PTTLNG Doc. No.

:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 1 of 13

PTTLNG Nong Fab LNG Receiving Terminal Project

Project Environmental Monitoring Plan

Doc. Class Z2

F1 IFF 04/04/2019 Issued for Final A.Capizzi C.Celebi G.Garbati

R1 IFR 10/10/2018 Issued For Review SHE P. Dentale G. Garbati

R1 IFR 31/07/2018 Issued For Review J. Lin P. Dentale G. Garbati

REV. STATUS DATE REVISION DESCRIPTION BY CHK. APPR.

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 2 of 13

Revision list:

Rev. Nr Modifications:
R1 First Issue
R1 Issued for Review
F1 Issued for Final

TABLE OF CONTENTS

1 SCOPE.......................................................................................................................................................... 4

2 PURPOSE..................................................................................................................................................... 4

3 REFERENCE DOCUMENTS........................................................................................................................ 4

4 RESPONSIBILITIES ..................................................................................................................................... 5

5 AIR QUALITY AT CONSTRUCTION PHASE.............................................................................................. 5

6 JOBSITE SURFACE WATER DRAIN SYSTEM.......................................................................................... 6


6.1 Excavation dewatering .......................................................................................................................... 6
6.2 Storm Water/Ground water Discharge ................................................................................................ 6
6.3 Hydro test effluent (pre-commissioning) ............................................................................................ 7
6.4 Flushing water (pre-commissioning) ................................................................................................... 7
6.5 Reporting ................................................................................................................................................ 7
6.6 Sampling and analysis methods for discharges to surface water ................................................... 8

7 SOIL QUALITY ............................................................................................................................................. 8

8 DIESEL ENGINE (STATIONARY AND MOBILE) EMISSIONS .................................................................. 9

9 NOISE ........................................................................................................................................................... 9

10 EXCEEDANCES ......................................................................................................................................... 10

11 METHODOLOGY OF ANALYSIS .............................................................................................................. 10


11.1 Environmental Baseline Sampling ..................................................................................................... 10
11.2 Methodology of AMBIENT AIR QUALITY .......................................................................................... 10
11.3 Methodology of NOISE LEVEL ........................................................................................................... 11

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 3 of 13

11.4 Methodology of GROUNDWATER QUALITY ..................................................................................... 11


11.5 Methodology of SOIL QUALITY .......................................................................................................... 11
11.6 Methodology of WATER QUALITY ..................................................................................................... 12
11.7 Methodology of MARINE WATER QUALITY ...................................................................................... 12

12 ENVIRONMENTAL STANDARD OF ISO14001 ........................................................................................ 12

13 CLOSE-OUT FOR MEASURES OF MITIGATION AND MONITORING ................................................... 12

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 4 of 13

1 SCOPE

This plan defines the requirements for the environmental monitoring throughout the SITE during the site
construction and commissioning activities by the CONTRACTOR and their SUBCONTRACTORs at the
PTTLNG Receiving Terminal Project.

This plan addresses field implementation and controls for CONSTRUCTION ENVIRONMENTAL
MONITORING management during construction and commissioning as well as the processes for
monitoring and mitigation of construction activities that could potentially impact the environment.

This plan will be updated if conditions or CONSTRUCTION ENVIRONMENTAL MONITORING


requirements change.

2 PURPOSE

The Construction Environmental Monitoring Procedure establishes the requirements for the
environmental monitoring during the construction and commissioning activities. Periodic monitoring will be
carried out to identify any deleterious impacts on the environment.

This may include: noise monitoring at Jobsite boundary and at nearest residences and monitoring of
effluent from wastewater discharges from Jobsite.

The monitoring of waste management operations is described in the Construction Waste Management
Procedure; CONTRACTOR SUBCONTRACTORs shall provide project all necessary assistance to
facilitate the Project Environmental Monitoring Program.

3 REFERENCE DOCUMENTS
EXTERNAL REFERENCE
 Ministerial Regulation on the Prescribing of Standard for Administration and
Management of Occupational Safety, Health and Environment in relation to Hazardous
Chemicals, B.E. 2556 (A.D. 2013), Fire Prevention and Control, B.E. 2555 (A.D. 2012),
Machines.
 Ministerial Regulation on the prescribing of Standard for Administration and
Management of Occupational Safety, Health and Environment B.E. 2552 (A.D. 2009)
 Safety, Occupational Hygiene and Workplace Environment Act B.E. 2554 (2011)
 Occupational, Health and Environment Act B.E. 2554 (A.D. 2011)
 Ministerial Regulation on the Standard for Administration and Management of Safety,
Occupational Health and Working Environment in Relation to Construction work year/ 2009
 Labor Announcement Regarding PPE Standards / year 2011

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 5 of 13

 Public Health Act BE 2535 (1992)


