Professional Documents
Culture Documents
30 09 2023 Daily Report
30 09 2023 Daily Report
Contractor Name: Arya Khan Afghan Road Construction Logistic & Engineering Company.
Activities in Progress
1 Existing Sub Base compaction completed from km 57+260 ~ 57+380
2 Base course paving for Carriageway Completed 48+350~ 48+530
3 Base course compaction completed from km 47+800 to 48+000
4 Base course compaction is in progress from 48+000 to 48+200
5 ATB paving for Carriageway Completed 46+550 to + 47+000
6 Existing asphalt removing is in progress from km
7 Application of Prime Coat for Carriageway
Deficiencies
Page 1
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
Safety Inspection / Safety Meetings: (Please write down if any meeting or safety inspection held)
Page 2
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
Concrete
Asphalt M3 342
LABOR HOURS
The following labor hours were reported Work starting 7:00 AM to 5:00 PM
today:
Power Man / Labor Number
No Hours Worked Remarks
Classification Employees
1 Project Manager 1 9
Assistant project
2 manager 1 9
3 QC Manager 1 9
4 Alt QC Manager 1 9
5 Design Engineer 2 18
6 Chief surveyor 1 9
7 surveyors 4 36
8 Survey helpers 6 54
9 Lab Manager 1 9
10 Lab Technician 4 36
11 Structure Engineer 1 9
12 Site Engineer 2 18
13 Forman 2 18
14 Admin 2 18
15 Skilled Labor 90 810
16 Unskilled Labor 34 306
17 Operator 23 184
18 Driver 80 720
19 Flagman 2 18
20 Cook 2 18
Total hours worked on date: Total
260 2317
EQUIPMENT HOURS
The following Equipment hours were reported today
Serial Number Description Number of Machinery Hours Worked Remarks
1 Asphalt plant 1 9
2 Crush plant 1 9
3 Crush plant 1 9
4 Pavers 3 27
5 Transit Mixer 3 0
6 Oil Tanker 1 9
7 Rollers 9 81
8 Dump Truck 60 540
9 PTR 5 45
10 Tandem 2 18
Page 3
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
11 Excavator 5 45
12 Tractor 1 9
13 Grader 3 27
14 Water Tanker 7 63
15 Vehicle car 15 135
16 Mini Rollers 2 18
17 Loader 5 45
18 Bob Cat 1 9
Total Operating hours to date: Total 125 1098
CONTRACTOR CERTIFICATION
Page 4
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
Activity images: Base course paving for Carriageway Completed 48+350 to 48+530
~
Page 6
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
Page 7
Page 8
DAILY HIGHWAY RECONSTRUCTION REPORT
Qalat to Muqur to Qalat 112 KM Re Construction Road Project
Page 9