You are on page 1of 2

Magnetic Bus Bracing Electrical Sector

Equipment Life Extension Low and Medium Voltage


and Modernization Power Circuit Breakers

Magnetic Influence Qualifying Bus Bracing Qualifying Bracing Upgrades high-power lab tests while doing
When electric currents pass IEEE C37.20.1 and IEEE C37.20.2 It is impractical to install qualification testing of numerous
through conductor systems, require manufacturers to test additional bracing and take the low voltage and medium voltage
they generate magnetic bus configurations to specific entire switchgear to a high- circuit breaker conversions.
fields. For two parallel round short circuit current ratings. power lab for qualification The same testing is utilized
conductors, the magnetic fields This ensures there is no testing. A more reasonable in the qualification of Eaton’s
are circular. Based on “the right movement that is mechanically approach is to perform new replacement power circuit
hand rule” the two conductors or electrically detrimental calculations and build sample breakers. This methodology has
repel each when the current to the bus or insulating bus structures based on the been successfully proven and
flows in opposite directions. components. Calculations calculations. The calculations tested by Eaton for over twenty
determine the location of indicate where additional years.
insulating components (bracing) braces should be added to
to prevent movement of the bus compensate for the increase Re-Qualification Process
conductors prior to test. High- in short circuit currents. The Eaton’s Power Breaker Center
power lab testing at the rated samples are tested in a high- has trained a number of Eaton’s
short circuit current parameters power lab. After testing, the Power Systems Engineers
verifies the calculations. As bus system is analyzed and the (PSE) on the details of bus
long as the switchgear is applied results correlated to the original bracing calculations due to the
within its original tested rating, calculations. This approach high demand for this service.
the bus bracing is sufficient. can save $3,000-$8,000 Eaton researches the existing
per switchgear structure as switchgear bus configuration
Ampere’s Law Bus Bracing Upgrades compared to replacing with new by visiting the customer’s
For alternating currents the equipment. site during an outage of the
Many power systems incur
fields are time-varying. The changes over time and the short switchgear requiring analysis.
magnetic fields create forces on circuit capability of the system 100% Confidence factor The calculations are performed
the conductors that are directly often exceeds the original rating Eaton’s Power Breaker Center and a report is generated to
proportional to the square of the switchgear. Modern has established a calculation determine if additional bracing
of the current and inversely circuit breaker technology methodology that yields is required. The report also
proportional to the conductor incorporated into conversions conservative results within indicates the location of the
separation. If unrestrained the can compensate for the high 5-10% of the actual lab test additional braces. The bracing
conductors can experience short circuit currents, but the measurements. Adjustments materials are designed,
substantial movement during a bus system usually requires can be made for copper or fabricated and sent to the
short circuit event. additional bracing to prevent aluminum bus, compensation customer’s site for installation
damage during a maximum for different insulating materials, by a qualified Eaton Service
short circuit event. A system different spacings between Engineer.
F =M 2 ×10 −7 i1i2 cannot be rated any higher than bus bars and the shape and
its lowest rated component. configuration of the bus New Certification Labels
l d
conductors. The calculations and The Engineer also attaches a
tests are based on using any label to each structure to certify
bus configuration and material, its new bus bracing rating. The
so the method is not specific new certification is backed
to any particular manufacturer’s by Eaton and is valid unless
bus design. The methodology additional changes are made to
has been tested in hundreds of the switchgear.
Fault Currents--10 Cycles
Dynamic Response - Fixed Ends
Imax/rms= 2.70
Peak Current= 97 KA

100,000 Max. Stress in PSI = 1,266,250


80,000 25.000
60,000 20.000

Deflection (inches)
40,000 15.000
20,000
10.000 A
5.000
0 B
1 11 21 31 41 51 61 71 81 91 101 111 121 131 141 151 161 171 181 0.000
-20,000
-5.000 C
-40,000 -10.000
-60,000 -15.000
-80,000 -20.000

0
9
19
28
37
46
56
65
74
83
93
102
111
120
130
139
148
157
167
-100,000

-120,000 Time (msec)


Phase A Currents Phase B Currents Phase C Currents

Three-Phase Short Circuit Fixed-Ends Beam Analysis


Three-phase fault waveforms are generated based on the required maximum The bus conductors in each vertical switchgear section are further analyzed as
short circuit rating for the new circuit breaker conversions and the associated beams with fixed ends to predict the possibility of the bus system reaching a
requirements of IEEE C37.20.1 or C37.20.2 and C37.59 switchgear standards. resonance condition. This is not a common occurrence, but it is possible and
The results of these calculations are used to generate the associated can cause catastrophic failure.
magnetic forces on the primary bus conductors in the switchgear.

Field Measurements Resonance Conditions


Each switchgear structure is de-energized and the bus system is grounded. Mechanical resonance can occur if the bus bracing is located at specific
Detailed measurements are taken of the bus system by an Eaton Service points that enhance the system’s vibration. Resonance, although rare, can
Engineer. The engineer also photographs each bus configuration and all occur in low voltage as well as medium voltage systems. Eaton’s analysis
existing insulation and bracing components. All data is submitted to the Eaton helps prevent incorrect bracing placement and reduces the propensity for
Power Systems Engineer (PSE) to perform the bus bracing study. resonance.

Bus Deflection (Simply Supported)


Maximum Stress in PSI = 103,416
8.0000
7.0000
Deflection (Inches)

6.0000
5.0000
4.0000
3.0000
2.0000
1.0000
0.0000
0 10 20 30 40
Span Distance (Inches)

Simply Supported Beam Analysis Bus Properly Braced


The bus conductors in each vertical switchgear section are analyzed as a Eaton uses a systems approach to bus bracing. We use processes that
uniformly loaded beam at various frequencies to determine there deflection. position braces at the optimum location, utilize proper materials and proven
Based on the general information, Eaton recommends limiting the deflection methods of installation. This results in a professional installation that provides
of bus components to 1/150th of the unsupported length to avoid damage to over 50 years of trouble-free service. It is also fully tested to the bracing
insulating components during a short circuit event. currents of the appropriate IEEE Standards and has very little or no corona
discharge. Contact your local Eaton representative or visit our website at
www.Eaton.com/ELEM for more information.

Eaton
1000 Eaton Boulevard
Cleveland, OH 44122
United States
Eaton.com

© 2017 Eaton
All Rights Reserved Eaton is a registered trademark.
Printed in USA
Publication No. PA182404EN All trademarks are property
June 2017 of their respective owners.

You might also like