Kakinada PR (PIU) Dvn, Kakinada PR (PIU) Sub Dvn, R Chodavaram PR (PIU) R Chodavaram
FORMAT 7
Road from Punyakshetram to G Yerrampalem (via) Bhupalapatnam
Construction of 1000mm dia NP III Class RCCThree Rows Pipe Culvert At Chainages KM 8/4 to
8/5
S Rate
Description No. L B D Quantity Per Amount
No
1 Dismatling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonary, cement concrete, wood work, steel work, including T & P and
scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000m as per
Technical specification clause 202.1
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
S Rate
Description No. L B D Quantity Per Amount
No
Body Walls 1 x 2 25.00 0.50 1.00 48.75
Deduct pipes 3 x 3.142/ 1.20 1.20 0.50 -1.70
portion 4
47.05 5253.10 cum 247158
5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design.
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material including fixing collar with cement mortar 1:2 but
excluding excavation, protection works, backfilling, concrete and masonry works in head
wall and parapets. Tech Specification Clause 1106 MORD ,including cost of pipe, collar,
overhead charges & Contractors profit but excluding VAT. & Seigniorage charges
at culvert 6/6 to 1 x 1.00 25.00 6.50 0.20 4.88 6013.22 Cum 29345
6/8
6 Add LS for other unforeseen items 4347
570000
0
Superintending Engineer, Executive Engineer Deputy Exe Engineer Assistant Engineer
PR Circle, Kakinada PR (PIU) Dvn, Kakinada PR (PIU) Sub Dvn, R Chodavaram PR (PIU) R Chodavaram
SUB ESTIMATE
Name of the work: R/F Dmanapalli to Katchuluru ( Up to Peddanoothulu)
Sub work :Constuction of 3 rows 600 mm Dia pipe culvert 4/3 to 4/4
S.No Description No Measurments Quantity Rate Amount
L B D
1 Dismatling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonary, cement concrete, wood work, steel work,
including T & P and scaffolding wherever necessary, sorting the dismantled material,
disposal of unserviceable material and stacking the serviceable material with all lifts
and lead of 1000m as per Technical specification clause 202.1
3 Sand filling in foundation including cost and conveyance of all materials and all
labiur charges etc complete
between pipes 1 20.00 6.50 0.70 91.00
Deduct pipes portion 3x 0.75 0.75 6.50 -0.20
TT/4
Total Quantity 90.80 612.59 / CUM 55624
5 Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD including overhead charges & Contractors
profit but exclu
3 Sand filling in foundation including cost and conveyance of all materials and all
labiur charges etc complete
Head walls 2 10.00 1.20 0.15 3.60
between pipes 1 50.00 6.50 0.70 227.50
Deduct pipes portion 5x 0.75 0.75 6.50 -1.32
TT/4
Total Quantity 229.78 612.59 / CUM 140758
5 Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD including overhead charges & Contractors
profit but exclu
Head H 0.60m
600mm dia
Q = 0.028 x P x A x Ic
Where P = Coefficient of Run Off for the catchments characteristics,
as per IRC SP - 13 1994, page 35, table 2 for Sandy soil, light growth P = 0.20
A = Catchments Area in Hectares 5.60 Hectares
Ic = Rainfall Intensity 21.00 Cm.
Q = 0.028 x P x A x Ic
= 0.028*0.2* 5.60*21
= 0.66 cumecs
The Discharge through the designed / Proposed 600mm dia pipe is 0.823 cumecs which is
more than required discharge 0.66 Cumecs
Head H 0.30m
600mm dia
Q = 0.028 x P x A x Ic
Where P = Coefficient of Run Off for the catchments characteristics,
as per IRC SP - 13 1994, page 35, table 2 for Sandy soil, light growth P = 0.20
A = Catchments Area in Hectares 6.80 Hectares
Ic = Rainfall Intensity 21.00 Cm.
Q = 0.028 x P x A x Ic
= 0.028*0.2* 6.80*21
= 0.7997 cumecs
L = Length of Pipe 7.50 m
D = Diametre of Pipe 600 mm
Lambda = Conveyance factor
λ For Round edges , from Plate 16 of SP13
For Length of Pipe 5m 0.381
For Length of Pipe 10m 0.333
The Discharge through the designed / Proposed 600mm dia pipe is 0.866 cumecs which is
more than required discharge 0.7997 Cumecs
1 Earth work in excavation for structures as per drawing and technical specifications
clause 305.1 including settling out construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a lead of 50m, dressing of
sides and bottom and back filling in tranches with excavated suitable material as per
clause 300 (1) of MORD excluding VAT
2 Sand filling in foundation including cost and conveyance of all materials and all
labiur charges etc complete
Head walls 2 15.00 1.00 0.10 3.00
Under pipes 2 5.60 0.90 0.10 1.01
Total Quantity 4.01 612.59 / CUM 2456
4 Providing and laying reinforced cement concrete pipe NP3( as per design single
Row)for culverts on first class beeding of granular material in single row including
fixing collar with cement mortor 1:2 but excluding excavation, protection works,
backfilling, concrete and masonary works in head walls and parapets as per clause
1106 and as per cluase 1100 of MORD excuding VAT
odavaram
SUB ESTIMATE
Name of the work: R/F Dmanapalli to Katchuluru ( Up to Peddanoothulu)
Sub work :Constuction of sigle row 600 mm Dia pipe culverts at 5/2 to , 5/7 to 5/8 , 6/9 to 7/0,
7/2 to 7/3 and 8/1 to 8/2
2 Sand filling in foundation including cost and conveyance of all materials and all
labiur charges etc complete
Head walls 2 3.00 1.20 0.15 1.08
Under pipes 1 5.60 0.90 0.15 0.76
Total Quantity 1.84 612.59 / CUM 1127
3 Plain cement concrete M 15 grade using 40,20 & 10mm metal mechanically mixed in
substructure complete as per drawings and technical specification Clauses 802, 804,
805, 806, 807, 1202 and 1204 MORD including overhead charges & Contractors
profit but exclu
1 Earth work in excavation for structures as per drawing and technical specifications
clause 305.1 including settling out construction of shoring and bracing, removal of
stumps and other deleterious material and disposal upto a lead of 50m, dressing of
sides and bottom and back filling in tranches with excavated suitable material as per
clause 300 (1) of MORD including all over heads , and Contractors profit and
seignorage charges
2 Providing concrete for plain/reinforced concrete PCC (1:3:6) nominal Mix M10 in
open foundations using 40 mm nominal size Graded HBG aggregate, including
cost, and conveyance of all materials to site and all labour charge mechanically
mixed, placed in foundation and compacted by vibration including curing for 14 days
complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203
MORD ncluding contractors profit & Over head charges but excluding Seigonarage
charges & VAT.
3 Providing concrete for plain concrete M 15 grade DESIGN MIX in Sub structure
using 40 mm nominal size Graded hard stone aggregate, mechanically mixed, placed
in foundation and compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD
including overhead charges & Contractors profit but excluding VAT. & Seigniorage
charges
58
Sl.
Length Width( Thinkne
No Description of Item No Quantity Rate (Rs) unit per Amount (Rs)
(m) m) ss(m)
.
1 2 3 4 5 6 7 11 12 13
AC 100mm dia Class 6 60 1 60.00 309.00 1 No 18540.00 ###
pipeClass-15
5 Provision for LS 15761.00
TOTAL : Rs 2050000.00
59
0.00
60
FORMAT 7
Road from Punyakshetram to G Yerrampalem (via) Bhupalapatnam
Construction of 1000mm dia NP III Class RCC Single Row Pipe Culvert At Chainages KM 7/7 to 7/9
S Rate
Description No. L B D Quantity Per Amount
No
1 Dismatling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonary, cement concrete, wood work, steel work, including T & P and
scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable
material and stacking the serviceable material with all lifts and lead of 1000m as per
Technical specification clause 202.1
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
S Rate
Description No. L B D Quantity Per Amount
No
Body Walls 1 x 2 15.00 0.50 1.00 29.25
Deduct pipes 3 x 3.14 1.20 1.20 0.50 -1.70
portion 2/4
27.55 5253.10 cum 144723
5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design.
