DAILY PROGRESS REPORT

Client : Jindal Paradip Port Ltd. Project No :

Vessel : M.L. Chandrama Date : 2/19/2024


Location : Paradip DPR No : 4
Party Chief: Mr. Manoranjan Rath (Project Manager) Client Rep.: Mr. Debashish
Project Title Bathymetric and Geophysical Survey at Paradip Port, Odisha

Survey Personnel :
1. Mr. Amit Jurel 2. Mr. Vishtasp Mehta 3. Shubham Sutrakar 4. Dhanasekaran Narayan

1. Norbit MBES with 2. Norbit Positioning 3. Geopulse Sub- 4. Geometrics G882 5. Hypack and
backscatter System bottom Profiler Magnetometer Hysweep software
Equipment
6. CODA DA4G
7. Maglog software 8. Valeport SVP
acquisition

Time (hrs) Activities


From To
23:59 7:00 Standby at hotel in Paradip
7:00 7:30 Team transit to jetty
7:30 8:00 Switched on MBES setup in presence of client rep
Setup of SBES (Bathy MF500) and calibration of MBES by comparing with SBES sounding and lead line
8:00 11:30 sounding. Results were found satisfactory by client rep. Sound velocity profile carried out twice, one in shallow
depth and the other inside the harbour.
Carried out GAMS (GPS Azimuth Measurement System) calibration to reduce the heading error in the Norbit
11:30 13:00
inbuilt navigation system

Carried out patch tests twice inside the harbour in front of client rep and the results were found agreeable . Run
13:00 19:30
two small test lines to check the calibration patch test values. All collected data handed over to the client rep.

19:30 20:00 Survey team transit to hotel


20:00 23:59 Team standby at hotel

Survey Details Cumulative details


Geophysical and Bathymetric Survey 0 0

Plan for next 24 hours: Planning of survey lines as per client's requirement and setup of magnetometer to run with MBES as per client rep
instruction

Remarks:
Safety Statistics Weather Conditions
Daily Cumulative
Tool Box Talk 1 4 Calm inside the harbour (inner channel)
Safety Meetings 0
Remarks (if any):

Party Chief Client Representative