Professional Documents
Culture Documents
Contents
1 Scope .................................................................................. 2
2 Purpose ............................................................................... 2
3 Conflicts and Deviations ...................................................... 3
4 Applicable Documents ......................................................... 3
5 Definitions and Abbreviations .............................................. 5
6 Instructions ........................................................................ 12
7 Responsibilities .................................................................. 22
Revision Summary ................................................................... 26
1 Scope
1.2 This procedure also provides guidelines to determine the process units that shall
be covered by RBI assessment.
1.3 This procedure also outlines when initial and evergreen RBI assessment shall be
conducted.
2 Purpose
2.1 To assure that Saudi Aramco systematic evaluation process for RBI assessment
is well defined.
2.2 Roles and responsibilities for RBI assessment activities in Saudi Aramco are
outlined.
2.5 Process and deliverables when utilizing Service Providers (SP) to perform RBI
assessment are clearly defined.
Any conflicts between this document and other applicable Mandatory Saudi Aramco
Engineering Requirements (MSAERs) shall be addressed to the EK&RD Coordinator.
Any deviation from the requirements herein shall follow internal company procedure
SAEP-302.
4 Applicable Documents
Except as modified by this SAEP, applicable requirements in the latest issues of the
following Industry Codes, Standards, and Practices shall be considered an integral part
of this procedure.
5.1 Definitions
Failure Mode: The manner of failure. For Risk-based Inspection, the failure of
concern is loss of containment of pressurized equipment items. Some examples
of piping failure modes are pinhole, crack and rupture.
Hazard and Operability (HAZOP) Assessment (as per OSHA 29 CFR 1910.119
and SAER-5437): A HAZOP assessment is a Process Hazard Analysis (PHA)
form of failure mode and failure effect analysis. HAZOP studies, which were
originally developed for the process industry, use systematic techniques to
identify hazards and operability issues throughout an entire facility. They are
particularly useful in identifying latent hazards designed into facilities due to lack
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 6 of 74
Document Responsibility: Inspection Engineering Standards Committee SAEP-343
Issue Date: 24 January 2019
Next Planned Update: 24 January 2022 Risk-based Inspection (RBI) for Saudi Aramco Facilities
In-plant Piping: Piping that is inside the boundary limits of the plant and is
generally, but not necessarily, designed to ASME B31.3 code except in area(s)
set aside for piping within other code or government regulations.
key parameters, identified and used as a basis for the RBI assessment, are
controlled to be within the assessment defined ranges. It also specifies that any
change to those parameters requires a review by RBI facilitator.
Mechanical Integrity: The ability of the assets to withstand the design loads
for optimum operation and maintenance of the assets at best condition
throughout its life cycle.
Off-plot Piping: Piping that is outside the boundary limits of the plant and is
generally, but not necessarily, designed to ASME B31.4/B31.8 code except in
area(s) set aside for piping within other code or government regulations.
Proponent: The customer who can undertake the assessment or for whom the
assessment is being undertaken by another party.
RBI Team: A team of people with the requisite skills and background in RBI
to conduct an effective assessment. The team is made up of Plant Proponent
personnel and RBI SP personnel.
Commentary Note:
For new construction project, RBI team shall be comprised of the Proponent
inspection personnel, SA PMT, EPC contractor, and RBI SP.
estimate the risk. Risk analysis provides a basis for risk evaluation, risk
mitigation and risk acceptance. Information can include historical data,
theoretical analysis, informed opinions, and concerns of stakeholders.
Risk Assessment: Overall process of risk analysis and risk evaluation, which
consists of deciding whether or not the risk is tolerable.
Risk Evaluation: Process used to compare the estimated risk against given risk
criteria to determine the significance of the risk. Risk evaluation may be used to
assist in the acceptance or mitigation decision.
RBI Software Practitioner: An individual who has experience using the RBI
software and the knowledge to perform the analysis required to develop an
inspection plan based on the risk results.
Unmitigated Risk: The risks for which mitigation activities have yet to be
performed.
5.2 Abbreviations
API American Petroleum Institute
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 10 of 74
Document Responsibility: Inspection Engineering Standards Committee SAEP-343
Issue Date: 24 January 2019
Next Planned Update: 24 January 2022 Risk-based Inspection (RBI) for Saudi Aramco Facilities
6 Instructions
6.1.1 The RBI methodology currently approved and implemented is the API
RBI from the American Petroleum Institute as described in API RP 581.
6.1.2 The latest available version of the API RBI software shall be used
where applicable to perform assessments. The software custodian
within Saudi Aramco is Inspection Department.
6.1.3 Usage of other RBI methodologies and software for quantitative risk
assessment is permissible for assets not covered by API-RBI software.
These RBI methodologies and software shall be approved by the IDRBI
team.
6.1.4 Each facility should prioritize the implementation of RBI for each
Process Unit based on next T&I date and integrity issues associated
with operational risk.
6.1.7 Appendix B RASCI chart defines the roles and responsibilities of all
RBI assessment participants.
Establish corrosion loops for the full unit under assessment. Each loop
shall include all main lines and associated piping/branches attached to
these main lines.
6.2.2 Piping
Piping systems which meet any of the following criteria shall at least
require a semi-quantitative risk analysis (comprehensive OSI review) or
full RBI assessment where applicable as addressed in Appendix A:
a) Process piping containing hydrocarbon, toxic or corrosive fluid.
b) Piping failure that could present a hazard to humans, to the
environment, or where such failure could not be repaired without
disrupting operation.
c) Piping known to exhibit a high probability of failure, e.g., piping
with injection point(s), dead leg(s) or vibrations.
d) Piping known to be susceptible to Corrosion under Insulation (CUI)
and environmental damage such as Stress Corrosion Cracking (SCC)
with failure consequences shown in item 2 above.
Commentary Note:
6.4.1 API RBI assessment shall be applied to all pressure containing equipment
(according to the RBI decision tree; Appendix A) such as:
1) In-plant piping
2) Pressure vessels (reactors, columns, drums, etc.)
3) Heat exchangers and fin fans
4) Tanks
5) Pressure relieving devices (PRD)
6) Exchanger tube bundles
6.4.2 All equipment items which are not covered by API RBI but do meet the
requirements for RBI decision tree in Appendix A to be assessed by RBI
methodology approved by ID.
Off-plot piping should be included but the software used in the assessment shall
be approved by the Inspection Department before deployment.
6.6 Pipeline
Software and methodology other than API RBI shall be used with prior approval
from ID RBI team.
6.6 Utilities
Software and methodology other than API RBI shall be used with prior approval
by ID RBI team. The assessment shall cover top and subsea steel structures,
top-side equipment, piping, risers and subsea pipelines.
6.9 PRDs
6.9.2 Fire demand case shall not be used for gas vessels with a liquid level
less than 10%.
6.10.2 Any methodology other than API RBI shall be thoroughly documented in
the final report, with full details that allow reproducing the assessment by
third party.
6.10.3 The algorithm built in the software program and version used to
perform the assessment shall be fully documented with all sufficient
details as requested by ID RBI team.
6.11.1 All data relevant to the RBI assessment including RBI software
database shall be captured and maintained such that the assessment can
be recreated or updated at a later time. The data shall be stored in a
designated data management system as directed by the Inspection
Department.