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material including fixing collar with cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonry works in head wall and
parapets. Tech Specification Clause 1106 MORD ,including cost of pipe, collar, overhead
charges & Contractors profit but excluding VAT. & Seigniorage charges
7 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates
conforming to IS : 383, mixed in a concrete mixer of not less than 0.2 cum capacity and
appropriate weigh batcher using approved mix design, laid in approved fixed side formwork
(steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates
including levelling the formwork as per drawing), spreading the concrete with sholvels,
rakes, compacted using needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion and construction joints,
applying debonding strips, primer, sealant, dowel bars, admixtures as approved, curing of
concrete slabs for 14- days, curing compound (where specified) and water finishing to lines
and grade as per drawing and Technical Specification Clause 1501 MORD including
overhead charges & Contractors profit but excluding VAT and seigniorage charges
at culvert 7/7 to 7/8 1 x 1.00 15.00 6.50 0.20 19.50 6013.22 Cum 117258
6 Add LS for other unforeseen items 11345
520000
As per calculation
sheet
Side earth 8614.45 87.15 cum 750749.00
3 Construction of embankment with approved material obtained from
borrow pits with all lifts, transporting to site, spreading, grading to
required slope and compacting to meet requirement of Tables 300.1 and
300.2 with a lead upto 1000 m as per Technical Specification Clause
301.5 MORD/ 305 MORTH including overhead charges & Contractor
profit, But excluding VAT and seigiorage charges
3420.00
7400.00
7400.00
7400.00
7400.00
7400.00
7400.00
7400.00
7400.00
7800.00
Executive Engineer
PIU Division Kakinada
ABSTRACT ESTIMATE FOR ROAD FURNITURE
Providing & fixing of typical PMGSY informatory sign board with LOGO as per
MORD secifications and drawing. Three MS plates of 1.6mm thick, top and
middle plate duly welded with MS flat iron 25mmx5mm size on black on edges.
The lower plate will be welded with MS angle iron frame of lower most plate and
flate iron frame of middle plate will be welded to 2 nos 75mmx75mm of 12 SWG
sheet tubes posts duly embedded in CC M15 grade blocks of
2
450mmx450mmx600mm, 600mm below ground level. The top most diamond
plate will be welded to middle plate by 47mmx47mm of 12 SWG sheet plate tube.
All MS will be stove enmeled on both sides. Lettering and paining of superior
quality in required shede and colour. All sections of framed posts and sheet tube
will be painted with primer and two coats of epoxy paint as per drawing clause
1701 and annexure 1700.1 if MORD excluding VAT
Total 202693.00
17 20 mm HBG M/C Metal -SS5 Yeleswaram 74.00 984.00 710.53 70.00 246.00 0.00 0.00 2010.53
18 12 mm HBG M/C Metal-SS5 Yeleswaram 74.00 780.00 710.53 70.00 195.00 0.00 0.00 1755.53
19 10 mm HBG M/C Metal-SS5 Yeleswaram 74.00 656.00 710.53 70.00 164.00 0.00 0.00 1600.53
20 2.36 mm Below Material ( HBG Yeleswaram 74.00 330.00 710.53 0.00 0.00 0.00 1040.53 743.931
Stone chips )
Conveyance Machine Deduct
Sl Lead in charges excl. Diff. cost Blasting Loading
Description in Material Name of the Quarry Initial 14%OH&CP,1s Crushing for Total Amount
No. Km of pipes Charges Charges
t km rate Charges stacking
1 2 3 4 5 6 7 8 11 12
21 Stone boulder 300mm (25 kg / Yeleswaram 74.00 136.00 710.53 0.00 0.00 846.53
40 Kg minimum)
22 Soling stone 150mm Yeleswaram 74.00 86.00 710.53 0.00 0.00 796.53
23 Jeddy stone 450-600mm Yeleswaram 74.00 171.00 710.53 0.00 0.00 881.53
24 Emulsion (SS-1) Visakapatnam 274.00 31700.00 822.00 CST @ 5% 1585.00 34107.00
26 Bitumen bulk 60/70 grade Visakapatnam 274.00 40699.19 822.00 CST @ 5% 2034.96 43556.15 42734.15
27 1000mm Dia NP3 Class Pitapauram 96.00 4171.00 919.93 61.02 CST @ 5% 237.76 CED 523.08 5912.79
12.36%
28 1000mm Dia Collar Pitapauram 96.00 908.00 5.04 CST @ 5% 51.29 112.85 1077.18
29 900mm Dia NP3 Class Pitapauram 96.00 4166.00 890.93 47.98 CST @ 5% 236.74 CED 520.85 5862.50
12.36%
30 900mm Dia Collar Pitapauram 96.00 716.00 4.69 CST @ 5% 40.49 89.08 850.26
31 600mm Dia NP3 Class Pitapauram 96.00 2020.00 422.25 32.79 CST @ 5% 115.33 CED 253.72 2844.09
12.36%
32 600mm Dia Collar Pitapauram 96.00 360.00 2.43 CST @ 5% 20.36 44.80 427.59
33 300mm Dia NP3 Class Pitapauram 96.00 778.00 202.79 8.86 CST @ 5% 44.21 CED 97.26 1131.12
12.36%
34 300mm Dia Collar Pitapauram 96.00 124.00 0.94 CST @ 5% 7.02 15.44 147.40
By Machanical Means
In area of non Throny Jungle (Light Jungle)
Page 84 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
c) Material
Water Kl 12.00 100.00 1,200.00
Total 7,644.31
d) Add 14.00 % for Over head charges & 1,070.20
Contractors profit
Rate for 100 cum 8,714.51
Rate per cum 87.15
3 RBR- Construction of Embankment with Material Obtained from Borrow pits by Machinery
EEC
D-4
RBR- Construction of Embankment with Material
EECD Obtained from Borrow pits by Machinery
-4 Construction of embankment with approved material obtained from borrow pits with all lifts,
transporting to site, spreading, grading to required slope and compacting to meet requirement of
Tables 300.1 and 300.2 with a lead upto 1000 m as per Technical Specification Clause 301.5
MORD/ 305 MORTH including overhead charges & Contractor profit, But excluding VAT
and seigiorage charges
Unit = cum
Taking output = 100 cum
a) Labour
Mazdoor (Unskilled) day 1.04 280.00 291.20
Add 25 % MAA / AA 25% 72.80
b) Machinery
Hydraulic Excator 0.90cum bucket capacity hour 1.67 2,751.50 4,595.01
at 60cum per hour
Tipper 5.5cum with 10T capacity hour 4.50 877.30 3,947.85
Dozer D50 for spreading @ 200 cum per hour 0.50 1,569.81 784.91
hour
Tractor with Grader @ 25 cum per hour hour 4.00 624.00 2,496.00
Water tanker 6 KL capacity hour 2.00 624.00 1,248.00
Vibratory Roller 80-100 kN @ 100 Cum hour 1.00 2,541.40 2,541.40
per Hr
c) Material
Water Kl 12.00 100.00 1,200.00
Basic rate of formation of road with 17,177.16
borrow soils per Cum
d) Add 14.00 % for Over head charges & Contractors profit 2,404.80
Rate per 100 cums 19,581.96
Deduct VAT @4.00% 0.00
Rate per cum 195.82
4 RBR- Granular Sub-base with Well Graded
SBBS Material / Close Graded Material (Table
-1 400.1)
By Mix in Place Method
Page 85 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
Construction of granular sub-base by providing well graded material / Close graded material,
spreading in uniform layers with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC, and compacting with smooth wheel roller 80-100 kN /
Vibratory Roller to achieve the desired density, complete as per Technical Specification
Clause 401 MORD / MORTH. including over heads and contractor's profit , VAT &
Seignorage charges
Page 86 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
Water tanker 6kl capacity hour 5.00 624.00 3,120.00
Tractor with grader @ 25 cum per hour hour 12.00 422.00 5,064.00
Tractor with rotavator @ 25 cum per hour hour 12.00 422.00 5,064.00
c) Material
Well graded granular sub-base material as
per table 400.2
Cost of materials
9.5 mm to 4.75 mm @ 66% (Gravel) cum 237.60 168.18 39,959.57
2.36 mm below @ 34% (HBG stone chips) cum 122.40 1040.53 127,360.87
c) Add 14.00 % for Over head charges & Contractors profit 93.14
758.40
Rate per cum 758.40
6 RBR- Selected Earth Shoulders (Table 407 &
SBBS 305,305.4.4)
-2 Construction of Shoulders by providing Selected earth having MDD not less than 1.85g/cc
with LL & PL not exceeding 40% and 20% respectively and and spreading in uniform
layers with tractor grader on prepared surface and copacted to OMC with Vibratory roller of
80 to 100kN capacity to achieve the desired density, complete as per IRC technical
specification clause 407 MoRD,305&305.4.4 MoRT&H including all over heads , and
Contractors profit but Excluding VAT and seigniorage charges
c) Material
Well graded granular sub-base material as
per table 400.2
Cost of materials
Selected Earth cum 360.00 159.18 57,304.80
c) Add 14.00 % for Over head charges & Contractors profit 39.38
320.64
Rate per cum 320.64
7 RBR- WBM Grading 2 (using Graded Metal)
SBBS
-9 Providing, laying, spreading and compacting stone aggregates of specific sizes for Grading 2
material to water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with Vibratory roller 80-100 kN in stages to proper grade and camber,
applying and brooming, stone screening/binding materials to fill-up the interstices of coarse
aggregate, watering and compacting to the required density grading 2 as per Technical
Specification Clause 405 MORD / 404 MORTH. For compacted thickness of 75 mm.
