FOOTING SCHEDULE (3000 PSI) DEPTH
REINFORCEMENTS
ITEM L W T mm
TOP BOTTOM
Ø16mm Ø16mm
F1 1500 1500 350 @200 mm @200 mm 1500
O.C. O.C.
Ø10mm Ø16mm
F2 1250 1250 300 @250 mm @200 mm 1500
O.C. O.C.

Total Order

Cement 206 (40kg) bags of Cement

Sand 14 cu.m of Sand

Gravel 28 cu.m of ¾ Gravel

16mm Steel Bars 112 pcs

20mm Steel Bars 120 pcs

10mm Steel Bars 48 pcs

G.I. Wire 16 360 kgs


F1 Volume = 1.5 x 1.5 x 0.35 = 0.7875 m3 x 4 = 3.15 m3
F2 Volume = 1.25 x 1.25 x 0.3 = 0.46875 m3 x 16 = 7.5 m3

C1F1 = 0.4 x 0.25 x 8.35 = 0.835 m3 x 4 = 3.34 m3


C1F2 = 0.4 x 0.25 x 8.4 = 0.84 m3 x 16 = 13.44 m3

Total = 27.43 m3

1. COMPUTE FOR TOTAL CEMENT BAGS FOR CONCRETING

= 27.43 x 7.5 = 205.695


Total = 206 bags of cement

2. COMPUTE FOR TOTAL SAND FOR CONCRETING

= 27.43 x 0.5
Total = 13.715 cu.m = 14 cu.m of Sand

3. COMPUTE FOR TOTAL GRAVEL 3/4 FOR CONCRETING

= 27.43 x 1
Total = 27.43 cu.m = 28 cu.m of Gravel

4. COMPUTE FOR 16MM (6M)

F1
1.35 + 0.2 + 0.2 = 1.75m

1.35/0.2 = 6.75 + 1 = 7.75 = 8 pcs


8 x 2 = 16 pcs of steel bars @ 1.35 m long

6m/1.75 = 3.428571 = 3 pcs per 6m rebar


16pcs/3 = 5.3 = 6 pcs rebars
6 pcs rebars x 4 F1 footings = 24 x 2 (top and bottom)

= 48 pieces 16mm x 6.00 m steel bars

F2
1.1 + 0.15 + 0.15 = 1.4m
1.1/0.2 = 5.5 + 1 = 6.5 = 7 pcs
7 x 2 = 14 pcs of steel bars @ 1.4 m long

6m/1.4 = 4.285714 = 4pcs per 6m rebar


14pcs/4 = 3.5 = 4 pcs rebars
4 pcs rebars x 16 F2 footings

= 64 pieces 16mm x 6.00 m steel bars

Total = 48 + 64 = 112 pieces 16mm x 6.00 m steel bars

5. COMPUTE FOR 20MM (6M)

6 - Ø20mm MAIN BARS


Column Height - 8.7m
Therefore 6m isn’t enough
1 pc of 6m rebar can fit 2 columns top part

6 x (20 + 20/2) columns


= 180 pieces of 20mm x 6.00 m steel bars

6. COMPUTE FOR 10MM (6M)

F2
1.1 + 0.15 + 0.15 = 1.4m

1.1/0.25 = 4.4 + 1 = 5.4 = 6 pcs


6 x 2 = 12 pcs of steel bars @ 1.4 m long

6m/1.4 = 4.285714 = 4
12pcs/4 = 3 pcs rebars
3 pcs rebars x 16 F2 footings

= 48 pieces 10mm x 6.00 m steel bars

7. COMPUTE FOR TOTAL KGS GI.WIRE 16.

162 / 162.2 = 1.578 kgs/m


1.578 x 6 = 9.468
9.468 x 80pcs = 757.44
757.44 x 0.10 = 75.744 kgs

102 / 162.2 = 0.6165228 kgs/m


0.6165 x 6 = 3.69914
3.69914 x 48pcs = 177.5585697
177.5585697 x 0.10 = 17.7559 kgs

202 / 162.2 = 2.46609 kgs/m


2.46609 x 6 = 14.79654747
14.7965 x 180pcs = 2663.378545
2663.378545 x 0.10 = 266.3378545 kgs

17.7559 + 75.744 + 266.3378 = 359.8377545 = 360 kgs of G.I. Wire 16