6.11.2 Assurance that all RBI assessment-related data and reports are properly
preserved is the responsibility of the Plant RBI facilitator/Team Leader
during the assessment, and the Plant Inspection Unit Supervisor, after
the assessment is completed.
6.11.4 The corporate RBI recommendations tracking system shall be updated with
the RBI assessment recommendations.
6.12.1 Identified active and potential damage mechanisms for each corrosion loop
shall be based on API RP 571, Saudi Aramco Corrosion Management
Program (CMP) Manual SABP-A-033 and other industry documents.
6.12.3 Criteria used to judge the severity of each degradation mechanism not
covered by the latest revision of API RP 581.
6.12.5 Key factors used to judge the severity of each failure mode.
6.12.7 List of all process variables that have a direct impact on the level of
susceptibility of the equipment to damage mechanisms. This information
shall be captured on the individual corrosion loop under the name
“Susceptible Threshold Values.”
6.12.8 Corrosion loop description shall be aligned with the last template/format
required by SAEP-88 and SABP-A-033.
The evergreening report shall be aligned with the latest template provided by
ID RBI team.
RBI requires data gathering from many sources, specialized assessment, and
then risk management decision-making. Generally, one individual does not
have the background or skills to conduct the entire assessment. RBI assessment
shall be conducted by a team of people with the required competencies.
Some team members may be part-time due to limited input needs. It is also
possible that not all the team members described in this SAEP may be required
if other team members have the required skill and knowledge of that discipline.
1) Team Leader
In-house assessments Team Leader shall be proposed by the
Proponent's Management.
RBI Contractors’ team leaders shall demonstrate to the ID RBI Team
their personnel are suitably qualified and experienced in RBI technology.
The qualifications of the RBI personnel shall be documented.
Team Leader qualifications:
o Demonstrated skills in team leadership or project management.
o Degree in Engineering and project management with minimum of
15 years’ experience in Oil and Gas industry.
o Adequate training in RBI methodology and software navigation,
i.e., having actively participated in a minimum of two RBI
assessments using the software approved for the assessment.
o Experience in NDT disciplines.
o Excellent report-writing skills.
o Excellent presentation skills.
2) RBI Facilitator
RBI facilitator should prioritize the implementation of initial RBI for the
Facility Process Units.
The contract Scope of Work (specification) and the bidders’ technical proposals
shall be reviewed and evaluated by the proponent and ID RBI team.
7 Responsibilities
composition, etc.
2) Document and provide an update on the variations in the process conditions
due to normal occurrences (such as start-ups and shutdowns) and abnormal
occurrences.
3) Describe the composition and variability of all the process fluids as well as
their toxicity and flammability, as required.
4) Provide information required for financial assessment such as equipment
replacement cost and production losses.
5) Participate in the development of the Inventory Groups and sign off
concurrence.
6) Verify that the facility/equipment is being operated within the parameters
set out in the process design.
7) Provide data on production losses
Provide data on the T&I cost of the facility/equipment being analyzed and the
T&I duration.
Revision Summary
21 August 2013 Major revision.
7 July 2015 Minor revision to remove the requirement of utilizing Saudi Aramco Engineering Report
number (SAER) for the RBI final report.
24 January 2019 Major revision to align the procedure with the international standards and clarify some of the
standards requirements. The document revision includes:
Mechanical and
Metallurgical Failure
Mechanisms per API 571
Section 4 (Not including Yes
corrosion)
Environment – Assisted
Yes
Cracking
HTHA
Yes
Titantium Hydrating
No
Implement
recommendations of Perform
Robust No
the Comprehensive Quantitative RBI
Review
Yes
RBI Team collects, sorts, formats, reviews and compiles draft RBI Team submits draft corrosion loop
corrosion loop drawings and descriptions and marks up the drawings and description for CSD or service
Inventory Group drawings provider for concurrence
No
Accepted
Yes
Phase 1 Overdue No Service Provider/EPC contractor Collect, Sort, Format, Review and comply data and
review or develop draft Corrosion Loops and description and Inventory Groups
Yes
Letter of nonconformance issued by ID
Phase 1, 3,4 Phase 2 Sent To No Yes
2 weeks 4 weeks Division Head Yes Phase 2 Overdue Incomplete Data
4 weeks 8 weeks Manager
8 weeks 12 weeks Admin Head
No
Service Provider/EPC contractor submit Draft Corrosion Contact SA proponent RBI team leader
Loops and Description, Inventory Groups and populated
database to SA proponent RBI team leader for review.
SA proponent RBI team leader provides contact
SA proponent RBI Team Leader to review submissions for details of Plant Engineer, Corrosion Engineer,
concurrence. Inspector or other applicable person who may
be able to assist.
No
Concur Service Provider/EPC contractor submit
corrosion loops and description, inventory
groups and populated database to SA
Yes proponent RBI team leader/facilitator for
review.
Service Provider/EPC contractor, proponent & ID RBI Teams
meet to review and validate submitted documents and
Create and document assumptions for missing
database.
data and get concurrence from SA proponent
RBI team leader/facilitator.
No
Concur
No Incomplete Data
Yes
Service Provider/EPC contractor/SA PMT/ SA proponent RBI
team leader/ SA ID RBI team representatives meet to perform
analysis of the RBI assessment and Ensure they are in correct
final format for inclusion in report.
No
Yes
No Results Report accepted
Phase 3
Validated by ID RBI and validation sheet signed
Overdue No
Team off by ID RBI Team
Yes
Yes
Service Provider/EPC contractor establish or review CML’s for
optimization per SAES-A-135 and SAEP-1135. Service Provider/EPC contractor
give presentation
to the proponent management.
Service Provider/EPC contractor submit the draft report and
presentation to SA proponent RBI Team Leader & ID RBI Team.
No
ID Concur
Yes
No
No
Request Extension Overdue?
Yes
Start
PE & CE
PFD’s, P&ID’s, Material Balance Review plant documents for design, feed composition & operating
Drawings & Operating Manuals parameters.
CE & PE
Verify corrosive elements in the streams and record expected
corrosion mechanisms.
Lab Data / Feed Data
CE & IE
Review and P&ID’s for all injection points, and impingement
areas from branch piping, injection nozzles, dead legs, etc.
PE & CE
Review and record any operation parameters beyond design
Inspection & Cprrosion Data limit and list effect on corrosion.
Reports, Post T&I Reports,
Failure Analysis (RCFA)
Reports and SAIF.
CE & IE
Refer API 571 for generic damage mechanisms and confirmation
to list the applicable damage mechanism.
CE & IE
Mark all applicable & identified damage mechanisms on the Unit
API 571 PFD.
Group all piping and equipment together that have the same CE & IE
damage mechanisms, operating parameters and like material
with a color code in a sequential manner as a loop.
SAES-L133
CE & IE
Mark different loops for all applicable and identified damage
mechanisms on a PFD.