including all over heads , and Contractors profit etc., Complete but Excluding VAT and
seigniorage charges for WBM Grading II ( Hand Broken)
By Manual means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 280.00 3,382.40
Mazdoor (unskilled) day 250.00 280.00 70,000.00
Add 25 % MAA / AA 25% 18,345.60
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour 6.00 2541.40 15,248.40
hour
Water tanker 6kl capacity hour 24.00 624.00 14,976.00
c) Material (Total Qty 435.60 Cum)
60-63 mm IRC HBG Metal (50% of 435.60 Cum 217.80 1199.53 261,257.63
cum)
40-45 mm IRC HBG Metal (46% of 435.60 Cum 200.38 1368.53 274,226.04
cum)
19-22 mm IRC HBG Metal metal (4% of Cum 17.42 1764.53 30,738.11
435.60 cum)
Stone Screening
Type -B 11.2mm @ 0.18 cum per 10 sqm cum 86.40 1288.03 111,285.79
( Avg. of 5-7 mm & 2.36-5mm)
Binding Material @ 0.06 cum per 10 sqm cum 28.80 1040.53 29,967.26
for Grading 2 material (size 2.36mm &
below having PI value 2-6%
By Manual means
Taking out put = 360 cum
a) Labour
Mazdoor (Skilled) day 12.08 280.00 3,382.40
Mazdoor (unskilled) day 250.00 280.00 70,000.00
Add 25 % MAA / AA 25% 18,345.60
b) Machinery
Vibratory Roller 80-100 KN @60cum per hour 6.00 2541.40 15,248.40
hour
Water tanker 6kl capacity hour 24.00 624.00 14,976.00
c) Material (total Qty of Metal 435.60
Cum)
40-45 mm IRC HBG Metal M/C ( 82% of Cum 357.19 1515.53 541,332.16
435.60 Cum)
19-22.40 mm IRC HBG M/C Metal ( 18% Cum 78.41 2010.53 157,645.66
of 435.60 cum)
Stone Screening
Type -B 11.2mm @ 0.18 cum per 10 sqm cum 86.40 1288.03 111,285.79
( Avg. of 5-7 mm & 2.36-5mm)
Binding Material @ 0.06 cum per 10 sqm cum 28.80 1040.53 29,967.26
for Grading 2 material (size 2.36mm &
below having PI value 2-6%
Water Kl 144.00 100.00 14,400.00
Page 89 of 149
Data Sheet
S. No. Index
RBR- Description of item Unit Qty Rate Amount
Code
CCP
V-5 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates
conforming to IS : 383, mixed in a concrete mixer of not less than 0.2 cum capacity and
appropriate weigh batcher using approved mix design, laid in approved fixed side formwork
(steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates
including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes,
compacted using needle, screed and plate vibrators and finished in continuous operation
including provision of contraction and expansion and construction joints, applying debonding
strips, primer, sealant, dowel bars, admixtures as approved, curing of concrete slabs for 14-
days, curing compound (where specified) and water finishing to lines and grade as per drawing
and Technical Specification Clause 1501 MORD including overhead charges & Contractors
profit but excluding VAT and seigniorage charges
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a) Labour
Mason (1st class) day 5.00 350.00 1,750.00
Mason (2nd class) day 5.00 320.00 1,600.00
Mazdoor (unskilled) day 150.00 280.00 42,000.00
Mazdoor(skilled) day 6.00 280.00 1,680.00
Surveyor day 2.00 500.00 1,000.00
Mazdoor (semi-skilled) day 6.00 280.00 1,680.00
Black smith for cutting of dowel bars day 1.00 320.00 320.00
including removal of burrs, fabrications &
fixing of dowel bars
Add 25 % MAA / AA 25% 12,427.50
b) Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 Hour 36.00 417.40 15,026.40
mixers) with weight batcher and suitable
capacity calibrated water tank
Needle vibrator Hour 9.00 140.60 1,265.40
Screed vibrator Hour 9.00 127.60 1,148.40
Plate vibrator Hour 9.00 42.00 378.00
Water tanker 6 Kl. Capacity Hour 5.00 624.00 3,120.00
Air compressor ( 1hour initial + 1 hour Hour 2.00 499.40 998.80
final)
c) Material
(I) Crushed stone coarse aggregates, grading
will be as per clause 1501.2.4.1 (Table
1500.1) of specifications @ 0.90 Cum/cum
of concrete
20mm Cum 44.55 2010.53 89,569.11
10mm Cum 22.95 1600.53 36,732.16
(ii) Sand as per IS:383 and conforming to cum 33.75 1095.53 36,974.14
clause 1500.2.4.2. @ 0.45 cum of concrete
Page 90 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
(iv) Polythene sheet 125 micron sqm 412.50 15.00 6,187.50
(v) Mild steel dowel bar 25mm dia of grade S
240.500 mm long 20 Nos. at culvert/bridge
slab and at construction joiont including 5
percent wastage
(4x20x0.500) + 5 per cent wastage = 42m Kg 161.91 44.50 7,205.00
@3.854 Kg per m = 161.91 kg.