 Factory Act BE 2535 (1992)
 Hazardous Substances Act BE 2535 (1992)
 Protective Measures for Operational Safety. Notification of Ministry of Industry
 No. 3 (B.E.2542 (A.D.1999)) issued under the Factory Act
 Notification of Industry - Industrial effluent standards B.E. 2560
 Announcement of National Environmental committee no. 27 B.E. 2549 type n. 5

PTTLNG REFERENCE
 Environmental Impact Assessment (EIA) Appendix E-1. (1602088-32016-PM-GE-028-F0)
 Approved PTTLNG’s EIA (approved February 27th, 2018 and April 28th, 2018).
 PTT Environmental Management Plan (1602088-32016-PM-RPT-103-F0)
 PTT Safety and Health Management Plan (1602088-32016-PM-RPT-113-F0)
 PTT Corporate Work Site Environmental Requirements. § 2.9. Health Hazards (1602088-
32016-PM-RPT-111)

CONTRACTOR REFERENCE
 Project SHE Plan (122018-SPCC-C-SH-PR-0001)
 Environmental Management Plan (122018-SPCC-C-SH-PR-0032)
 Environmental Procedures (122018-SPCC-C-SH-PR-0004)

4 RESPONSIBILITIES
CONTRACTOR shall be responsible for, but not limited to, the commissioning, start-up, activities as per
the requirements outlined in the Contract documents:
 Construction SUBCONTRACTOR(s);
 Construction Environmental Monitoring Services SUBCONTRACTOR. The above
Contractors shall provide CONTRACTOR all necessary assistance to facilitate the Project
environmental Monitoring Program.
CONTRACTOR will take responsibility all monitoring actions even through belonging to
SUBCONTRACTOR.
A summary of all environmental monitoring activity is outlined in the Environmental impact monitoring
schedule attached to the present PLAN. Refer to Attachment A.

5 AIR QUALITY AT CONSTRUCTION PHASE


The sources of dust are any activities from construction and transportation inside project site.
CONTRACTOR will arrange spray vehicle to spray water covering the construction area to control dust
suspension, and maintain equipment to reduce the pollution twice per day.
Regularly check and maintain the engine and machinery to reduce air emission.

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 6 of 13

6 JOBSITE SURFACE WATER DRAIN SYSTEM

6.1 EXCAVATION DEWATERING


The CONTRACTOR and earth work SUBCONTRACTORs shall be responsible for the monitoring of the
excavation dewatering discharges to the surface water drain systems in accordance with visual inspection
before pumping. Truck shall be equipped with suitable cover while transporting soil to approved area.
The Construction Environmental Monitoring Services SUBCONTRACTOR shall comply with all Project
Health and Safety procedures during the sampling process surrounded this Project workplace.

6.2 STORM WATER/GROUND WATER DISCHARGE


The Construction Environmental Monitoring Services SUBCONTRACTOR will perform both a monitoring
role to provide data for PTTLNG environmental personnel to evaluate prior to approving a release of
water from a sediment basin into existing external storm water sewer system and an auditing role to
document the quality of water being released.
The monitoring will be accomplished through onsite analysis prior to discharge and the auditing will be
accomplished by collecting samples concurrent with monitoring activities for offsite analysis.
CONTRACTOR will direct the Environmental Monitoring Services SUBCONTRACTOR on specific sample
locations (i.e., which pond outlet valve(s) to sample from).The Environmental Monitoring Services
SUBCONTRACTOR shall be responsible for the monitoring of the discharge of storm water (Jobsite
sedimentation basins.) in accordance with the requirements specified in the following table :

Monitoring Parameter Analysis /Monitoring method Monitoring Station Frequency


Discharge of • pH • pH monitored by pH Meter 2 Monitoring stations are Every month, in
stormwater • Suspended Solids • Evaporate suspended solids • Sediment pond at case of
between 103-105 ºC for 1 discharging into the sea discharge into
hour or • Polishing pond to receive the sea
approved method by relevant wastewater from Concrete
government agency. Batching Plant

The Environmental Monitoring Services SUBCONTRACTOR shall be responsible for the auditing the
discharge of storm water (Jobsite sedimentation basins) in accordance with the requirements specified in
the EASTERN INDUSTRIAL ESTATE authorized institute regular inspection table. (will be provided by
selected Construction Environmental Monitoring Services Contractor in due date ). On receipt of the test

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 7 of 13

results, PTTLNG may alter the monitoring schedule (i.e. parameters of high significance will be monitored
more frequently and parameters of low significance will be monitored less frequently).