CE & IE
List is a spreadsheet all the loops by their damage mechanisms,
operating parameters, materials. CMP
Key: Complete a corrosion loop description that in a word document CE & IE RBI
PE Process Engineer that includes a short process description, table including each
CE Corrosion Engineer component with description in the loops, listing the specific
IE Inspection Engineer damage mechanism, PWHT status, Insulation type, material,
5% of Project Time 70% of Project Time 10% of Project Time 15% of Project Time
Task 4: Conduct RBI Workshop Task4: Conduct Site Interviews and Task 4: Present Findings to RBI Team
(for new members) Collect Missing Data Leader
Responsibility for the formation of the team is assigned to the Team Leader.
This activity should be accomplished by a formal written request to the appropriate
supervisors. These requests should specify the following items:
1) The nature and objective of the assessment
2) The location of the assessment
3) The input and responsibilities required from the engineers/specialists requested to
participate in the assessment
4) The duration of the assessment.
The Team Leader should also specify the extent of the involvement of the team
members requested, i.e., whether it is part-time or full-time and whether any additional
involvement is required before and after the assessment, e.g., for report writing, data
gathering, etc.
The Team Leader will ensure a Gantt chart is developed showing all assessment phases,
tasks and detailed activities, as applicable.. He should specify the required milestones,
the assigned resource(s) and duration. This chart may be compiled using software tools
such as Microsoft Project. This document is to be submitted, in the first instance, to the
Proponent for approval, then to the team members for information. When the
assessment is performed by a Service Provider the schedule shall be submitted to the
Proponent Engineering Division for the review and concurrence. Task 3 – Kick-off
Meeting
The Team Leader will develop an agenda and organize a meeting grouping all members
of the RBI Assessment Team.
The RBI team should be given an orientation to the Unit using the process flow diagram
(PFD) then performing a walkthrough of the unit.
The success of an RBI assessment depends strongly on the accuracy of the data and
information that is based on. It is the RBI Team's responsibility to clearly define the
data needed to analyze the equipment so that the results meet the assessment goals and
the proponent expectations.
Where possible, all data, including PFDs, should be made available to the Team Leader
in electronic format.
Assumptions shall be made throughout the assessment and included in the final report.
Task 2 – Review and mark PFDs for development of the corrosion loops and inventory
groups.
Review the PFDs and understand the process system. Optimize the data gathering for
in-plant piping using the following steps:
1) Establish corrosion loops for each individual system. Each loop shall include all
main lines and associated piping/branches attached to these main lines.
2) From each corrosion loop, select one or more main (representative) line and include
it in the RBI assessment as a component. Include lines before and after equipment.
a) The corrosion loop description and drawing shall be developed using a
template acceptable by ID.
b) The information required for submittal of concurrence of the corrosion loops
shall include the following as a minimum:
i) Corrosion Loop description
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 35 of 74
Document Responsibility: Inspection Engineering Standards Committee SAEP-343
Issue Date: 24 January 2019
Next Planned Update: 24 January 2022 Risk-based Inspection (RBI) for Saudi Aramco Facilities
Create the component (equipment and piping) list in the latest version of the import
spreadsheet (RBIExport). The purpose of creating the component list is to define the
boundaries of the systems included, and the actual equipment items to be analyzed.
From the information collected and assembled, fill in the required information for each
component in the import spreadsheet (RBIExport).
is a P&ID containing many small fuel gas lines; in this case instead of entering
each pipe, it is useful to enter a typical pipe for that P&ID or service.
11) Some equipment will be modeled in two or more parts to account for the large
differences in process conditions and damage mechanisms found between them.
This equipment is then broke down as components. For example, heat exchanger
tube and shell side, fin fan tubes, fin fan inlet header, and fin fan outlet header,
column top, middle and bottom, etc.
Documenting Assumptions:
1) With the available data, populate all applicable sheets and columns of the import
spreadsheet. If data is not available, make assumptions so that the final risk result
is on the conservative side. Document these assumptions in a word document as
an Appendix in the final report.
2) The assumptions shall be reviewed and approved by the proponent.
damage mechanism inspected for, the method of inspection applied, the number of
inspections, the coverage and the date of each inspection.
9) When assigning the inspection category, use the Inspection Effectiveness look up
tables found in Appendix J.
Corrosion Allowance
Use the design corrosion allowance (CA) from Safety Instruction Sheets, Line
Designation Table and SAES-L-105, as applicable.
This is measured in mils per year (MPY). 1 mil = 0.001”. Most condition
monitoring location (CML) are only read to two decimal places (10-mil accuracy),
i.e., a change in thickness from 0.50” to 0.49” is a 10-mil change in thickness.
The corrosion rate is usually derived from SAP-SAIF, the Saudi Aramco Inspection
Data Management System. The corrosion engineer together with the Sr. Inspector
or Inspection Engineer shall carefully examine the historical data gathered and
decide on the most applicable corrosion rates being experienced by the various plant
items. Engineering judgment and historical plant experience shall both play a major
role in determining the applicable corrosion rates. Note that the selected rates will
have a significant effect on the criticality of the plant items under assessment. If the
measured corrosion rate is used it shall be the highest mpy for each CML in that
equipment circuit, always taking the worst case between the near and long term
corrosion rate (CR). Field verification may be required to confirm measured
thickness for CML with questionable/abnormal CR.
It is noted that H2S is usually quantified in ppm. Note also that 1% (mass or weight)
= 10,000 ppm or 0.1%=1000 ppm.
PFDs normally provide H2S and other components in moles (lb-mol/hr). To obtain
a mole % (volume %), divide the moles/hr of the specific component, e.g., H2S, by
the total moles/hr. To obtain a mass or weight % for H2S, use the formula:
34 × [𝐻2 𝑠]𝑙𝑏∙𝑚𝑜𝑙/ℎ
𝑀%𝐻2 𝑆 =
[𝑇𝑜𝑡𝑎𝑙]𝑚𝑜𝑙 𝑤𝑡 × [𝑇𝑜𝑡𝑎𝑙]𝑙𝑏∙𝑚𝑜𝑙/ℎ
The length of tubing of Finfans for RBI is taken as tube length x # of tubes.
The inlet/outlet header boxes size (area) has to be converted to diameter and the
length will be the depth of the box.
The exchanger channel length is taken as 2 x channel length (on U-1 or SIS) for
U-tube exchanger and 2 x the channel head length plus the shell length for straight
tube.
For plate and frame exchangers, it is advised to only model the nozzles.
The corrosion, inspection and materials engineers and Sr. inspectors shall jointly review
the inspection, corrosion rates and damage mechanism data collected from the records
and interviews. A decision will also be made by this group to set the import
spreadsheet (RBIExport) to measured or estimated corrosion rates. This may reduce the
assessment time later in the RBI software.
The RBI team shall review details and changes to the location of block valves for
inventory grouping, detection systems, injection points, type of toxic (H2S), % of toxic,
mitigation systems, representative fluids and phases, pH, contaminants (H2S, Chlorine),
velocities, temperatures and pressures.
The RBI software practitioner shall complete the import spreadsheet and verify the
validity and accuracy of the data entered. Any assumptions made are to be updated;
if required, sensitivity to final results shall be evaluated.
