DAILY PROGRESS REPORT

Client : Jindal Paradip Port Ltd. Project No :

Vessel : M.L. Chandrama Date : 2/17/2024


Location : Paradip DPR No : 2
Party Chief: Mr. Manoranjan Rath (Project Manager) Client Rep.: Mr. Debashish
Project Title Bathymetric and Geophysical Survey at Paradip Port, Odisha

Survey Personnel :
1. Mr. Amit Jurel 2. Mr. Vishtasp Mehta 3. Shubham Sutrakar 4. Dhanasekaran Narayan

1. Norbit MBES with 2. Norbit Positioning 3. Geopulse Sub- 4. Geometrics G882 5. Hypack and
backscatter System bottom Profiler Magnetometer Hysweep software
Equipment
6. CODA DA4G
7. Maglog software 8. Valeport SVP
acquisition

Time (hrs) Activities


From To

7:00 9:30 Survey team transit to Paradip


9:30 10:00 Check-in at hotel
10:00 11:45 Procurement of passes for port entry
11:45 12:15 Unloading of survey equipment from vehicle to boat at Jetty
Mobilization of MBES. Levelling of MBES mounting to check for any inclinations in presence of the client rep.
12:15 18:15
Installation of Norbit MBES transducer and positioning system
18:15 18:45 Survey team transit to hotel
18:45 23:59 Team standby at hotel

Survey Details Cumulative details


Geophysical and Bathymetric Survey 0 0

Plan for next 24 hours: Complete mobilization and commence function tests of survey equipment

Remarks:
Safety Statistics Weather Conditions
Daily Cumulative
Tool Box Talk 1 2
Safety Meetings 0
Remarks (if any):

Party Chief Client Representative