*Calculation of Asphalt Pavement Structure in


AASHTO 1993*

*****************************************************************

I Project Information
Project Name:尼日利亚疏港路项目
Project Location:尼日利亚
Roadway Classification:Local
Estimated Completion Year:2020
Start Chainage:0
End Chainage:100
Pavement Type:新建沥青路面
Project Description:首都至港口

II Design Parameters
Design Period(Years):20
Reliability Level R(%):90
ZR:-1.282
Overall Standard Error S0:0.45
Initial Serviceability Index pi:4
Terminal Serviceability Index pt:2
Change in Serviceablity ∆PSI:2

III Traffic & Loading


AADTT(Vehicles / Day):1800
Traffic Growth Rate(%):1.5
Directional Distribution Factor DDF(%):50
Lane Distribution Factor LDF(%):80
Total Cumulative Heavy vehicles During Design period CHV(Vehicles):1600000
Load Equivalency Factor LEF:1
Total Design Equivalent Single Axle Loads ESALs:1600000

IV Pavement Structure and Material Parameters


Subgrade Resilient Modulus MR(psi):9000
Number of Structural Layers:3
No. Structural Layer Pavement Materials Thickness
Di(in.) Resilient Modulus(psi) Layer Coef. ai Drainage
Coef. mi
1 面层 沥青混凝土 4 400000
0.42 1.0
2 基层 水泥稳定碎石 6 320000
0.32 1.0
3 底基层 级配碎石 8 30000
0.11 1.1

V Calculation Analysis
No. Structural Layer Pavement Materials Calculated
Vallues of SN/Layer Allowable Vallues of SN/Layer Yes/No
1 面层 沥青混凝土 1.68 0.753
满足
2 基层 水泥稳定碎石 3.6 2.183
满足
3 底基层 级配碎石 4.568
3.399 满足

VI Recommended Pavement Structure


According to AASHTO guide for design of pavement structure (1993 edition), the
calculation results of pavement structure are as follows:
4in. 面层(沥青混凝土)+6in. 基层(水泥稳定碎石)+8in. 底基层(级配碎石) meets the
specification requirements!