API RBI software functionality is covered in; API RP 581. The major steps to follow
when analyzing data in the RBI software are:
1) Update the Component Data table to meet the Safety Instruction Sheets, Line
Designation Tables, SAES-L-310, and 01-SAIP-02 for the minimum retirement
thickness, tmin. If the specified tmin is greater than the software calculated tmin,
use the specified tmin in the software.
3) Saudi Aramco Inspection department will define the Risk and Damage factor
Targets. The targets may be variable depending on the assessment.
4) List equipment by the equipment letter, then the number (example D-101) in the
equipment and component fields.
5) List piping by service letter first (example P-1111-6CS9F) in equipment field and
by the diameter (example 18-P-1111-6CS9F) in the component field.
6) Copy all inspection history by year in the comment section of the software for
inspection history.
6) If any parameters are altered as you review the applicable likelihood supplements
and consequence information inside the software, run the batch calculations.
7) Determine the dominant damage mechanisms. Determine what is driving the
damage mechanisms. Is it the remaining wall thickness? The age?
Process parameters? The material of construction used? The lack of inspection?
This information shall be documented for inclusion in the final report.
8) Determine what is driving the high consequence items. Is it the representative
fluid used? Phase? Toxicity? Size of the inventory? This information shall be
documented for inclusion in the final report.
9) If the existing software does not properly model a certain damage mechanism or a
critical equipment item that the proponent wishes to address; then, these shall be
analyzed outside the software. Any methodology used or recommended to
address these issues shall be adequately referenced and documented in the final
report.
10) Inspection Department is required to validate the database.
There are several ways of mitigating risk effectively using the inspection plan that is
provided by the software. The likelihood aspect of risk may be reduced by:
1) Adding an inspection.
2) Repairing, replacing or derating equipment close to its end of life.
3) Removing the source of corrosion or damage mechanism or applying barriers, e.g.
coating, cladding, etc.
4) Repairing the coating or insulation if CUI is a driver.
5) Improved monitoring, i.e., adding Hydrogen Probes or Key Process Monitoring if
SCC is a concern.
6) Modifications to the operating procedures may reduce the consequence side of
risk by:
7) Reducing the toxic and / or flammable inventory
8) Adding isolation devices
9) Improving detection systems
10) Reducing population density.
12) It is cautioned that any mitigation measures considered for risk reduction shall be
reviewed by the relevant experts before implementation. It is noted that, for risk
reduction inside the software, an inspection may be required. The type and
effectiveness (as defined in API RP 581) of the inspection should be determined
using the inspection plan and API RP 571 damage mechanism tables. It is not
possible to treat the remainder of the mitigation measures inside the software.
Rather, these shall be addressed separately in the final report.
13) Prepare the Inspection Plan. Extensions of equipment should be evaluated on
whether or not the risk increases with time and with or without new inspections.
14) Discuss and agree with the proponent the cost savings derived from the RBI
Assessment.
15) Prepare the Cost Benefit Analysis of the RBI assessment.
17) The cost savings from an RBI assessment may include the following:
a) Reduction of inspections costs as a result of equipment being removed from
upcoming scheduled T&Is.
b) Reduction of maintenance costs as a result of equipment being removed
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 43 of 74
Document Responsibility: Inspection Engineering Standards Committee SAEP-343
Issue Date: 24 January 2019
Next Planned Update: 24 January 2022 Risk-based Inspection (RBI) for Saudi Aramco Facilities
Task 3 CML selection and optimization shall be reviewed and implemented using the
criteria listed in SAEP-1135.
Provide the proponent with the findings from the assessment at the conclusion of the
assessment.
The Team Leader or another team member (assigned by the Team Leader) should
provide a PowerPoint presentation to the proponent. This exercise shall be carried out
prior to the departure of the team from site, as applicable, and shall focus on the
preliminary findings derived from the assessment.
Comments made by the proponent shall be documented and evaluated for incorporation
in the Final Report.
Preparation of this document shall be the responsibility of the Team Leader or Service
Provider Facilitator. This report shall incorporate all comments made during the
presentation meeting (Phase 3, Task 4) in addition to any other changes. The report
shall have a SAER number that is requested from the Technical Information Center.
The report shall be submitted to the proponent and RBI team members for review.
A copy of the report (SAER) shall be submitted to the Technical Information Center.
A copy of the final RBI software files should be archived in an electronic storage
system acceptable to Inspection Department.
This folder is also divided into multiple sub-folders named after the proponent's facility
units, e.g., Ras Tanura Refinery Crude Distillation Unit, Hydrocracker, etc.
All correspondence, databases, reports, etc., are to be stored in the respective subfolder.
The custodian of this folder shall be the RBI team, Inspection Technical Support
Division, ID who will assign access rights to the relevant RBI team members.
The team leader for each assessment is responsible for placing relevant assessment data
in the folders.
Upon submission of the Final Report (SAER), the Team Leader or Service Provider
Facilitator shall convene a presentation meeting at the proponent's offices.
Participants of this meeting shall include all team members, proponent representatives
and management, as required. It is important that any economic benefits derived from
the assessment are duly emphasized.
This presentation meeting should take place no later than three weeks following
delivery of the Final Report (SAER).
Information for RBI can be found in many places within a facility. It is important to stress that
the accuracy and precision of the data should match the sophistication of the RBI method used.
The individual or team must understand the sensitivity of the data needed for the program
before gathering any data.
Specific potential sources of information include and are not limited to:
1. Design and Construction Records / Drawings
a) Safety Instruction Sheets (SIS)
b) P&IDs, PFDs, etc.
c) Piping Isometric Drawings
d) Engineering Specification Sheets
e) Materials of Construction Records
f) Construction QA/QC Records
g) Codes and Standards Used (e.g., ASME SEC VIII, NB-23, ASME B31.3, etc.)
h) Protective Instrument Systems
i) Leak Detection and Monitoring
j) Isolation Systems
k) Inventory
l) Emergency Depressurizing and Relief Systems
m) Safety Systems
n) Fire-Proofing and Fire Fighting Systems
o) Layout
p) Line Designation Tables
q) Piping specification drawings
r) Corrosion coupons
s) Corrosion Allowance – SAES-L-105
2. Inspection Records
a) Equipment Inspection Schedules (EISs)
b) Inspection History (OSI data, T&I reports, OSI reports, worksheets)
c) Repairs, Replacements, and Alterations
3. Process Data
a) Fluid composition analysis including contaminants or trace components
c) Distributed control system data
Saudi Aramco: Company General Use
©Saudi Aramco 2019. All rights reserved. Page 46 of 74
Document Responsibility: Inspection Engineering Standards Committee SAEP-343
Issue Date: 24 January 2019
Next Planned Update: 24 January 2022 Risk-based Inspection (RBI) for Saudi Aramco Facilities
Inspection
Inspection Non-intrusive Inspection
Effectiveness Intrusive Inspection Example1-6
Category Example1-6
Category
For the total surface area:
50% UTT or RT of CML’s.
A Highly Effective 100% visual examination with Profile radiography made also be
random UTT measurements of performed at selected locations.
suspect areas,
For the total surface area:
>25% UTT or RT of CML’s.
