Total Order
Total = 27.43 m3
= 27.43 x 0.5
Total = 13.715 cu.m = 14 cu.m of Sand
= 27.43 x 1
Total = 27.43 cu.m = 28 cu.m of Gravel
F1
1.35 + 0.2 + 0.2 = 1.75m
F2
1.1 + 0.15 + 0.15 = 1.4m
1.1/0.2 = 5.5 + 1 = 6.5 = 7 pcs
7 x 2 = 14 pcs of steel bars @ 1.4 m long
F2
1.1 + 0.15 + 0.15 = 1.4m
6m/1.4 = 4.285714 = 4
12pcs/4 = 3 pcs rebars