Bitumen primer @ 200ml. Per joint for 23 t 0.005 43556.15 217.78
joints
Bitumenous sealant 800 ml. Per joint for 23 Litre 19.00 36.00 684.00
joints
Jute rope 12mm dia including 5 per cent m 90.00 5.00 450.00
wastage
Debonding strips 3.75m. (length) x 10mm m 90.00 9.00 810.00
(width) x 5 mm (thick) cut-out of rubber
fillter board of similar material including 5
per cent wastage
Polythene sheathing, covering 2/3rd dowel No 483.00 0.50 241.50
bars (20x23) and tight fit including 5 per
cent wastage
Plasticizer 0.5 per cent by weight of cement Litre 122.00 75.00 9,150.00
Joint filler board 20mm thick as per IS:1838 sqm 3.00 791.00 2,373.00
Unit = sqm
Taking output = 1750 sqm
a) Labour
Mate day -
Mazdoor (Unskilled) day 1.04 280.00 291.20
Add 25 % MAA / AA 25% 72.80
b) Machinery
Page 91 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
Hydraulic broom @ 1250 sqm per hour hour 1.40 357.00 499.80
Air compressor 210 cfm hour 1.40 499.40 699.16
Emulsion pressure distributor @1750 sqm hour 1.00 860.00 860.00
per hour
c) Material
Bitumen emulsion (RS-1) @ 0.275 kg per t 0.48 35608.50 17,092.08
sqm
Cost of 1750 sqm = (a+b+c+d+e) 19,515.04
Rate per sqm = a+b+c+d+e/1750 11.15
(e) d,e)Over head charges & contracots profit 1.56
@ 14.00% on (a+b+c+d)
Rate per Sqm 12.71
11 Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade
cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates
conforming to IS : 383, mixed in a concrete mixer of not less than 0.2 cum capacity and
appropriate weigh batcher using approved mix design, laid in approved fixed side formwork
(steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates
including levelling the formwork as per drawing), spreading the concrete with sholvels, rakes,
compacted using needle, screed and plate vibrators and finished in continuous operation
including provision of contraction and expansion and construction joints, applying debonding
strips, primer, sealant, dowel bars, admixtures as approved, curing of concrete slabs for 14-
days, curing compound (where specified) and water finishing to lines and grade as per drawing
and Technical Specification Clause 1501 MORD including overhead charges & Contractors
profit but excluding VAT and seigniorage charges
Unit = cum
Taking output = 75cum (172.50 t)
(100x3.75 x 0.200)
a Labour
Mason (1st class) day 5.00 350.00 1,750.00
Mason (2nd class) day 5.00 320.00 1,600.00
Mazdoor (unskilled) day 150.00 280.00 42,000.00
Mazdoor(skilled) day 6.00 280.00 1,680.00
Surveyor day 2.00 500.00 1,000.00
Mazdoor (semi-skilled) day 6.00 320.00 1,920.00
Black smith for cutting of dowel bars day 1.00 320.00 320.00
including removal of burrs, fabrications &
fixing of dowel bars
Add 25 % MAA / AA 25% 592.50 12,567.50
b Machinery
Concrete mixer 0.28/0.40 cum capacity ( 6 Hour 36.00 417.40 15,026.40
mixers) with weight batcher and suitable
capacity calibrated water tank
Needle vibrator Hour 9.00 152.20 1,369.80
Screed vibrator Hour 9.00 137.50 1,237.50
Plate vibrator Hour 9.00 48.00 432.00
Water tanker 6 Kl. Capacity Hour 5.00 624.00 3,120.00
Page 92 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
Air compressor ( 1hour initial + 1 hour Hour 2.00 499.40 998.80
final)
c Material 0.00
Crushed stone coarse aggregates, grading 0.00
will be as per clause 1501.2.4.1 (Table
1500.1) of specifications @ 0.90 Cum/cum
of concrete
20mm Cum 44.55 2010.53 89,569.11
10mm Cum 22.95 1600.53 36,732.16
Sand as per IS:383 and conforming to cum 33.75 410.26 13,846.28
clause 1500.2.4.2. @ 0.45 cum of concrete
Joint filler board 20mm thick as per IS:1838 sqm 3.00 791.00 2,373.00
(4x3.75x0.200 = 3 sqm)
383,956.49
d Form work @ 3% on (a+b+c) 3% 11,518.69
Cost for 75 cum = a+b+c+d 395,475.18
Rate per Cum = (a+b+c+d+e)/75 5,273.00
Over head charges & contracots profit @ 14% 738.22
14.00% on (a+b+c+d)
Rate per Cum 6,013.22
Rate per Cum excluding VAT
Page 93 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
12 302.3. Earth work excation for road way in hard rock with (requiring blasting) by
5 drilling , blasting and breaking, trimming of bottom and side slopes in
accordacne with requirements of lines, grades and corss sections, loading and
disposal of cut rock with a lift upto 1.50m and leads upto 1000m as per
technical specification. clause 302.3.5.
Unit = cum
Taking output = 180 cum
a) Labour
Mate Day 0.22 320.00 70.40
Mazdoor ( Unskilled) Day 3.00 280.00 840.00
Driller Day 2.00 400.00 800.00
Blaster Day 0.25 400.00 100.00
Add Agency Allowance (A.A) @ 25% 452.60
b) Machinery
Dozer D-50 for spreading @ 200cum/H Hour 6.00 2511.70 15070.20
Air compressor 210 cfm Hour 6.00 499.40 2996.40
Front end loader 1 cum bucket capacity Hour 6.00 1646.00 9876.00
Tipper 5.50 cum Capacity Hour 16.00 877.30 14036.80
c) Material
Gelatine 80 per cent Kg 70.00 73.00 5110.00
Electric Detonators @ 1 detonator for 2 each 252.00 4.00 1008.00
gelatine sticks of 285 gm of each.
Credit for excavated rock found suitable for Cum 90.00 0.00 0.00
use cum @ 50 per cent quanity blasted.
Total 50360.40
Rate per cum =(a+b+c)/180 279.78
Over head charges @ 14% 39.17
sundries
318.95
13 Modified Penetration Macadam
Construction of penetration macadam over prepared base by providing a layer of compacted
crushed coarse aggregate using chips spreader with alternate applications of bituminous binder
and key aggregates and rolling with a three wheel 80-100 kN static roller as per Tech.
Specification No 506 MORD.
B 75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum)
(I) Bitumen (S-90)
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.000 280.00 2240.00
Mazdoor (Skilled) day 2.400 280.00 672.00
b) Machinery 0.00
Hydraulic self propelled chip spreader both hour 6.000 2567.00 15402.00
for aggregates and key aggregates @ 1500
sqm per hour for 4500 x 2 sqm = 9000 sqm
By Mechanical Means
Taking out put = 8200 Sqm (205Cum) (450
tonnes)
a) Labour
Mate day 0.84 350.00 294.00
Mazdoor working withHMP, Mechanical day 14.00 280.00 3920.00
brrom, paver, roller, asphalt cutter and
assistance for setting oulines, levels and
layout of construction.
Skilled Mazddor for checking line and day 5.00 280.00 1400.00
levesl
Add Agency allowence 25% 1403.50
b) Machinery
HMP 40 -60 TPH hour 12.00 19120.00 229440.00
Electric generator set 250 KVA hour 6.00 1850.00 11100.00
Front end loader 1cum bucket capacity hour 6.00 1646.00 9876.00
Paver finisher @ 100 TPH hour 4.80 11441.00 54916.80
Three wheel 80-100 kN static roller hour 6.00 1038.40 6230.40
c) Materials
Cost of materials
Crushed stone chips of 13.2mm to 5.6mm cum 276.75 1483.03 410428.55
size @ 0.34 cum per 10 sqm. ( 66% of
11.20 mm HBG chips and 34 % of 5 to 7
mm HBG chips
Page 95 of 149
Data Sheet
S. No. Index Description of item Unit Qty Rate Amount
Code
Bitumen 60/70 grade @ 14.60 Kg per 10 MT 19.48 43556.15 848473.79
sqm
Basic rate of OGPC for 8200 Sqm 1577483.04
Basic rate of OGPC per Sqm 192.38
e) Over head chaes & Contractors profit @ 26.93
14.00% excluding VAT
Rate per sqm 219.31
Page 96 of 149
Data Sheet
xx
Page 97 of 149
Data Sheet
126
45
189
Page 98 of 149
Data Sheet
xx
Page 99 of 149
Data Sheet
60-63 mm
IRC HBG
Metal , 40-45
mm IRC HBG
Metal ,19-22
mm IRC HBG
Metal , stone
screenings
Type B 11.2
mm for
Binding Material @ 0.06 cum per 10 sqm for Grading 2 material size 2.36mm & below having PI val
26250
1.44
5932.12
erial size 2.36mm & below having PI value 2-6% ( 66% stone dust +34% Gravel )-> Stone dust 66% -->
Excavation of structures:
1 Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal up to a
lead of 50 m, dressing of sides and bottom and backfilling in trenches with
excavated suitable material as per Technical Specification 305 MORD / 304
MORTH ,including overhead charges & Contractors profit but excluding VAT
& Seigniorage charges.