6.3 HYDRO TEST EFFLUENT (PRE-COMMISSIONING)


CONTRACTOR shall be responsible for the monitoring of the discharge of hydro test water (water reused
for hydro test and flushing – excess routed to Permanent Operation Effluent Treatment Plant or
discharged to storm water drain system or disposed of offsite).
Due to the nature of hydro testing (high pressures), CONTRACTOR shall take particular care in
complying with all Project Health and Safety procedures during the monitoring of the hydro test activity.
If visual inspection identifies ‘oily’ sheen or turbidity, CONTRACTOR shall perform total petroleum
hydrocarbon (TPH) and/or total suspended solids (TSS) analysis.
CONTRACTOR shall not discharge water until results confirm water is in compliance with general
standards and THAI law standards identified as following sample table.

Analysis /Monitoring
Monitoring Parameter Monitoring Station Frequency
method
Effluent from Effluent from Hydrostatic Notification of Ministry of 1 Monitoring station Once time after
Hydrostatic Test Natural Resources and is the hydrostatic completed Hydro
Test • COD Environment: The Test discharging Test activity before
• Temperature Specification of Effluent point discharge to the sea
• pH Standard for a Factory,
• Oil and Grease Industrial Estate and
• Total Dissolved Solids Operating Factory Area
• Suspended Solid 2016 (B.E.2559).
• Residual Chlorine (Cl-)
• Total Iron (Fe)
• Nickel

6.4 FLUSHING WATER (PRE-COMMISSIONING)


CONTRACTOR and SUBCONTRACTORs shall be responsible for the monitoring of the discharge of
flushing water (water reused for hydrotesting and flushing – excess routed to Permanent Operation
Effluent Treatment Plant or discharged to storm water drain system or disposed of offsite)
CONTRACTOR shall take particular care in complying with all Project SHE procedures during the
monitoring of the flushing activity.
CONTRACTOR shall not discharge water until results confirm water is in compliance with EIA
requirements identified as above depicted in Paragraph—6.3 snapshot.

6.5 REPORTING
A monthly report of the sediment basin sampling (during the rainy season), excavation dewatering (during
the rainy season), discharge, hydrotest water discharge, and flushing water discharge (during
commissioning) monitoring shall be provided by the CONTRACTOR and the Construction Environmental
Monitoring Contractors and this shall include:
 Results of monitoring;

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 8 of 13

 Test methods used; and


 Comparison with Project and Thai standards.
 CONTRACTOR shall provide these monthly reports to PTTLNG formally.

6.6 SAMPLING AND ANALYSIS METHODS FOR DISCHARGES TO SURFACE WATER


CONTRACTOR submits the test methods to PTTLNG for approval. These test methods shall, as a
minimum, comply with Thai Environmental Regulation, and the PTTLNG Environmental Impact
Assessment regulated methods. The Main Contractors (CONTRACTOR and their SUBCONTRACTORs)
shall carry out quarterly reviews of the sampling and analysis test methods. CONTRACTOR and their
SUBCONTRACTOR shall submit details of the reviews (including any proposed changes) to PTTLNG
Authorized Representative for approval.

7 SOIL QUALITY

The Construction Environmental Monitoring Services Contractor shall be responsible for the sampling and
analysis of the soil quality (in areas of suspected contamination). CONTRACTOR will instruct the
Environmental Monitoring Services SUBCONTRACTOR on the locations required sampling and analysis.
To determine the potential contaminated locations, CONTRACTOR will refer to the PTTLNG
Environmental Impact Assessment Report.

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 9 of 13

8 DIESEL ENGINE (STATIONARY AND MOBILE) EMISSIONS


CONTRACTOR will inspect and monitor the operation of vehicles in accordance with the Construction
Environmental Monitoring Procedure. Stationary and mobile equipment including vehicles will be
inspected prior to be allowed to be used on the project site, in accordance with the Thai Environmental
Regulation, and the PTTLNG Environmental Impact Assessment. CONTRACTOR and
SUBCONTRACTORs shall comply with all the requirements specified in this procedure.
After the mobilization of a SUBCONTRACTOR, and / or the Environmental Monitoring Services,
SUBCONTRACTOR shall carry out the regular check and monitoring of diesel engine emissions: The
inspect standard as following sample table. If the value is not applied to actual requirement,
CONTRACTOR will recheck the value again while the CONTRACTOR performing this DIESEL ENGINE
EMISSIONS audit.

Vehicle type THAI Standard TIS General Standard(Smoke


1105-2535(1992) value, FSN)
Diesel engine 4.5 (New Vehicle) 4.5
Vehicle with new approved designed engine 4.0 4.0
and fuel system (after 01 July 1995)

Vehicle type THAI Standard (Smoke value, FSN) General Standard


(microgram/Nm3)
Engine in use (licensed) 5.0 (also should not exceed Ringelmann 5.0 (also should not exceed
before 01 July 1995 2 smoke value) Ringelmann 2 smoke value)
Engine in use (licensed) 4.5 (also should not exceed Ringelmann 4.5 (also should not exceed
after 01 July 1995 2 smoke value) Ringelmann 2 smoke value)

9 NOISE
Ambient noise and vibration emissions shall comply with the Thai Environmental Regulation, and the
PTTLNG Environmental Impact Assessment, as a minimum and these are described in the following
table:

Max allowable log equivalent (hourly) (dB(A))


Receptor Day-time Night-time
06.00-22.00 22.00-06.00
Residential, institutional 55 45
Industrial, commercial 70 70
Work Site 85 85

Noise monitoring will be carried out by certificate third party.