B Usually Effective >50% visual examination with Profile radiography made also be
random UTT measurements of performed at selected locations.
suspect areas,
For the total surface area:
>25% visual examination with
>10% UTT or RT of CML’s.
random UTT measurements of
C Fairly Effective Profile radiography may also be
suspect areas,
performed at selected locations.
Or 100% hydrostatic or pneumatic
test 6.
For the total surface area: <10% UTT or RT of CML’s.
D Poorly Effective <5% visual examination without Profile radiography may also be
thickness measurements. performed at selected locations.
No inspection or ineffective No inspection or ineffective
E Ineffective
inspection technique inspection technique used
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Condition monitoring locations (CML’s) are set up by knowledgeable individuals
3. The number of CML’s and area for scanning, spot UTT or profile radiography) is one that will detect damage if occurring.
Refer to SAES-A-135 for guidelines.
4. Percentage refers to percent of established CML’s examined. Reference
5. Inspection Effectiveness for Heat Exchanger Bundles (Fin Fan Coolers & Shell/Tubes)
For Ferromagnetic Tubes:
“A” Effectiveness- >40% MFL and Visual Inspection of all accessible tubes. OR >25% IRIS Testing with Visual Inspection
“B” Effectiveness- 20-39% MFL and Visual Inspection. OR >15-25% IRIS Testing with Visual Inspection.
“C” Effectiveness- 10-19% MFL and Visual Inspection. OR 5-15% IRIS Testing with Visual Inspection.
“D” Effectiveness- <10% MFL and/or Visual Inspection only. OR <5% IRIS and/or Visual Inspection only.
Note: Actual MFL wall losses greater than 20% shall be quantified. Wide wall loss range (e.g., 20%-40%;
40%-60%) is not acceptable
6. Only if specified by the EIS.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-9 Example1-9
Category
For the total area: For the total Suspect area:
100% visual examination 100% coverage of the CML’s using
A Highly Effective AND manual UTSW, AUT or profile
100% follow-up at locally radiography.
thinned areas
For the total area: For the total Suspect area:
>75% visual examination >75% coverage of the CML’s using
B Usually Effective AND manual UTSW, AUT or profile
100% follow-up at locally radiography.
thinned areas.
For the total area: For the total Suspect area:
>50% visual examination >50% coverage of the CML’s using
AND manual UTSW, AUT or profile
C Fairly Effective 100% follow-up at locally radiography.
thinned areas.
Or 100% hydrostatic or
pneumatic test 6.
For the total area: For the total Suspect area:
>20% visual examination >20% coverage of the CML’s using
D Poorly Effective AND manual UTSW, AUT or profile
100% follow-up at locally radiography.
thinned areas.
No inspection, less than above For the total Suspect area:
E Ineffective recommendations or ineffective <20% coverage of the CML’s,
technique used. ineffective technique or no inspection
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Percentage coverage in non-intrusive inspection includes welds.
3. Follow-up inspection can be UT, pit gauge or suitable NDE techniques that can verify minimum wall thickness.
4. Profile radiography technique is sufficient to detect wall loss at all planes.
5. Suspect area is total surface area unless defined by corrosion engineer.
6. Inspection Effectiveness for Heat Exchanger Bundles (Fin Fan Coolers & Shell/Tubes)
For Ferromagnetic Tubes:
“A” Effectiveness- >40% MFL and Visual Inspection of all accessible tubes. OR >25% IRIS Testing with Visual
Inspection
“B” Effectiveness- 20-39% MFL and Visual Inspection. OR >15-25% IRIS Testing with Visual Inspection.
“C” Effectiveness- 10-19% MFL and Visual Inspection. OR 5-15% IRIS Testing with Visual Inspection.
“D” Effectiveness- <10% MFL and/or Visual Inspection only. OR <5% IRIS and/or Visual Inspection only.
Note: Actual MFL wall losses greater than 20% shall be quantified. Wide wall loss range (e.g. 20%-40%;
40%-60%) is not acceptable
7. Only if specified by the EIS.
8. Give an inspection effectiveness of “C” for performing 10% MFL of tubes, “B” for >25% and “A” for >50%.
9. Any area not subject to visual inspection shall be inspected using non-intrusive inspection methods.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1 Example1
Category
For the total surface area: No inspection techniques yet
100% Visual inspection and 20% PT of the available.
welds.
AND
A Highly Effective
100% Holiday test
AND
100% UT or magnetic tester for disbonding
for bonded liners.
For the total surface area: For the total surface area:
>75% Visual inspection < 20% PT of >95% coverage of the CML’s
welds. using advanced or manual UTSW
Usually AND scanning.
B
Effective >75% Holiday test
AND
>75% UT or magnetic tester for
disbonding for bonded liners.
For the total surface area: For the total surface area:
>35% Visual inspection and <20% PT of >67% coverage of the CML’s
welds. using advanced or manual UTSW
AND scanning.
C Fairly Effective
>35% Holiday test
AND
>35% UT or magnetic tester for
disbonding for bonded liners.
For the total surface area: For the total surface area:
>4% Visual inspection <20% PT of welds. >34% coverage of the CML’s
AND using advanced or manual UTSW
scanning.
D Poorly Effective >5% Holiday test
AND
>5% UT or magnetic tester for disbonding
for bonded liners.
No inspection or ineffective inspection No inspection or ineffective
E Ineffective technique used inspection technique used
Assumption:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
Inspection
Inspection
Effectiveness Soil Side Product Side
Category
Category
a. MFL Floor scan >90% & UT a. Commercial blast if required
follow-up b. Effective supplementary light
b. Include welds if warranted from c. Visual 100% (API STD 653)
the results on the plate scanning
d. Pit depth gauge
c. Manual UTSW scan of the critical
Highly e. 100% vacuum box testing of
A zone
Effective suspect welded joints
Coating or Liner:
a. Holiday test 100%
b. Adhesion test
c. Scrape test
a. MFL Floor scan >50% & UTSW a. Brush blast if required
follow-up b. Effective supplementary light
OR c. Visual 100% (API STD 653)
Usually b. EVA or other statistical method d. Pit depth gauge
B with Floor scan follow-up if
Effective Coating or Liner:
warranted by the result
a. Holiday test >75%
b. Adhesion test
c. Scrape test
a. Brush blast if required
a. MFL Floor scan >5% plates;
supplement with scanning near b. Effective supplementary light
Shell & UTSW follow-up; Scan c. Visual 100%
circle and X pattern d. Pit depth gauge
C Fairly Effective b. Progressively increase if damage Coating or Liner:
found during scanning
a. Holiday test >50%
c. Helium/Argon test
b. Adhesion test
d. Hammer test
c. Scrape test
e. Cut coupons
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-8 Example1-8
Category
For the total weld area: For the total weld area:
>75% WFMPT or ACFM of welds >75% AUT or manual UTSW scanning.
A Highly Effective
with manual UTSW follow-up of
relevant indications.
For selected welds: For selected welds:
>50 WFMPT or ACFM of welds >67% AUT or manual UTSW scanning
B Usually Effective with manual UTSW follow-up of OR
all relevant indications. AE testing with 100% follow-up of
relevant indications.
For selected welds: For selected welds:
>25% WFMPT or ACFM of welds >34% AUT or manual UTSW scanning
C Fairly Effective OR
with manual UTSW follow-up of
all relevant indications. 67% radiographic testing.