S. Index Amount
Description of item Unit Qty Rate
No. Code
2 RBR- Providing concrete for plain concrete M 10 grade in open foundations using 40
FNDN-4 mm nominal size Graded hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD
and 1500, 1700 & 2100 MORTH ,including overhead charges & Contractors
profit but excluding VAT& Seigniorage charges for Leveling Coarse
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5800.00 1276.00
Coarse sand cum 0.45 1095.53 492.99
40 mm aggregate cum 0.9 1515.53 1363.98
Water kl 1.2 100.00 120.00
(b) Labour
Mate day -
Mason (1st Class) day 0.10 350.00 35.00
Mazdoor (Unskilled) day 1.39 280.00 389.20
Add 25 % MAA / AA 25% 106.05
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum hour 0.40 417.40 166.96
capacity fitted with water measuring device and
preferably also with load cell.
Water tanker 6 kl capacity hour 0.13 624.00 81.12
4031.30
(d) Formwork @ 4% on cost of material, labour 0.00% 0.00
and machinery (a+b+c)
e). 4031.30
Add 14% for Over head charges & Contractors profit (excl. 4% 14% 564.38
VAT per
Rate ) cum = a+b+c+d+e+f Rs 4595.68
3 RBR- Providing and Laying Reinforced Cement
PCVT-3 Concrete Pipe NP3 as per design.
Providing and laying reinforced cement concrete pipe NP3 for culverts on first
class bedding of granular material including fixing collar with cement mortar
1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head wall and parapets. Tech Specification Clause 1106
MORD ,including overhead charges & Contractors profit but excluding VAT &
Seigniorage charges
Unit = m
Taking output = 7.5 m
(3 pipes of 2.5 m length each)
iii) 600 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.15 350.00 52.50
Mazdoor (Unskilled) day 1.25 280.00 350.00
149109
S. Index Amount
Description of item Unit Qty Rate
No. Code
Add 25 % MAA / AA 25% 100.63
Laying & fixing of Pipes with colors in position rm 402.50
including lifting, aligning etc.,
Deduct 20% for 600 mm dia pipes -80.50
b) Material
Sand at site cum 0.024 1095.53 26.29
Cement at site t 0.018 5800.00 104.40
RCC pipe NP3 pipe m 7.50 2844.09 21330.68
RCC pipe NP3 collar at site nos 2.00 427.59 855.18
c). 22638.55
Add 14% for Over head charges & Contractors profit (excl. 4% 14% 3169.40
VATfor
Cost ) 7.5 m = a+b+c 25807.95
Rate per m = (a+b+c)/7.5 3441.06
Rate per m Rs. 3441.06
B 1000 mm dia
a) Labour
Mate day -
Mason (1st Class) day 0.25 350.00 87.50
Mazdoor (Unskilled) day 2.09 280.00 585.20
Add 25 % MAA / AA 0.25 168.18
Laying & fixing of Pipes with colors in position rm 672.70
including lifting, aligning etc.,
b) Material
Sand at site cum 0.04 1095.53 43.82
Cement at site t 0.03 5800.00 174.00
RCC pipe NP3 pipe including collar at site m 7.50 5912.79 44345.93
cost of RCC NP3 collar nos 2.00 1077.18 2154.36
c&d) Overheads & Contractors Profit 14.00% 6658.26
Cost for 7.5 m = a+b+c+d 54217.25
Rate per m = (a+b+c+d)/7.5 7228.97
5 Cement Mortar (1 : 5)
Unit : 1cum
A. MATERIALS:
Cement kg. 288.00 5800.00 1670.40
Sand (including 5% wastage) cum 1.05 1095.53 1150.31
Seigniorage charges for sand cum 1.05 0
B. MACHINERY
- Nil - -
C. LABOUR:
Man mazdoor for mixing mortar day 0.20 280.00 56.00
Grand Total 2878.71
6 Plastering with CM (1:5), 12 mm thick
including cost and conveyance of all materials
and all labour charges.etc complete.
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5) cum 0.150 2878.71 431.81
Seigniorage charges for F.A cum 0.150
B. LABOUR:
149110
S. Index Amount
Description of item Unit Qty Rate
No. Code
Mason 1st class day 0.60 350.00 210.00
Mazdoor (unskilled) day 0.96 280.00 268.80
Grand Total 3791.32
Add 14% for Over head charges & Contractors 14% 530.78
profit (excl. 4% VAT )
Plain cement concrete M15grade (Nominal mix) using 40,20 & 10mm metal
mechanically mixed in substructure complete as per drawings and technical
specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500,
8 1700 & 2200 MORTH ,including overhead charges & Contractors profit but
excluding VAT & Seigniorage chares. for Abutments, Piers, cut-off walls
above Bed Level
Note : Water for concrete : A provision for cost of water may be added at 1.2
kl / 1 cum (including curing purpose) keeping the site conditions
149111
S. Index Amount
Description of item Unit Qty Rate
No. Code
Coarse Aggregate : Single grade nominal size can also be used instead of graded
metal, keeping the site conditions in view
For height up to 5 m
Unit = cum
P.C.C grade M15 (Nominal mix) MORTH
for Abutments, Piers, cut-off walls above
Bed Level
Unit = cum
(a) Material
Cement t 0.275 5800.00 1595.00
Coarse sand cum 0.480 1095.53 525.85
40 mm aggregate cum 0.480 1515.53 727.45
20 mm aggregate cum 0.240 2010.53 482.53
10 mm aggregate cum 0.080 1600.53 128.04
Water kl 1.2 0 0.00
(b) Labour 0.00
Mate day -
Mason (1st Class) day 0.100 350.00 35.00
Mazdoor (Unskilled) day 1.390 280.00 389.20
Add 25 % MAA / AA 25% 106.05
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 370 148.00
Generator 33 KVA hour 0.000 0 0.00
Water tanker 6Kl capacity hour 0.130 372 48.36
4187.48
(d) Formwork @ 10% on cost of material, 10.00% 418.75
labour and machinery (a+b+c)
e). 4606.23
Add 14% for Over head charges & Contractors profit (excl. 4% 644.87
VAT per
Rate ) cum = a+b+c+d+e+f 5253.10
Dismatling of existing structures like culverts, bridges, retaining walls and other
structure comprising of masonary, cement concrete, wood work, steel work,
including T & P and scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000m as per Technical specification clause
202.1
Unit = Cum
Taking output = 125 Cum
By Mechanical Means
A. Cement concrete
(a) Labour
Mate day 0.02 350.00 7.00
Mazdoor (Unskilled) day 0.5 280.00 140.00
Add agency allowance 25%
(b) Machinery
Air compressor 210 cfm with 2 leads of hour hour 499.40 374.55
pneumatic breaker @ 1.50 cum per hour 0.75
149112
S. Index Amount
Description of item Unit Qty Rate
No. Code
Tractor with trolley hour 0.27 415.00 112.05
633.60
C) over heads @ 10% on (a+b) 63.36
d) Contractor's profit @ 14% (a+b+c) 97.57
Cost for 1.25 cum = a+b+c+d 794.53
Sundries
Rate per 1 cum = (a+b+c+d)/ 1.25 635.63
Providing weep holes in brick masonry/stone masonry, plain/reinforced concrete
abutment, wing wall, return wall with 100 mm dia AC pipe extending through
the full width of the structures with slope of 1(V):20(H) towards drawing face
complete as per drawings
Unit = Nos
Taking output = 30 Nos
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
(a) Material
S. Index Amount
Description of item Unit Qty Rate
No. Code
15 RBR- Providing and laying reinforced cement concrete M20 grade
SPST-1 (Design Mix) using 20 & 10mm metal mechanically mixed in
superstructure as per drawing and technical specifications Clauses
800, 1205.4 and 1205.5 MORD including overhead charges &
Contractors profit but excluding VAT& Seigniorage charges upto
5m height.