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 10 of 13

Resolution of noise complaints will be handled through the CONTRACTOR SHE Manager. In the event of
anticipated atypical noise events (e.g., steam blows, blasting), CONTRACTOR will notify the local villages
that such events may occur. Regular check and maintain the construction engine and machinery to
reduce the noise level. Provide ear muffs or ear plugs for workers working at site where receive over
noise level.

10 EXCEEDANCES
CONTRACTOR shall notify the exceeded evaluation to the PTTLNG’s Authorized Representative.
CONTRACTOR management will provide instruction to SUBCONTRACTORs on the necessary
countermeasures required to rectify the exceeded evaluation.
Limit of vehicle speed inside the construction area is 20 km/hr.
Maintain and check vehicles following up the manual guidebook every time.
Control hauling weight to be under the legal limits and provide equipment to contain shipment from falling
off the trucks to prevent damage to road surface.
Enforce truck drivers to follow the traffic regulations.
Provide traffic route system inside construction area and assign security officers to serve at entrance.
Repeated monitoring will be carried out at an appropriate interval in order to ensure that
the exceeded item is corrected.

11 METHODOLOGY OF ANALYSIS

11.1 ENVIRONMENTAL BASELINE SAMPLING


The environmental baseline study (EBS) is carried out to establish environmental conditions on the
existing environment of the proposed PTTLNG site in Nong Fab as well as its surrounding areas.
The EBS covered various environmental components which include the physical, chemical,
biological and human environments.
The baseline environmental data will be used as a yardstick to measure the extent of impact to the
surrounding environment and nearby receptors during the development and eventual operation of
PTTLNG. It will also be used to gauge the effectiveness of the control / mitigating measures adopted
during the construction and operational phases of this Project.
The baseline study was designed to cover an area within a 5-km radius from the proposed site
boundary and data gathering was focused on key issues related to the current conditions at site.
Baseline data are derived from two sources i.e. primary data from specific field surveys executed,
and secondary data from existing available databases, literature, remote sensing, etc.

11.2 METHODOLOGY OF AMBIENT AIR QUALITY


The ambient air quality measurements were taken from starts of site works to the end of commissioning
phase. The ambient air was measured for the following parameters:
• TSP and PM10 monitored by Gravimetric High-Volume Method or by equivalence method
announced by relevant agency

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 11 of 13

• Wind speed and direction monitoring by Cup Anemometer/ Anemometer/ Anodized


Aluminium Vane/Ultrasonic Anemometer or by equivalence method announced by
relevant agency

11.3 METHODOLOGY OF NOISE LEVEL


Noise level measurements were taken from starts of site works to the end of commissioning phase,
and the data were analyzed for:
 LA eq 24hrs (in community); 8hrs (in SITE);
 LA dn;
 LA max;
 LA 90.

Noise level standard refers to IEC 651 or IEC 804 or IEC61672 standard or equivalence method
announced by relevant agency.

11.4 METHODOLOGY OF GROUNDWATER QUALITY


The samplings of the groundwater were undertaken from starts of site works to the end of commissioning
phase. The groundwater samples were collected for the Analysis of:

 Volatile Organic Compounds (VOC): Purge and Trap Gas Chromatography or Purge and
Trap Gas Chromatography/ Mass Spectrometry or approved method by Pollution Control
Department.
 Arsenic and Selenium: Hydride Generation/Atomic Absorption Spectrometry or Inductively
Coupled Plasma/Plasma Emission Spectroscopy or approved method by Pollution Control
Department.
 Cadmium (Cd), Chromium hexavalent (Cr6+), Barium (Ba), Copper (Cu), Lead (Pb),
Manganese (Mn), Nickel (Ni), Zinc (Zn) and Iron (Fe): Direct Aspiration/ Atomic Absorption
Spectrometry or Inductively Coupled Plasma/Plasma Emission Spectroscopy or approved
method by Pollution Control Department.
 Mercury (Hg): Cold-Vapor Atomic Absorption Spectrometry/Plasma Emission Spectroscopy
or approved method by Pollution Control Department.

