LEARNING ACTION PLAN


SY 2023-2024

RESOURCES
PERSONS
PHASE ACTIVITIES TIME FRAME SOURCE OF SUCCESS INDICATOR
INVOLVED FUNDS
FUNDS
PLANNING Gathering and Assessing Professional School Head, Master February 19, 2024 7,000.0 School MOOE, Developed/Prepared LAC
development Needs Teachers, Grade 0 School Canteen and Plan
Identifying Topics and Learning Outcomes Chairmen, Subject Fund, HRD Approved proposal of
Developing LAC Implementation Plan Coordinator, Proponent Fund Activities on LAC
Developing Progress Monitoring and Evaluation Developed M & E plan
Plan
IMPLEMENTATION Implementation/conduct of LAC sessions on School Head, LAC March 1, 15, 29, April 100% of the objectives of
scheduled date and time Facilitators/ Speakers, 12, 26, 2024 all sessions attained
TWG, Teacher 100% participation of all
Participants involved
Conducted as scheduled
Properly documented, and
with accomplished report
EVALUATION Monitoring & Evaluation by the M & E Team, The whole duration of 100 % of Evaluation Form
SDO/District/School M & E Team using the Participants the implementation of had been answered and
standard evaluation form and answering the SLAC collected
Evaluation Form by the participants in all
sessions

Prepared by: Noted:

JUAN G. BORIDAS SALVE T. TEMPLO


INSET/LAC Proponent & Organizer School Principal III

Recommending approval: Approved:

ELIAS V. ABUNDO SOCORRO V. DELA ROSA, CESO V


Public Schools District Supervisor Schools Division Superintendent