For selected welds: For selected welds:
>5% WFMPT or ACFM of welds >5-% AUT or manual UTSW scanning
D Poorly Effective with manual UTSW follow-up of OR
all relevant indications or
>34% radiographic testing.
No inspection or ineffective No inspection or ineffective inspection
E Ineffective
inspection technique used technique used
Assumptions;
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Cold bends may need inspection also for Caustic Cracking
3. Selected weld areas identified by corrosion engineer
4. UTSW – Ultrasonic testing shear wave
5. WFMPT – wet florescent magnetic particle testing as per SAEP-325. WFMPT shall be used as the initial Intrusive inspection
technique for Caustic Cracking. If no cracking is detected, then ACFM may be used in lieu of WFMPT for future Caustic
Cracking inspection. If cracking is detected by WFMPT, then follow-up inspection must be the same technique. Non-PWHT
equipment and equipment subject to frequent steam-out requires WFMPT.
6. ACFM – Alternating Current Field Measurement. Can be used if equipment has already been WFMPT tested AND provided
no history of cracking.
7. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2
8. RT inspection can be used in lieu of UTSW for piping less than or equal to 3 NPS.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-6 Example1-6
Category
For the total weld area: For the total weld area:
>75% WFMPT or ACFM of >75% AUT or manual UTSW scanning.
A Highly Effective welds with manual UTSW
follow-up of relevant
indications.
For selected welds: For selected welds:
>50% WFMPT or ACFM of >67% AUT or manual UTSW scanning
Usually welds with manual UTSW OR
B AE testing with 100% follow-up of
Effective follow-up of all relevant
indications. relevant indications.
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Selected weld areas identified by corrosion engineer
3. UTSW – Ultrasonic testing shear wave
4. WFMPT – Wet florescent magnetic particle testing as per SAEP-325. WFMPT shall be used as the initial Intrusive
inspection technique for Caustic Cracking. If no cracking is detected, then ACFM may be used in lieu of WFMPT for
future Caustic Cracking inspection. If cracking is detected by WFMPT, then follow-up inspection must be the same
technique. Non-PWHT equipment and equipment subject to frequent steam-out requires WFMPT.
5. ACFM – Alternating Current Field Measurement. Can be used if equipment has already been WFMPT tested AND provided
no history of cracking.
6. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2.
7. RT inspection can be used in lieu of UTSW for piping less than or equal to 3 NPS.
Table 10.7 – Guidelines for Assigning Inspection Effectiveness – Sulfide Stress Cracking
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-7 Example1-7
Category
For the total surface area: For the total surface area:
>75% WFMPT or FPT or ACFM of >75% AUT or manual UTSW
A Highly Effective welds with UTSW follow-up of scanning.
relevant indications.
Perform random hardness testing.
For selected areas: For selected areas:
>50% WFMPT or FPT or ACFM >67% AUT or manual UTSW
with UTSW follow-up of all relevant scanning
B Usually Effective OR
indications.
AE testing with 100% follow-up of
Perform random hardness testing.
relevant indications.
For selected areas: For selected areas:
>25% WFMPT or FPT or ACFM of >34% AUT or manual UTSW
welds with UTSW follow-up of all scanning
C Fairly Effective OR
relevant indications.
>67% radiographic testing.
Perform random hardness testing.
For selected areas: For selected areas:
>5% WFMPT or FPT or ACFM of >5% AUT or manual UTSW scanning
D Poorly Effective welds with manual UTSW follow-up OR
of all relevant indications. >34% radiographic testing.
Perform random hardness testing.
No inspection or ineffective No inspection or ineffective inspection
E Ineffective
inspection technique used technique used
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Selected weld areas identified by corrosion engineer.
3. UTSW – Ultrasonic testing shear wave
4. WFMPT – wet florescent magnetic particle testing as per SAEP-325. Initial testing for “SSC Intrusive inspection” shall
be WFMT.
5. FPT – Florescent penetrant testing
6. ACFM – Alternating Current Field Measurement
7. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-6 Example1-6
Category
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
>50% manual UTSW and follow >75% manual UTSW and follow up
up indications with TOFD or other indications with TOFD or other
acceptable AUT technique. acceptable AUT technique.
A Highly Effective HIC:100% Visual of total surface HIC: Three 1 ft2 areas manual UTSW
area of the base metal on equipment each
AND random UTSW of the base plate and the heads and on piping
metal, followed up using AUT for selected locations, All suspect areas
suspect areas. are to be followed up using AUT.
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
>25% manual UTSW and follow >50% manual UTSW and follow up
up indications with TOFD or other indications with TOFD or other
acceptable AUT technique acceptable AUT technique
B Usually Effective HIC:100% Visual of total surface HIC: Two ½ ft2 areas manual UTSW
area of the base metal on equipment each
AND random UTSW of the base plate and the heads and on piping
metal, followed up using AUT for selected locations, All suspect areas
suspect areas. are to be followed up using AUT
SOHIC: For the weld and HAZ:
SOHIC: For the weld and HAZ:
>5% manual shear wave and
>25% manual shear wave and
follow up indications with TOFD
follow up indications with TOFD or
or other acceptable AUT
other acceptable AUT technique
technique.
C Fairly Effective HIC: One 1 ft2 areas manual UTSW of
HIC: 100% Visual of total surface
the base metal on equipment each
area
plate and the heads and on piping
AND random UTSW of the base
selected locations, All suspect areas
metal, followed up using AUT for
are to be followed up using AUT
suspect areas.
SOHIC: For the weld and HAZ:
SOHIC: For the weld and HAZ:
<5% manual shear wave and
>5% manual shear wave and follow
follow up indications with TOFD
up indications with TOFD or other
or other acceptable AUT
acceptable AUT technique.
technique.
D Poorly Effective HIC: One ½ ft2 areas manual UTSW
HIC: 100% Visual of total surface
of the base metal on equipment each
area
plate and the heads and on piping
AND random UTSW of the base
selected locations, All suspect areas
metal, followed up using AUT for
are to be followed up using AUT
suspect areas.
No inspection or ineffective No inspection or ineffective
E Ineffective
inspection technique used inspection technique used
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Inspection Area; Welds and plates that are susceptible to the damage mechanism.
3. UTSW – Ultrasonic testing shear wave
4. TOFD – Time of Flight Diffraction
5. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140.
6. HAZ – Heat affective zone
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-6 Example1-6
Category
For the total weld area: For the total weld area:
>75% WFMPT or ACFM with >75% AUT or manual UTSW
A Highly Effective manual UTSW follow-up of scanning.
relevant indications.
Assumptions;
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Selected weld areas identified by knowledgeable individual
3. UTSW – Ultrasonic testing shear wave
4. WFMPT – Wet florescent magnetic particle testing as per SAEP-325.
5. ACFM – Alternating Current Field Measurement
6. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140.
Inspection
Inspection Intrusive Inspection Example1- Non-intrusive Inspection
Effectiveness 4
Category Example1-4
Category
For the total surface area: No inspection techniques yet available
100% Visual inspection and to meet category A requirements.
>95% dye penetrant or eddy
A Highly Effective current test with manual
UTSW follow-up of relevant
indications.