11.5 METHODOLOGY OF SOIL QUALITY


The sampling of the soil was undertaken from starts of site works to the end of commissioning phase, and
the samples were collected for the analysis of:
 Volatile Organic Compounds (VOC): Purge and Trap Gas Chromatography or Purge and
Trap Gas Chromatography/ Mass Spectrometry or approved method by Pollution Control
Department.
 Arsenic and Selenium: Hydride Generation/Atomic Absorption Spectrometry or Inductively
Coupled Plasma/Plasma Emission Spectroscopy or approved method by Pollution Control
Department.
 Cadmium (Cd), Chromium hexavalent (Cr6+), Barium (Ba), Copper (Cu), Lead (Pb),
Manganese (Mn), Nickel (Ni), Zinc (Zn) and Iron (Fe): Direct Aspiration/ Atomic Absorption

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 12 of 13

Spectrometry or Inductively Coupled Plasma/Plasma Emission Spectroscopy or approved


method by Pollution Control Department.
 Mercury (Hg): Cold-Vapor Atomic Absorption Spectrometry/Plasma Emission Spectroscopy
or approved method by Pollution Control Department.

11.6 METHODOLOGY OF WATER QUALITY


The sampling of the water was undertaken from starts of site works to end of construction. Surface water
was measured in-situ for:
 Methodology in the Notification of the National Committee B.E. 2560: Seawater Quality
Standard.
 Wastewater :
 - pH: pH Meter
 - Suspended Solid: Suspended Solid must be dried between 103-105 ºC for 1 hour or
approved method by relevant government.

11.7 METHODOLOGY OF MARINE WATER QUALITY


Marine water samples were taken from 10th November 2011 to 11th November 2011.
Marine water was measured in-situ for:
 Follow the Standard Methods for the Examination of Water and Wastewater 22 Edition (2012)
issued by APHA, AWWA และWWF or approved method by relevant agencies.

12 ENVIRONMENTAL STANDARD OF ISO14001

The Environmental Standard of ISO 14001 will be applied at all stages of the monitoring programmes.

13 CLOSE-OUT FOR MEASURES OF MITIGATION AND MONITORING


All Measures of MITIGATION for EIA will be adequately controlled and traced to close out on short time.
All MONITORING activities for the EIA have been reported here in attachment.

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
PTTLNG Doc. No.:
122018-SPCC-C-SH-PR-0024
Project Environmental SPCC Doc. No.:
Monitoring Plan XA74-0000-024
Revision : F1 Status : IFF
Contractor Project : PTTLNG Nong Fab LNG Receiving Terminal Project Rev. Date : 04/04/2019
Contractor Discipline : SH Contractor Phase : EPCC Phase Page 13 of 13

14 ATTACHMENT A PROJECT ENVIRONMENTAL MONITORING PLAN

SPCC_NF
Terminal+IPC_Work p

This document is the property of SPCC who will safeguard its rights according to the civil and penal provisions of the Law.
Environmental Impact Monitoring Plan in Construction Period of Nong Fab LNG Receiving Terminal Project during September 2018- December 2021 (40 Months) and In-plant Generator Project for Nong Fab LNG Receiving Terminal during April 2019 - October 2021 (31 Months)
SAIPEM-CTCI Joint Venture (SPCC)
2018 2019 2020 2021 2022

Project Environmental Aspect Monitoring Station Frequency Parameter

May
May

May

Mar
Mar

Mar

Nov

Nov
Nov

Nov

Aug
Aug

Aug

Dec

Dec
Dec

Dec

Sep
Sep

Sep

Sep

Apr
Apr

Apr

Feb
Feb

Feb

Oct

Oct
Oct

Oct

Jun
Jun

Jun

Jan

Jan
Jan

Jan

Jul
Jul

Jul
Environmental Impact Monitoring follow EIA Requirement
1. Ambient Air Quality
TERMINAL 2 Stations : 2 times/year - Total Suspended Particulate (TSP) 1 2 3 4 5 6 7
- In front of the construction area of the project (7 consecutive days) - Particulate Matter Less Than 10 µm (PM10)
- Nong Fab Temple - Wind speed/Wind direction (WS/WD)

IPG 2 Stations : 2 times/year - Total Suspended Particulate (TSP) 1 2 3 4 5 6


- The north of LNG Receiving Terminal contruction (7 consecutive days) - Particulate Matter Less Than 10 µm (PM10)
area NOTE: The Monitoring must be different - Wind speed/Wind direction (WS/WD)
- Nong Fab Temple period from LNG Receiving Terminal Project

2. Noise Level and Vibration


TERMINAL 2.1 Noise Level at Construcion Area Station : 2 times/year - LAeq 8 hours 1 2 3 4 5 6 7
- In front of the construction area of the project (5 consecutive days)

2.2 Noise Level at Community Area Station : - LAeq 24 hours, LAeq 90, LAmax, LAdn 1 2 3 4 5 6 7
- Nong Fab Temple - Annoyance noise