15601.8
149115
149116
Rayapalli_Vangalamadugu
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps t 1.05 45000.00 47250.00
and wastage
Binding wire kg 6.00 70.00 420.00
(b) Labour for cutting, bending, shifting to site,
tying and placing in position
Mate day -
Blacksmith day 2.00 350.00 700.00
Mazdoor (Unskilled) day 6.40 280.00 1792.00
Add 25 % MAA / AA 0.00% 0.00
c&d) Overheads & Contractors Profit 0.00% 0.00
Rate per t = a+b+c+d 50162.00
RBR 2 Earthwork in excavation for structures as per drawing and technical specifications
- Clause 305.1 including setting out, construction of shoring and bracing, removal of
FND stumps and other deleterious material and disposal upto a lead of 50 m, dressing of
N-1 sides and bottom and backfilling in trenches with excavated suitable material as per
Technical Specification 305 MORD / 304 MORTH ,including overhead charges &
Contractors profit but excluding VAT.
P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5800.00 1276.00
Coarse sand cum 0.45 1095.53 492.99
40 mm aggregate cum 0.90 1515.53 1363.98
Water kl 1.20 0.00 0.00
Road Furniture-Data
Rayapalli_Vangalamadugu
Road Furniture-Data
Rayapalli_Vangalamadugu
Unit = Each
Taking output = one traffic sign
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 101.92 12.84
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter cum 0.126 4212.03 530.72
11
(iii) Painting two coats including prime coat
on concrete surface with Epoxy Paint as per
specifications
As per item No. 9 of this Chapter sqm 0.46 85.75 39.44
(a) labour (For fixing at site)
Mate day -
Mazdoor (Unskilled) day 0.26 280.00 72.80
Add 25 % MAA / AA 25.00% 18.20
b) Material
Support of M.S. Sheet tube
(I) 47 mm x 47 mm x 12 SWG Sheet 3050 mm kg 12.40 44.50 551.80
long
(II) Angle iron 50 x 50 x 6 mm for hold fast kg 1.06 44.50 47.17
including 5% wastage
Add 3% cost of MS Sheet tube 12 SWG and 17.97
angle irons towards the cost of fabrication,
drilling holes, nuts and bolts etc.
(III) 1.5 mm thick M.S. Sheet duly painted with
stove enameled paint including lettering, signs,
border, message with reflective tape of
engineering grade required size, shade and
(0.36 Sqm. X 0.0015X7850 Kg/cum) Kg 4.24 44.50 188.64
(vi) 600 mm x 600 mm square sqm 0.36
(c) Machinery
Tractor with trolley hour 0.08 415.00 33.20
d&e) Overheads & Contractors Profit 14.00% 211.79
Rate per traffic sign = (i+ii+iii+a+b+c+d+e) 1724.57
Note : 1. Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site
requirement and in accordance with IRC-67.
Road Furniture-Data
Rayapalli_Vangalamadugu
Unit = each
Take Output = 0.9 sqm
(i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.126 101.92 12.84
(ii) Cement concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter cum 0.126 4212.03 530.72
11
(iii) Painting on M.S. tube post with primer
and two coat of epoxy paint as per
specifications
As per item No.9 of Chapter 10 sqm 0.59 85.75 50.59
(a) labour (For fixing at site)
Mate day -
Mazdoor (Unskilled) day 0.26 280.00 72.80
Add 25 % MAA / AA 25.00% 18.20
b) Material
(i) Support of MS sheet tube
47 mm x 47 mm of 12 SWG sheet 3050 mm kg 12.40 44.50 551.80
long
(ii) Angle iron 50 x 50 x 6 mm for lugs kg 1.06 44.50 47.17
including 5% wastage
Road Furniture-Data
Rayapalli_Vangalamadugu
(c) Machinery
Tractor with trolley hour 0.08 415.00 33.20
d&e) Overheads & Contractors Profit 14.00% 275.10
Cost for 0.9 sqm = (i+ii+iii+a+b+c+d+e) 2240.07
Rate per sqm (for sign having area upto 0.9 2488.97
sqm) = (i+ii+iii+a+b+c+d+e)/0.90
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day -
Painter (1st Class) day 3.00 350.00 1050.00
Painter Assistant day
Mazdoor (Unskilled) day 2.20 280.00 616.00
Add 25 % MAA / AA 25.00% 416.50
b) Material
Cement Primer as per specifications litre 3.00 134.00 402.00
Paint conforming to requirement of Clause litre 6.00 244.00 1464.00
1701.3.8
Add for scaffolding @ 1 per cent of labour cost
where
Filling required
Material on Paint Cost
c&d) Overheads & Contractors Profit
Cost for 40 sqm = a+b+c+d 3948.50
Rate per sqm = (a+b+c+d)/40 98.71
RBR 9 Painting on Concrete/Steel Surfaces with
- Epoxy
TSR Painting two coats including prime coat with epoxy paint of approved brand on
A-9 concrete/steel surfaces after through cleaning of surface to give an even shade as per
drawing and Technical Specification Clause 1701 MORD
Unit = sqm
Road Furniture-Data
Rayapalli_Vangalamadugu
Unit = each
Taking output = 14 Nos.
a) M-15 grade of concrete
As per item No. 5 (i) or (ii) of Chapter 12 cum 3.77 4212.03 15879.36
b) Steel reinforcement @ 5 kg per sqm
As per item No. 6 of Chapter 12 kg 26.32 50.16 1320.26
c) Excavation in soil for foundation
As per item No. 1 of Chapter 11 cum 2.77 101.92 282.32
d) Painting two coats on concrete surface
As per item No.5 of Chapter 10 sqm 11.41 98.71 1126.31
e) lettering on km post (average 12 letters of 10
cm height each)
As per item No. 1 of Chapter 10 per cm high 1680.00 0.45 755.06
per letter
Road Furniture-Data
Rayapalli_Vangalamadugu
Unit = Each
Taking out put = one typical board
i) Excavation for foundation
As per item No. 1 of Chapter 11 cum 0.252 101.92 25.68
(ii) Cement Concrete M15 grade
As per item No. 4 (A) (iii) or (iv) of Chapter 11 cum 0.252 4212.03 1061.43
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 9 of Chapter 10 sqm 1.80 85.75 154.35
(iv) Printing new letters and figures of any
shade with synthetic enamel paint black or
any other approved colour to give an even
shade.
