Daily report of 22/04/2024
1
PROJET : UCB MUNGO BREWERY
PHASE 1 : GENERAL EARTHWORKS
__________________________________________________________________________________
Topographic
Nothing to report
control
External control
Geotechnical
9
control
Nothing to report
Incident or
10
others
1-CAMBUILD Total station broken down Monitoring Engineer
Observations of 2-Stand-by in the supply of pozzolan since
11 office 12/04/2024;
Engineering 3-Absence of the CAMBUILD lab team on site since NDINDJOCK Jacques M.
13/04/2024.
Backfilling of the area comprising axis 2, the storage area Cut at PF1
and axis 1 at PF1
Adjustment of the upper earthwork section (UES) at PF1. Compaction of a new layer at PF4.
___________________________________________________________________________
Daily report of 22/04/2024
2