2.3 Vibration Stations : - Peak Particle Velocity (mm/sec) 1 2 3 4 5 6 7


- North fence of the project area - Frequency (Hz)
- Nong Fab Temple

IPG 2.1 Noise Level at Construcion Area Station : 2 times/year - LAeq 8 hours 1 2 3 4 5 6
- The north of LNG Receiving Terminal contruction (7 consecutive days)
area

2.2 Noise Level at Community Area Station : - LAeq 24 hours, LAeq 90, LAmax, LAdn 1 2 3 4 5 6
- Nong Fab Temple - Annoyance noise

3. Coastal Water Quality


TERMINAL 3.1 Coastal Water Quality 10 Stations : 2 times/year - Depth, Temperature, Salinity, Transparency, 1 2 3 4 5 6 7
- 500 m. east of the bridge at 1 km. from coast Turbidity, pH, Dissolved Oxygen, Suspended
Solids, Oil and Grease, Lead, Cadmium, Mercury,
- 500 m. west of the bridge at 1 km. from coast
Fecal Coliform Bacteria, Total Coliform Bacteria
- 500 m. east of the bridge at 3 km. from coast
- 500 m. west of the bridge at 3 km. from coast
3.2 Particle Dispersion - 500 m. east of jetty construction area - Prior jetty construction for - Suspended Solids for standard values 1
- 500 m. west of jetty construction area suspended solids standard values (as (10 stations x 3 levels x 25 times)
specified in Audit)
- 100 m. from outlet of Seawater Intake
- 100 m. from outlet of Seawater Outfall
- At Hin Klong rock mound - Once time before jetty construction - Suspended Solids for baseline 1
- Referent station: 5 km. from project area process for baseline

- Once a week during low tide to lowest - Suspended Solids 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27


tide

NOTE: Monitoring in nearby area of


construction activity

3.3 Effluent from Sediment pond and 2 Stations : - Every month, in case of discharge into - pH, Suspended Solid 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Effluent sump from Concrete Plant - Sediment pond the sea
- Effluent sumpt

3.4 Hydrostatic Test Station : - Once time after completed Hydro Test - COD, Temperature, pH, Oil and Grease , Total 1 tme after after completed Hydro Test activity before discharge to the sea
- Discharge point of hydrostatic test activity before discharge to the sea Dissolved Solids, Suspended Solid, Choride, Total
(as specified in both Audit and Monitor iron, Nickel
sections)

IPG 3.1 Coastal Water Quality 2 Stations 2 times/year Same as TERMINAL in 3.1, 1 2 3 4 5 6
(Stations are faraway from the coast with 1 km., except Lead, Cadmium, and Mercury
See in Appendix A)

3.2 Effluent Station : - Every month, in case of discharge into Same as TERMINAL in 3.3 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
- Sediment pond the sea
Environmental Impact Monitoring Plan in Construction Period of Nong Fab LNG Receiving Terminal Project during September 2018- December 2021 (40 Months) and In-plant Generator Project for Nong Fab LNG Receiving Terminal during April 2019 - October 2021 (31 Months)
SAIPEM-CTCI Joint Venture (SPCC)
2018 2019 2020 2021 2022

Project Environmental Aspect Monitoring Station Frequency Parameter

May

May

May
Mar

Mar

Mar

Nov
Nov

Nov

Nov

Aug
Aug

Aug

Dec
Dec

Dec

Dec
Sep

Sep
Sep

Sep
Apr

Apr

Apr
Feb

Feb

Feb
Oct

Oct
Oct

Oct
Jun

Jun

Jun

Jan
Jan

Jan

Jan
Jul

Jul

Jul
4. Groundwater Quality
TERMINAL 3 Stations : - Once time before construction activities - VOCs : Benzene, Carbon Tetrachloride, 1,2- 1
- GW1: North of the project area (For Baseline) Dichloroethane, 1,1-Dichloroethylene, cis-1,2-
Dichloroethylene, trans-1,2-Dichloroethylene,
- GW2: West of the project area
Dichloromethane, Ethylbenzene, Styrene,
- GW3: Southeast of the project area Tetrachloroethylene, Toluene, Trichloroethylene,
1,1,1-Trichloroethane, 1,1,2-Trichloroethane,
Total Xylenes

6+
- Heavy Metals : Cd, Cr , Cu, Pb, Mn, Ni, Zn, As,
Se, Hg, Ba, Fe

IPG Same as TERMINAL - Once time before construction activity Same as TERMINAL 1
process

5. Soil
TERMINAL 7 Stations - Once time before construction activities - VOCs : Benzene, Carbon Tetrachloride, 1,2- 1
(For Baseline) Dichloroethane, 1,1-Dichloroethylene, cis-1,2-
Dichloroethylene, trans-1,2-Dichloroethylene,
Dichloromethane, Ethylbenzene, Styrene,
Tetrachloroethylene, Toluene, Trichloroethylene,
1,1,1-Trichloroethane, 1,1,2-Trichloroethane,
Total Xylenes