Logo Border 60x4x5 = 1200 per cm height per
letter
Figure 60x10 = 600 per cm height per letter
Road Furniture-Data
Rayapalli_Vangalamadugu
Road Furniture-Data
Rayapalli_Vangalamadugu
Road Furniture-Data
Rayapalli_Vangalamadugu
14.13
0.9
Road Furniture-Data
Rayapalli_Vangalamadugu
Road Furniture-Data
Hire/ Usage charges for plant and machinery as per 2012-13
Blasting charges 70
Loading unloading
Loading and Unloading for metal & Stone
Loading and Unloading for earth,Sand and
gravel
Seignrage charges
Earth/Gravel 22
Sand 40
Metal 50
VAT: 5% 0.05
Initial Rates
12 Gravel 98.00
27838.39
Lead charges of 2013-14
Metal Gravel & Sand pipes 1000 pipes 900 pipes 600
lead Rate lead Rate lead Rate lead Rate Rate
0.5 28.90 0.25 30.00 0.5 171.00 0.5 142.00 0.5 81.00 0.5
1 28.90 0.5 30.00 1 171.00 1 142.00 1 81.00 1
2 40.40 1 30.00 2 171.00 2 142.00 2 81.00 2
3 56.00 2 42.00 3 171.00 3 142.00 3 81.00 3
4 68.00 3 56.00 4 171.00 4 142.00 4 81.00 4
5 80.00 4 68.00 5 171.00 5 142.00 5 81.00 5
6 92.00 5 80.00 6 179.23 6 150.23 6 84.75 6
7 104.00 6 92.00 7 187.46 7 158.46 7 88.50 7
8 116.00 7 104.00 8 195.69 8 166.69 8 92.25 8
9 128.00 8 116.00 9 203.92 9 174.92 9 96.00 9
10 140.00 9 128.00 10 212.15 10 183.15 10 99.75 10
11 152.00 10 140.00 11 220.38 11 191.38 11 103.50 11
12 164.00 11 152.00 12 228.61 12 199.61 12 107.25 12
13 176.00 12 164.00 13 236.84 13 207.84 13 111.00 13
14 188.00 13 176.00 14 245.07 14 216.07 14 114.75 14
15 200.00 14 188.00 15 253.30 15 224.30 15 118.50 15
16 212.00 15 200.00 16 261.53 16 232.53 16 122.25 16
17 224.00 16 212.00 17 269.76 17 240.76 17 126.00 17
18 236.00 17 224.00 18 277.99 18 248.99 18 129.75 18
19 248.00 18 236.00 19 286.22 19 257.22 19 133.50 19
20 260.00 19 248.00 20 294.45 20 265.45 20 137.25 20
21 272.00 20 260.00 21 302.68 21 273.68 21 141.00 21
22 284.00 21 272.00 22 310.91 22 281.91 22 144.75 22
23 296.00 22 284.00 23 319.14 23 290.14 23 148.50 23
24 308.00 23 296.00 24 327.37 24 298.37 24 152.25 24
25 320.00 24 308.00 25 335.60 25 306.60 25 156.00 25
26 330.00 25 320.00 26 343.83 26 314.83 26 159.75 26
27 340.00 26 330.00 27 352.06 27 323.06 27 163.50 27
28 350.00 27 340.00 28 360.29 28 331.29 28 167.25 28
29 360.00 28 350.00 29 368.52 29 339.52 29 171.00 29
30 370.00 29 360.00 30 376.75 30 347.75 30 174.75 30
31 380.00 30 370.00 31 384.98 31 355.98 31 178.50 31
32 390.00 31 380.00 32 393.21 32 364.21 32 182.25 32
33 400.00 32 390.00 33 401.44 33 372.44 33 186.00 33
34 410.00 33 400.00 34 409.67 34 380.67 34 189.75 34
35 420.00 34 410.00 35 417.90 35 388.90 35 193.50 35
36 430.00 35 420.00 36 426.13 36 397.13 36 197.25 36
37 440.00 36 430.00 37 434.36 37 405.36 37 201.00 37
38 450.00 37 440.00 38 442.59 38 413.59 38 204.75 38
39 460.00 38 450.00 39 450.82 39 421.82 39 208.50 39
40 470.00 39 460.00 40 459.05 40 430.05 40 212.25 40
41 480.00 40 470.00 41 467.28 41 438.28 41 216.00 41
42 490.00 41 480.00 42 475.51 42 446.51 42 219.75 42
43 500.00 42 490.00 43 483.74 43 454.74 43 223.50 43
44 510.00 43 500.00 44 491.97 44 462.97 44 227.25 44
45 520.00 44 510.00 45 500.20 45 471.20 45 231.00 45
46 530.00 45 520.00 46 508.43 46 479.43 46 234.75 46
47 540.00 46 530.00 47 516.66 47 487.66 47 238.50 47
48 550.00 47 540.00 48 524.89 48 495.89 48 242.25 48
49 560.00 48 550.00 49 533.12 49 504.12 49 246.00 49
50 570.00 49 560.00 50 541.35 50 512.35 50 249.75 50
51 580.00 50 570.00 51 549.58 51 520.58 51 253.50 51
52 590.00 51 580.00 52 557.81 52 528.81 52 257.25 52
53 600.00 52 590.00 53 566.04 53 537.04 53 261.00 53
54 610.00 53 600.00 54 574.27 54 545.27 54 264.75 54
Metal Gravel & Sand pipes 1000 pipes 900 pipes 600
lead Rate lead Rate lead Rate lead Rate Rate
55 620.00 54 610.00 55 582.50 55 553.50 55 268.50 55
56 630.00 55 620.00 56 590.73 56 561.73 56 272.25 56
57 640.00 56 630.00 57 598.96 57 569.96 57 276.00 57
58 650.00 57 640.00 58 607.19 58 578.19 58 279.75 58
59 660.00 58 650.00 59 615.42 59 586.42 59 283.50 59
60 670.00 59 660.00 60 623.65 60 594.65 60 287.25 60
61 680.00 60 670.00 61 631.88 61 602.88 61 291.00 61
62 690.00 61 680.00 62 640.11 62 611.11 62 294.75 62
63 700.00 62 690.00 63 648.34 63 619.34 63 298.50 63
64 710.00 63 700.00 64 656.57 64 627.57 64 302.25 64
65 720.00 64 710.00 65 664.80 65 635.80 65 306.00 65
66 730.00 65 720.00 66 673.03 66 644.03 66 309.75 66
67 740.00 66 730.00 67 681.26 67 652.26 67 313.50 67
68 750.00 67 740.00 68 689.49 68 660.49 68 317.25 68
69 760.00 68 750.00 69 697.72 69 668.72 69 321.00 69
70 770.00 69 760.00 70 705.95 70 676.95 70 324.75 70
71 780.00 70 770.00 71 714.18 71 685.18 71 328.50 71
72 790.00 71 780.00 72 722.41 72 693.41 72 332.25 72
73 800.00 72 790.00 73 730.64 73 701.64 73 336.00 73
74 810.00 73 800.00 74 738.87 74 709.87 74 339.75 74
75 820.00 74 810.00 75 747.10 75 718.10 75 343.50 75
76 830.00 75 820.00 76 755.33 76 726.33 76 347.25 76
77 840.00 76 830.00 77 763.56 77 734.56 77 351.00 77
78 850.00 77 840.00 78 771.79 78 742.79 78 354.75 78
79 860.00 78 850.00 79 780.02 79 751.02 79 358.50 79
80 870.00 79 860.00 80 788.25 80 759.25 80 362.25 80
81 880.00 80 870.00 81 796.48 81 767.48 81 366.00 81
82 890.00 81 880.00 82 804.71 82 775.71 82 369.75 82
83 900.00 82 890.00 83 812.94 83 783.94 83 373.50 83
84 910.00 83 900.00 84 821.17 84 792.17 84 377.25 84
85 920.00 84 910.00 85 829.40 85 800.40 85 381.00 85
86 930.00 85 920.00 86 837.63 86 808.63 86 384.75 86
87 940.00 86 930.00 87 845.86 87 816.86 87 388.50 87
88 950.00 87 940.00 88 854.09 88 825.09 88 392.25 88
89 960.00 88 950.00 89 862.32 89 833.32 89 396.00 89
90 970.00 89 960.00 90 870.55 90 841.55 90 399.75 90
91 980.00 90 970.00 91 878.78 91 849.78 91 403.50 91
92 990.00 91 980.00 92 887.01 92 858.01 92 407.25 92
93 1000.00 92 990.00 93 895.24 93 866.24 93 411.00 93
94 1010.00 93 1000.00 94 903.47 94 874.47 94 414.75 94
95 1020.00 94 1010.00 95 911.70 95 882.70 95 418.50 95
96 1030.00 95 1020.00 96 919.93 96 890.93 96 422.25 96
97 1040.00 96 1030.00 97 928.16 97 899.16 97 426.00 97
98 1050.00 97 1040.00 98 936.39 98 907.39 98 429.75 98