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Selected weld areas identified by corrosion engineer
3. UTSW – Ultrasonic testing shear wave
4. AUT – Advanced ultrasonic testing; Approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-5 Example1-5
Category
For the total surface area: No inspection techniques yet available to
100% Visual inspection and meet category A requirements.
>75% Dye penetrant or eddy
A Highly Effective
current test with manual UTSW
follow-up of relevant
indications.
For selected areas: For selected areas:
100% Visual inspection and >75% manual UTSW scanning and
>50% dye penetrant or eddy AUT
B Usually Effective OR
current testing with manual
AE testing with 100% follow-up of
UTSW follow-up of all relevant
relevant indications.
indications.
For selected areas: For selected areas:
100% Visual inspection and >67% AUT or manual UTSW
>25% dye penetrant or eddy scanning
C Fairly Effective current testing with manual OR
UTSW follow-up of all relevant >67-100% radiographic testing.
indications.
Assumptions:
1. Areas selected by corrosion engineer.
2. Inspection quality is high and all NDT is performed in accordance with approved procedures.
3. UTSW – Ultrasonic testing shear wave
4. AE – Acoustic Emissions
5. AUT – Advanced ultrasonic testing; approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-7 Example1-7
Category
For the total weld area: For the total weld area:
>75% WFMPT or ACFM with >75% AUT or manual ultrasonic
A Highly Effective scanning.
manual UTSW follow-up of
relevant indications.
For selected welds: For selected welds:
>50% WFMPT or ACFM with >67% AUT or manual ultrasonic
manual UTSW follow-up of all scanning
B Usually Effective OR
relevant indications.
AE testing with 100% follow-up of
relevant indications.
For selected welds: For selected welds:
>25% WFMPT or ACFM with >34% AUT or manual ultrasonic
C Fairly Effective manual UTSW follow-up of all scanning
OR
relevant indications.
>67% radiographic testing.
For selected welds: For selected welds:
>5% WFMPT or ACFM with >5% AUT or manual ultrasonic
D Poorly Effective manual UTSW follow-up of all scanning
relevant indications. OR
>34% radiographic testing.
No inspection or ineffective No inspection or ineffective inspection
E Ineffective
inspection technique used technique used
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Selected weld areas identified by knowledgeable individual.
3. UTSW – Ultrasonic testing shear wave
4. WFMPT – wet florescent magnetic particle testing as per SAEP-325.
5. ACFM – Alternating Current Field Measurement
6. AE – Acoustic Emissions
7. AUT – Advanced ultrasonic testing; approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2.
Inspection
Inspection Intrusive Inspection Non-intrusive Inspection
Effectiveness
Category Example1-6 Example1-6
Category
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
>50% manual shear wave and follow >75% manual shear wave and
up indications with TOFD or other follow up indications with TOFD
acceptable AUT technique. WFMPT or other acceptable AUT technique.
A Highly Effective >50% of weld seams. HIC: Three 1 ft2 areas manual UTSW
HIC:100% Visual of total surface area of the base metal on each plate and
AND random manual UTSW of the the heads and indications followed
base metal with indications followed up with using AUT.
up on using AUT.
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
>25% manual shear wave and follow >50% manual shear wave and
up indications with TOFD or other follow up indications with TOFD or
acceptable AUT technique. other acceptable AUT technique
B Usually Effective
WFMPT >20 to 49% of weld seams. HIC: Two ½ ft2 areas manual UTSW
HIC:100% Visual of total surface area of the base on each piping circuit or
AND random manual UTSW with equipment and indications followed
indications followed up on using AUT. up with AUT.
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
>5% manual shear wave and follow >25% manual shear wave and
up indications with TOFD or other follow up indications with TOFD
acceptable AUT technique. WFMPT or other acceptable AUT technique
C Fairly Effective <5 to 20% of the weld seams. HIC: One 1 ft2 areas manual UTSW of
HIC: 100% Visual of total surface area the base metal on each piping circuit
AND random manual UTSW with or equipment and indications
indications followed up on using followed up with AUT.
AUT.
SOHIC: For the weld and HAZ: SOHIC: For the weld and HAZ:
<5% manual shear wave and follow >5% manual shear wave and follow
up indications with TOFD or other up indications with TOFD or other
acceptable AUT technique. WFMPT acceptable AUT technique.
D Poorly Effective
<4% of the weldments. HIC: One ½ ft2 areas manual UTSW
HIC: 100% Visual of total surface area of the base on each piping circuit or
AND random manual UTSW with equipment and indications followed
indications followed up on using AUT. up with AUT.
No inspection or ineffective inspection No inspection or ineffective
E Ineffective
technique used inspection technique used
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Inspection Area - welds and plates that are susceptible to the damage mechanism.
3. UTSW – Ultrasonic testing shear wave WFMPT – wet florescent magnetic particle testing as per SAEP-325.
4. TOFD – Time of Flight Diffraction
5. AUT – Advanced ultrasonic testing; approved Advanced UT techniques are listed in SAEP-1140, paragraph 5.1.3.2.
6. HAZ – Heat affective zone
Inspection
Inspection
Effectiveness Inspection1
Category
Category
Highly Visual inspection of >95% of the exposed surface area with follow-up by UT,
A
Effective RT or pit gauge as required.
Usually Visual inspection of >60% of the exposed surface area with follow-up by UT,
B
Effective RT or pit gauge as required.
Fairly Visual inspection of >30% of the exposed surface area with follow-up by UT,
C
Effective RT or pit gauge as required.
Poorly Visual inspection of >5% of the exposed surface area with follow-up by UT, RT
D
Effective or pit gauge as required.
Visual inspection of <5% of the exposed surface area with follow-up by UT, RT
E Ineffective
or pit gauge as required.
Assumption:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
Assumptions:
1. Suspect areas include damaged insulation, penetrations, terminations, etc.
2. Inspection quality is high and all NDT is performed in accordance with approved procedures.
3. Surface preparation is sufficient to detect minimum wall for the NDE technique used to measure thickness.
Inspection
Inspection
Effectiveness Inspection1, 2
Category
Category
For the suspected surface area: 100% Visual inspection and 100% dye
A Highly Effective
penetrant or eddy current test with UTT follow-up of relevant indications.
For the suspected surface area: 100% Visual inspection and greater than 60%
B Usually Effective dye penetrant or eddy current testing with UTT follow-up of all relevant
indications.
For the suspected surface area: 100% Visual inspection and greater than 30%
C Fairly Effective dye penetrant or eddy current testing with UTT follow-up of all relevant
indications.
For the suspected surface area: 100% Visual inspection and greater than 5%
D Poorly Effective dye penetrant or eddy current testing with UTT follow-up of all relevant
indications.
Less than “D” effectiveness or no inspection or ineffective inspection
E Ineffective
technique used.
Assumptions:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
2. Suspected area is the area identified by corrosion engineer or 100% Acoustic Emission testing maybe used to
identify suspect areas.
