DAILY HIGHWAY RECONSTRUCTION REPORT

Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Report No.: Enter


successive Report 103
Number.
Lot Number 03 Reconstruction
Document Purpose:
Date: Enter date of08-07-1402
daily report. Time Period of Inspection:Enter the time
07:00
period
AMof the
To report.
05:00 PM
Enter Start Time. The
Location:
Enter the
location of From km 40+000 ~ 60+000 Total Length =20 km
the report
subject.

Weather Working Day: ✘


Yes No Not Applicable Total Working Days to Date: 40days

M Sunny ✘ Cloudy Rainy


o o Weather Wend Speed km/hr. 14
Min the
6 Temperature: Indicate 7 lowest and
to highest temperature
ax of the day.
C C Conditions:
22
Impact: Comments: Dusty Air

Client Name: Ministry of Public Works (MOPW)

Contractor Name: Arya Khan Afghan Road Construction Logistic & Engineering Company.

CONTRACT NUMBER: MOPW/1401/W-018/NCBOPW/1402/W-/NCB

Activities in Progress
1 Existing Sub Base compaction completed from km 57+260 ~ 57+380
2 Base course paving for Carriageway Completed 48+350~ 48+530
3 Base course compaction completed from km 47+800 to 48+000
4 Base course compaction is in progress from 48+000 to 48+200
5 ATB paving for Carriageway Completed 46+550 to + 47+000
6 Existing asphalt removing is in progress from km
7 Application of Prime Coat for Carriageway

Deficiencies

Daily Lab Eng. Tests Record


N Stations R/D Layer/Activities Remarks
Structure Test Description Test Location
o
1 Road Sub Base FDT 56+635 Top layer Retest Pass
2 Road Sub Base FDT 56+670 Top layer Retest Pass
3 Road Sub Base FDT 55+880 Top layer Retest Pass
Road Existing Sub Base Top layer pass
4 57+425
FDT

Page 1
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Daily Lab Eng. Tests Record


Road Existing Sub Base Existing Sub pass
5 57+460
FDT base layer
Road Existing Sub Base Existing Sub fail
6 57+495
FDT base layer
Road Existing Sub Base Existing Sub pass
7 57+530
FDT base layer
Road Existing Sub Base Existing Sub fail
8 57+565
FDT base layer
Road Existing Sub Base Existing Sub pass
9 57+605
FDT base layer
Road Existing Sub Base Existing Sub pass
10 57+640
FDT base layer
Road Existing Sub Base Existing Sub fail
11 57+675
FDT base layer
Road Existing Sub Base Existing Sub fail
12 57+710
FDT base layer
Road Base Course Top layer Retest pass
13 47+640
FDT
Road Base Course Top layer pass
14 47+740
FDT
Road Base Course Top layer pass
15 47+790
FDT
Road Base Course Top layer pass
16 47+840
FDT
Road Base Course Top layer pass
17 47+890
FDT
18 Culvert # 59 Backfill FDT 58+812 third layer L/S pass
19 Culvert # 59 Backfill FDT 58+812 Third layer L/S pass
20 Culvert # 59 Backfill FDT 58+812 fourth layer L/S pass
21 Culvert # 59 Backfill FDT 58+812 fourth layer L/S pass

Safety Inspection / Safety Meetings: (Please write down if any meeting or safety inspection held)

Quantity of material supplied to site


Thick Ave Wide Ave Length Total Remarks
Description Item Unit (m) (m) (m) Volume
Sub base M3 273
Base course M3 216

Page 2
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Concrete
Asphalt M3 342

Material supplied to site

LABOR HOURS
The following labor hours were reported Work starting 7:00 AM to 5:00 PM
today:
Power Man / Labor Number
No Hours Worked Remarks
Classification Employees
1 Project Manager 1 9
Assistant project
2 manager 1 9
3 QC Manager 1 9
4 Alt QC Manager 1 9
5 Design Engineer 2 18
6 Chief surveyor 1 9
7 surveyors 4 36
8 Survey helpers 6 54
9 Lab Manager 1 9
10 Lab Technician 4 36
11 Structure Engineer 1 9
12 Site Engineer 2 18
13 Forman 2 18
14 Admin 2 18
15 Skilled Labor 90 810
16 Unskilled Labor 34 306
17 Operator 23 184
18 Driver 80 720
19 Flagman 2 18
20 Cook 2 18
Total hours worked on date: Total
260 2317