- Heavy Metals : As, Cd and Compounds, Cr6+,


Pb, Mn and Compounds, Hg and Compounds, Ni,
soluble salts, Se

IPG Same as TERMINAL - Once time before construction activity Same as TERMINAL 1
process

6. Marine Ecology
TERMINAL 10 Stations : Same as Coastal water quality - 2 times/year - Phytoplankton 1 2 3 4 5 6 7
monitoring - Zooplankton

9 Stations: (Same as Coastal water quality - Benthos 1 2 3 4 5 6 7


monitoring, expect Hin Klong Station)

1 Stations at Hin Klong - Coral survay (Line-intercept method) 1 2 3 4 5 6 7


- 1st Coordinate: 727602E, 1400707N
- 2nd Coordinate 727787E, 1400734N

IPG 2 Stations - 2 times/year - Phytoplankton 1 2 3 4 5 6


(See in Appendix A) - Zooplankton

7. Transportation
TERMINAL 7.1 Land Transportation Station :
- Entrance-exit gate of the project area - Every week and report every 6 months - Record traffic volume at enter-exit from the Recorded by SPCC
project area by sorting vehicle type

- Entrance-exit gate of the project area - Every time of accident happening and - Record a number of accident / cause of
- Transportation route report every 6 months accident in the project area

7.2 Marine Transportation Station : - Every time of accident happening and - Record a number of accident/ cause of marine Recorded by SPCC
- Contruction area report every 6 months accident in the project area

IPG 7.1 Land Transportation Station :


- Entrance-exit gate of the project area - Every week and report every 6 months - Record traffic volume at enter-exit from the Recorded by SPCC
project area by sorting vehicle type
Environmental Impact Monitoring Plan in Construction Period of Nong Fab LNG Receiving Terminal Project during September 2018- December 2021 (40 Months) and In-plant Generator Project for Nong Fab LNG Receiving Terminal during April 2019 - October 2021 (31 Months)
SAIPEM-CTCI Joint Venture (SPCC)
2018 2019 2020 2021 2022

Project Environmental Aspect Monitoring Station Frequency Parameter

May

May

May
Mar

Mar

Mar

Nov
Nov

Nov

Nov

Aug
Aug

Aug

Dec
Dec

Dec

Dec
Sep

Sep
Sep

Sep
Apr

Apr

Apr
Feb

Feb

Feb
Oct

Oct
Oct

Oct
Jun

Jun

Jun

Jan
Jan

Jan

Jan
Jul

Jul

Jul
- Construction project area - Every time of accident happening and - Record a number of accident / cause of Recorded by SPCC
- Transportation route report every 6 months accident in the project area

8. Waste Management
TERMINAL Station : - Every week and report every 6 months - Record type, volume, transportation, and waste Recorded by SPCC
- construction area management from construction activities

IPG Station : - Every week and report every 6 months - Record type, volume, transportation, and waste Recorded by SPCC
- construction area management from construction activities

9. Socio-Econimics
TERMINAL Attitude Survey of community leader, Station : - 1 time/year - Effect from the project constructionoppinion to 1 2 3 4
community member, and fishery group - Community and fishy group within 5 Km. from - Suggestion to reduce the impact
the project location - Concern on the project development

IPG 9.1 Community Leader Station : - 1 time/year by using questinaire - Population, habitat, occupation, public utility, 1 2 3
- Community within 5 radius from the project area social problem, social relation and interaction,
concern and impact, acknowladgement and
oppinion to the project

9.2 Household (General family) - Occupation, Finance, public utility, social


relation and interaction, current status, concern
and impact, acknowladgement and oppinion to
the project

9.3 Governmental Agency Station : - Function and role, area of responsibility,


- Relative governmental agency to the project, such function and role to the project, social problem,
as Local office of the Department of Disaster complaint and problem-solving, concern and
Prevention and Mitigation, Regional office of impact, acknowledgement and opinion to the
Natural Resources and Environment, Map Ta Phut project
Municipality, Ban Chang Municipality, Rayong
Energy Office and Rayong Public Health Office

9.4 Complaint Station : - Every week and and report every 6 - Complaint record from community (Number Recorded by SPCC
- Transportation area months and case)
- Construction area

10. Public Health


TERMINAL Station : - Every of accident happening and report - Record a number and cause of worker illness in Recorded by SPCC
- Contruction area every 6 months the project medical room

IPG Station :
- LNG Receiving Terminal contruction area - Every of accident happening and report - Record a number and cause of worker illness in Recorded by SPCC
every 6 months the project medical room