99 1060.00 98 1050.00 99 944.62 99 915.62 99 433.50 99
100 1070.00 99 1060.00 100 952.85 100 923.85 100 437.25 100
101 1080.00 100 1070.00 101 961.08 101 932.08 101 441.00 101
102 1090.00 101 1080.00 102 969.31 102 940.31 102 444.75 102
103 1100.00 102 1090.00 103 977.54 103 948.54 103 448.50 103
104 1110.00 103 1100.00 104 985.77 104 956.77 104 452.25 104
105 1120.00 104 1110.00 105 994.00 105 965.00 105 456.00 105
106 1130.00 105 1120.00 106 1002.23 106 973.23 106 459.75 106
107 1140.00 106 1130.00 107 1010.46 107 981.46 107 463.50 107
108 1150.00 107 1140.00 108 1018.69 108 989.69 108 467.25 108
109 1160.00 108 1150.00 109 1026.92 109 997.92 109 471.00 109
110 1170.00 109 1160.00 110 1035.15 110 1006.15 110 474.75 110
Metal Gravel & Sand pipes 1000 pipes 900 pipes 600
lead Rate lead Rate lead Rate lead Rate Rate
111 1180.00 110 1170.00 111 1043.38 111 1014.38 111 478.50 111
112 1190.00 111 1180.00 112 1051.61 112 1022.61 112 482.25 112
113 1200.00 112 1190.00 113 1059.84 113 1030.84 113 486.00 113
114 1210.00 113 1200.00 114 1068.07 114 1039.07 114 489.75 114
115 1220.00 114 1210.00 115 1076.30 115 1047.30 115 493.50 115
116 1230.00 115 1220.00 116 1084.53 116 1055.53 116 497.25 116
117 1240.00 116 1230.00 117 1092.76 117 1063.76 117 501.00 117
118 1250.00 117 1240.00 118 1100.99 118 1071.99 118 504.75 118
119 1260.00 118 1250.00 119 1109.22 119 1080.22 119 508.50 119
120 1270.00 119 1260.00 120 1117.45 120 1088.45 120 512.25 120
121 1280.00 120 1270.00 121 1125.68 121 1096.68 121 516.00 121
122 1290.00 121 1280.00 122 1133.91 122 1104.91 122 519.75 122
123 1300.00 122 1290.00 123 1142.14 123 1113.14 123 523.50 123
124 1310.00 123 1300.00 124 1150.37 124 1121.37 124 527.25 124
125 1320.00 124 1310.00 125 1158.60 125 1129.60 125 531.00 125
126 1330.00 125 1320.00 126 1166.83 126 1137.83 126 534.75 126
127 1340.00 126 1330.00 127 1175.06 127 1146.06 127 538.50 127
128 1350.00 127 1340.00 128 1183.29 128 1154.29 128 542.25 128
129 1360.00 128 1350.00 129 1191.52 129 1162.52 129 546.00 129
130 1370.00 129 1360.00 130 1199.75 130 1170.75 130 549.75 130
131 1380.00 130 1370.00 131 1207.98 131 1178.98 131 553.50 131
132 1390.00 131 1380.00 132 1216.21 132 1187.21 132 557.25 132
133 1400.00 132 1390.00 133 1224.44 133 1195.44 133 561.00 133
134 1410.00 133 1400.00 134 1232.67 134 1203.67 134 564.75 134
135 1420.00 134 1410.00 135 1240.90 135 1211.90 135 568.50 135
136 1430.00 135 1420.00 136 1249.13 136 1220.13 136 572.25 136
137 1440.00 136 1430.00 137 1257.36 137 1228.36 137 576.00 137
138 1450.00 137 1440.00 138 1265.59 138 1236.59 138 579.75 138
139 1460.00 138 1450.00 139 1273.82 139 1244.82 139 583.50 139
140 1470.00 139 1460.00 140 1282.05 140 1253.05 140 587.25 140
141 1480.00 140 1470.00 141 1290.28 141 1261.28 141 591.00 141
142 1490.00 141 1480.00 142 1298.51 142 1269.51 142 594.75 142
143 1500.00 142 1490.00 143 1306.74 143 1277.74 143 598.50 143
144 1510.00 143 1500.00 144 1314.97 144 1285.97 144 602.25 144
145 1520.00 144 1510.00 145 1323.20 145 1294.20 145 606.00 145
146 1530.00 145 1520.00 146 1331.43 146 1302.43 146 609.75 146
147 1540.00 146 1530.00 147 1339.66 147 1310.66 147 613.50 147
148 1550.00 147 1540.00 148 1347.89 148 1318.89 148 617.25 148
149 1560.00 148 1550.00 149 1356.12 149 1327.12 149 621.00 149
150 1570.00 149 1560.00 150 1364.35 150 1335.35 150 624.75 150
pipes 450
Rate
49.00 5 SAND 43.86 243.86
49.00 50 METAL 474.65 175.4386 279.10 244.8246
49.00
49.00
49.00
49.00
50.69
52.38
54.07
55.76
57.45
59.14
60.83
62.52
64.21
65.90
67.59
69.28
70.97
72.66
74.35
76.04
77.73
79.42
81.11
82.80
84.49
86.18
87.87
89.56
91.25
92.94
94.63
96.32
98.01
99.70
101.39
103.08
104.77
106.46
108.15
109.84
111.53
113.22
114.91
116.60
118.29
119.98
121.67
123.36
125.05
126.74
128.43
130.12
131.81
pipes 450
Rate
133.50
135.19
136.88
138.57
140.26
141.95
143.64
145.33
147.02
148.71
150.40
152.09
153.78
155.47
157.16
158.85
160.54
162.23
163.92
165.61
167.30
168.99
170.68
172.37
174.06
175.75
177.44
179.13
180.82
182.51
184.20
185.89
187.58
189.27
190.96
192.65
194.34
196.03
197.72
199.41
201.10
202.79
204.48
206.17
207.86
209.55
211.24
212.93
214.62
216.31
218.00
219.69
221.38
223.07
224.76
226.45
pipes 450
Rate
228.14
229.83
231.52
233.21
234.90
236.59
238.28
239.97
241.66
243.35
245.04
246.73
248.42
250.11
251.80
253.49
255.18
256.87
258.56
260.25
261.94
263.63
265.32
267.01
268.70
270.39
272.08
273.77
275.46
277.15
278.84
280.53
282.22
283.91
285.60
287.29
288.98
290.67
292.36
294.05
Name of Work : “Ponnapudi-Utukur road To Pattapupalem" of Vidavalur Mandal in SPSR Nellore District
As per IS 458
300 50 0.78 1.53 0.0549779 2.4936 5100 5800.00 46000 44000.00 13.85 -4.99 8.86
450 65 0.78 1.9 0.1051648 2.908 5100 5800.00 46000 44000.00 26.5 -5.82 20.68
600 75 1.18 2.2 0.1590431 3.644 5100 5800.00 46000 44000.00 40.08 -7.29 32.79
700 85 1.18 4.87 0.2096228 6.6344 5100 5800.00 46000 44000.00 52.82 -13.27 39.55
900 100 2.66 11.55 0.3141593 15.596 5100 5800.00 46000 44000.00 79.17 -31.19 47.98
1000 115 2.66 15.7 0.4028307 20.244 5100 5800.00 46000 44000.00 101.51 -40.49 61.02
1200 125 3.55 21.25 0.5203263 27.35 5100 5800.00 46000 44000.00 131.12 -54.7 76.42
0.0731598
300 16 30 150 0.11 0.22 0.00653 0.3564 5100.00 5800.00 46000.00 44000.00 1.65 -0.71 0.94
450 19 35 200 0.15 0.6 0.01436 0.822 5100.00 5800.00 46000.00 44000.00 3.62 -1.64 1.98
600 19 40 200 0.23 1.05 0.02081 1.406 5100.00 5800.00 46000.00 44000.00 5.24 -2.81 2.43
700 19 45 200 0.23 1.85 0.02695 2.302 5100.00 5800.00 46000.00 44000.00 6.79 -4.6 2.19
900 19 55 200 0.33 2.25 0.04123 2.85 5100.00 5800.00 46000.00 44000.00 10.39 -5.7 4.69
1000 19 60 200 0.33 3.09 0.05006 3.7908 5100.00 5800.00 46000.00 44000.00 12.62 -7.58 5.04
1200 19 75 200 0.5 5.08 0.07365 6.1896 5100.00 5800.00 46000.00 44000.00 18.56 -12.38 6.18
S.No. Description As per DPR As per estimate
7 Prime coat
8 Tack coat
9 OGPC ( HMP)
10 Seal coat Type-A(Mechanical)
11 CC Pavement
s per estimate Remarks if any
deviation
Amount