EQUIPMENT HOURS
The following Equipment hours were reported today
Serial Number Description Number of Machinery Hours Worked Remarks
1 Asphalt plant 1 9
2 Crush plant 1 9
3 Crush plant 1 9
4 Pavers 3 27
5 Transit Mixer 3 0
6 Oil Tanker 1 9
7 Rollers 9 81
8 Dump Truck 60 540
9 PTR 5 45
10 Tandem 2 18

Page 3
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

11 Excavator 5 45
12 Tractor 1 9
13 Grader 3 27
14 Water Tanker 7 63
15 Vehicle car 15 135
16 Mini Rollers 2 18
17 Loader 5 45
18 Bob Cat 1 9
Total Operating hours to date: Total 125 1098

Construction material on site Health, Safety & Environmental Arrangements


Existence Of Materials Material Arrangements
Yes Not N/A Yes Not N/A
Yes ✘ Not N/A Cement Yes ✘ Not N/A ✘ Safety Sign
Yes ✘ Not N/A Sand Yes ✘ Not N/A ✘ Safety Tape
Coarse Aggregate
Yes ✘ Not N/A Yes ✘ Not N/A Safety Glasses
(37.5mm)
Coarse Aggregate Safety/ Hard Soled
Yes ✘ Not N/A Yes ✘ Not N/A
(25mm) Shoes
Coarse Aggregate
Yes ✘ Not N/A Yes ✘ Not N/A Safety Gloves
(19mm)
Coarse Aggregate Safety Helmet/ Hard
Yes ✘ Not N/A Yes ✘ Not N/A
(12.5mm) Hat
Coarse Aggregate
Yes ✘ Not N/A Yes ✘ Not N/A Dust Mask
(9.5mm)
Yes ✘ Not N/A Stone Dust Yes ✘ Not N/A Reflective Vest
Yes ✘ Not N/A Base Coarse Material Yes ✘ Not N/A Safety Flag
Yes ✘ Not N/A Sub-Base Material Yes ✘ Not N/A Sign Board
Yes ✘ Not N/A Filling (Borrow Material) Yes ✘ Not N/A Barrier
Curing To Prevent
Yes Not N/A Stone Yes ✘ Not N/A
Dust
Transfer Of
Yes Not N/A Flat Stone Yes ✘ Not N/A
Excavated Materials
Cleaning Of Waste
Yes ✘ Not N/A Steel Bar Yes ✘ Not N/A Materials Engineering
Camp & Site Office
Yes Not N/A Seal Compound Material Yes ✘ Not N/A
Yes Not N/A Shutter Yes ✘ Not N/A
Yes Not N/A Water Pipe Yes ✘ Not N/A
Yes ✘ Not N/A Water For Construction Yes ✘ Not N/A
Yes ✘ Not N/A Bitumen Yes ✘ Not N/A
Yes ✘ Not N/A Admixture Yes ✘ Not N/A
Yes Not N/A Yes ✘ Not N/A

CONTRACTOR CERTIFICATION

Page 4
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Activity images: Base course paving for Carriageway Completed 48+350 to 48+530
~

Activity images: Existing Sub base Completed from km 57+260 to 57 + 400

Activity images: Base course compaction is in progress from 48+000 to 48+200


Page 5
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Activity images: ATB Paving is completed from km 46+550 to 47+000

Activity images: Base Course FDT is conducted in km 47+640 to 47+900

Page 6
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Activity images: Existing Sub base FDT is conducted in km 57+400 – 57 + 710

Page 7

Activity images: ATB Paving is completed from km 45+540 to 45 + 900


DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Activity images: Backfilling FDT is conducted in Culvert # 59 km 58+812

Reported By Arya khan Afghan Road construction company

Submitted By: Eng. Himat

Title: Quality Control Manager

Signature: Submitted Date: 08/07/1402

Page 8
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project

Page 9