- Transportation route - Collect patient statistic that related to project


- LNG Receiving Terminal contruction area impact from local public health agencies with
complaint record (Number and case)

11. Occupational Health and Safety


TERMINAL Station : - Every week and report every 6 months - Accident Record, such as cause of accident, Recorded by SPCC
- Construction area location, severity and solution

IPG Station : - Every week and report every 6 months - Accident Record, such as cause of accident, Recorded by SPCC
- LNG Receiving Terminal contruction area location, severity and solution

Environmental Impact Monitoring follow RFQ Requirement


Background Noise
TERMINAL (Adddional item request by SPCC) 15 monitoring points 10 minutes per point LA90, LA50, LA10,LAeq, LAmax 1
(See in Appendix B) 2 times per day (day and night time)
Environmental Impact Monitoring Plan in Construction Period of Nong Fab LNG Receiving Terminal Project during September 2018- December 2021 (40 Months) and In-plant Generator Project for Nong Fab LNG Receiving Terminal during April 2019 - October 2021 (31 Months)
SAIPEM-CTCI Joint Venture (SPCC)
2018 2019 2020 2021 2022

Project Environmental Aspect Monitoring Station Frequency Parameter

May
May

May

Mar
Mar

Mar

Nov

Nov
Nov

Nov
Aug

Aug

Aug
Dec

Dec
Dec

Dec

Sep

Sep
Sep

Sep

Apr
Apr

Apr

Feb
Feb

Feb

Oct

Oct
Oct

Oct
Jun

Jun

Jun
Jan

Jan
Jan

Jan
Jul

Jul

Jul
1 monitoring point (Point 4) 24 hours LA90, LA50, LA10,LAeq, LAmax 1
(See in Appendix B)
Environmental Impact Monitoring Plan in Construction Period of Nong Fab LNG Receiving Terminal Project during September 2018- December 2021 (40 Months) and In-plant Generator Project for Nong Fab LNG Receiving Terminal during April 2019 - October 2021 (31 Months)
SAIPEM-CTCI Joint Venture (SPCC)
2018 2019 2020 2021 2022

Project Environmental Aspect Monitoring Station Frequency Parameter

May

May

May
Mar
Mar

Mar
Nov

Nov

Nov

Nov
Aug

Aug

Aug
Dec

Dec

Dec

Dec
Sep

Sep

Sep

Sep
Apr

Apr

Apr
Feb
Feb

Feb
Oct

Oct

Oct

Oct
Jun

Jun

Jun
Jan

Jan
Jan

Jan
Jul

Jul

Jul
Environmental Mitigation Measures Audit
TERMINAL 1. General Mitigation Measures Station Every month by UAE Environmental Mitigation Measure 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
2. Air Quality - Project area Implementation Compliance Audit
3. Noise Level and Vibration - Worker camp
4. Coastal Water Quality
5. Marine Ecology
6. Land Transportation
7. Marine Trasportation
8. Water Utilization
9. Fishery and Fish Breeding
10. Waste management
11. Socio-Economics
12. Public Health
13. Occupational Health and Safety
14. Public Participation and Publicity

IPG 1. General Mitigation Station Every month by UAE Environmental Mitigation Measure 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
2. Air Quality - Project area Implementation Compliance Audit
3. Noise Level - Worker camp
4. Water Quality
5. Marine Ecology
6. Groundwater Quality
7. Land Use
8. Transportation
9. Waste Management
10. Drainage
11. Socio-Economics
12. Occupational Health and Safety
13. Public Health
14. Public Participation and Publicity

EMMC Meeting
TERMINAL EMMC Meeting and Presentation to 28 Committee members Every month by EMMC Committee 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
Committee

IPG EMMC Meeting and Presentation to 28 Committee members Every 3 months by EMMC Committee 1 2 3 4 5 6 7 8 9 10
Committee
Report Preparation
TERMINAL 1. Every 6 months to ONEP and related Every 6 months 1 2 3 4 5 6 7
agencies - 11 reports in Thai version
- 3 reports in English version

2. Monthly report Every month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39


- 2 reports in Thai Version

IPG 1. Every 6 months to ONEP and related Every 6 months - Energy Regulatory commission
agencies - 8 reports in Thai version - Department of Industrial Work
- 3 reports in English version - Office of Natural Resources and Environmental
Policy and Planning 1 2 3 4 5 6
- Rayong Provincial Office

2. Monthly report Every month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31


- 2 reports in Thai Version

3. Baseline Report (for Groundwater Once time - Groundwater quality monitoring for baseline 1
Quality) - 2 reports in Thai Version

Remark: 1. The overall construciton activities are carried out 40 months


2. The environmental monitoring plan may properly change according to the actual construction activity
3. Some environmental monitoring of IPG Project was performed together with Terminal Project. There is item 3.1, 4, 5 and 6