Inspection
Inspection
Effectiveness Insulation Removed Insulation Not Removed
Category
Category
For the suspected area: No inspection techniques yet available
100% external visual inspection meet requirements
prior to removal of insulation
Assumption:
1. Inspection quality is high and all NDT is performed in accordance with approved procedures.
Inspection
Inspection
Effectiveness Inspection1-
Category
Category
Inspection techniques for HTHA are not available to qualify for a Category A
A Highly Effective
inspection.
Inspection of susceptible areas with the following techniques:
NDT using Phased Array Total Focusing Method (PAUT TFM), TOFD
Advanced Imaging, Wet Fluorescent MPT and in-situ metallography.
For Equipment: Minimum three locations of (24”x24”) in the parent metal
and three weld locations (24”) NDT scanning for each component (Shell and
Usually
B Heads).
Effective
For Piping: Two locations of (12”x12”) in the parent metal and two weld
locations (12”), per 50 ft of piping.
PAUT TFM for parent metal. ToFD Imaging for welds and heat affected
zone. Wet Fluorescent MPT and in-situ metallography to be used for parent
metal and weld locations.
Inspection of susceptible areas with the following techniques:
NDT using AUBT, Phased Array, ToFD. Wet Fluorescent MPT and in-situ
metallography.
For Equipment: Minimum two locations of (24”x24”) in the parent metal
C Fairly Effective NDT scanning for each component (Shell and Heads). Wet Fluorescent MPT
and in-situ metallography to be used for parent metal and weld locations.
For Piping: two locations of (12”x12”) per 50 ft of piping NDT scanning.
AUBT for parent metal followed by Phased Array to verify indications,
TOFD for the weld and heat affected zone. Wet Fluorescent MPT and
in-situ metallography to be used for parent metal and weld locations.
Inspection of susceptible areas with the following techniques:
NDT using AUBT, Phased Array and ToFD,.
For Equipment: One location of (24”x24”) NDT scanning for each
D Poorly Effective
component (Shell and Heads).
For Piping: One location of (12”x12”) per 50 ft of piping NDT scanning.
AUBT for parent metal followed by Phased Array to verify indications, TOFD
for the weld and heat affected zone
E Ineffective No inspection or ineffective inspection technique used
Assumptions:
1. PAUT, TOFD WFMPT and metallography or sampling can be used to confirm suspected indications.
2. Suspected Areas include all surfaces exposed to the HTHA environment, but corrosion or materials engineers shall
determine the most susceptible areas for monitoring
3. Selected areas are determined by individuals experienced in HTHA.
4. Inspection quality is high and all NDT is performed in accordance with approved procedures.
5. PAUT TFM – Phased Array total focusing method
6. PAUT – Phased array ultrasonic test
7. ToFD AI – Time of Flight Diffraction Advanced Imaging
8. ToFD – Time of flight diffraction
9. AUBT – Advanced Ultrasonic Backscatter Technique
10. WFMPT – Wet Florescent Magnetic Particle Testing
11. In-Situ Metallography - Samples shall be taken on the process side and should include the welds, HAZ, and base metal.
Please follow the effectiveness examples in API RP 581 3rd Edition, Annex 2.C
Last T&I Date _________ Current EIS Interval _______ Next T&I Date ________
EIS Deviation/Extension Proposed Yes ___ No___ Proposed T&I date ________
Comments:
Last T&I Date _________ Current EIS Interval _______ Next T&I Date ________
Comments:
3. The RBI Team Leader is someone from the Proponent and is the single point contact for
the assessment.
4. The concurrence of the corrosion loops by CSD/CMP is only required for the new
construction projects. For in service plant, proponent corrosion engineer could concur
the corrosion loops.
5. The inventory Loops shall be concurred to by the Plant/operation Engineer from the
RBI team.
6. If the assessment includes any API STD 650/620/12C tanks the environmental
sensitivity requires concurrence by the Environmental Protection Department.
7. The assumptions shall be reviewed by the proponent RBI team and approved by the ID
RBI Team as per RBI validation Form-I and RBI validation Form-II.
8. RBI Databases, Inspection Plans, and Risk Analysis’s shall be reviewed by proponent
RBI facilitator and approved by the ID RBI Team as per RBI validation Form-I and
RBI validation Form-II.
Risk
FACILITY Ownership / Department
High Medium Low
Abandoned Chemical Storage
Material Planning and System Department x
Facilities
Abqaiq GOSP 2 North Ghwar Producing Department x
Abqaiq GOSP 3 North Ghwar Producing Department x
Abqaiq GOSP 5 North Ghwar Producing Department x
Abqaiq GOSP 6 North Ghwar Producing Department x
Abqaiq Pipelines Southern Area Pipeline Department x
Ain Dar GOSPs (1 & 2) North Ghwar Producing Department x
Ain Dar GOSPs (1 & 2) North Ghwar Producing Department x
Al-Hasa BP Eastern Region Distribution Department x
Al-Jouf BP Western Region Distribution x
Berri Gas Plant Berri Gas Plant x
Dhahran AFO Air Fueling Operations Department x
Dhahran BP E/C Region Distribution Department x
Dhahran Hills Water Wells Central Area Community Department x
Duba BP Western Region Distribution x
Haradh Southern Area Producing x
Hawiyah Southern Area Producing x
Jizan BP Western Region Distribution x
Ju’aymah Area(COT) Terminal Department x
Ju’aymah Gas Plant Juaymah NGL Fractionation Department x
KAIA AFO Air Fueling Operations Department x
KFIA AFO Air Fueling Operations Department x
Khurais Khurais Producing Department x
Khursaniyah Producing Field Ras Tanura Producing Department x
Najran BP Western Region Distribution Department x
North Jeddah BP Western Region Distribution Department x
Pump Station 1 East-West Pipelines Department x
Pump Station 10 East-West Pipelines Department x
Pump Station 11 East-West Pipelines Department x
Pump Station 2 East-West Pipelines Department x
Pump Station 3 East-West Pipelines Department x
Pump Station 4 East-West Pipelines Department x
Pump Station 5 East-West Pipelines Department x
Risk
FACILITY Ownership / Department
High Medium Low
Pump Station 6 East-West Pipelines Department x
Pump Station 7 East-West Pipelines Department x
Pump Station 8 East-West Pipelines Department x
Pump Station 9 East-West Pipelines Department x
Qassim BP C/E Region Distribution Department x
Qatif BP C/E Region Distribution Department x
Rabigh Bulk Plant Western Region Distribution Department x
Ras Tanura N&S Terminals Terminal Department x
Ras Tanura Refinery Ras Tanura Refinery x
Riyadh Air Base Air Fueling Operations Department x
Riyadh Refinery and Bulk Plants Pipelines, Distribution, and Terminals x
Safaniya & Tanajib Plants Northern Area Oil Operations x
Safaniya BP E/C Region Distribution Department x
Shedgum Southern Area Producing x
Sulayyil BP E/C Region Distribution Department x
Tabouk AFO Eastern Region Distribution Department x
Tabouk BP Western Region Distribution Department x
Taif AFO Western Region Distribution Department x
Turaif BP Western Region Distribution Department x
Uthmaniyah Southern Area Producing x
Yanbu COT Terminal Department x
Yanbu Gas Plant Yanbu NGL Fractionation Department x
Yanbu Refinery Yanbu Refinery Department x