Material Consumption Statement

Name of work:- Repair of Lining dowel and other puca structure of Bhadloo Disty From KM 0.00 to 17.100
Agency:- Mahadev Construction Company (V.684)

Item Unit Qty Cement Bajri Agg. 20 mm R.R. Stone


S No. @ Qty. In Bag @ Qty. In @ Qty. In @ Qty. In
Cum Cum Cum
(G-3) 08.20.2.1 Cement concrete lining cast in situ 1:3:6
(1 cement : 3 Bajari (Coarse sand) : 6 grit (graded
coarse aggregate) 20 mm nominal size) including use of
mechanical mixer, scaffolding , form work, dressing,
laying LDPE film , applying primer confirming to IS:
3384 on panel side,finishing, curing for 28 days etc. as
per specifications complete in all respect including cost
1 of primer and excluding the cost of LDPE/HDPE film /cum 120.93 4.5 54.42 0.47 5.68 0.94 113.6742 _ _
but including cost of jointing material.IN SIDE
SLOPES(7.5 cm thick lining)

(G-4) 011.2 Cement plaster with cement sand mortar


2 (1:3) including racking of joints, smooth finishing and /sqm 3983.08 0.154 613.39 0.016 63.73 _ _
curing etc.complete including all leads of all
construction materails of thickness. 011.2.3 12 mm
thick in 1 coats.
G-5) 010.1 Random Rubble stone masonry for
foundation and plinth (using R. R. stones where
75 % stones to be not less 15 cm in size in any
3 direction and weighing not less 23 kg) for /Cum 230.31 2.05 472.14 0.428 98.57268 _ _ 1.1 253.34
foundation including curing, all leads of
construction material and all taxes level etc.
complete. 010.1.5 In cement sand mortar 1:6

G-6) 011.3 Cement plaster with cement sand


mortar (1:4) including racking of joints, smooth
4 finishing and curing etc.complete including all /sqm 16.74 0.162 2.71 0.023 0.38502 _ _
leads of all construction materails of thickness.
011.3.2 20mm thick in 2 coats.
G-7) 011.10 Flush or ruled pointing on stone
5 masonry including racking of joints and curing /sqm 36 0.004 0.14 0.0043 0.1548 _ _
etc. complete. 011.10.2 Cement sand mortar 1:3

(G-9) 011.4 Cement plaster with cement sand


mortar (1:5) including racking of joints, smooth
7 finishing and curing etc.complete including all /sqm 4114.04 0.093 38.260572 0.016 6.582464 _ _ _ _
leads of all construction materials of thickness.
011.4.3 12 mm thick in 1 coats.
total 1181.06 175.11 253.34
1182
bags

Assistant Engineer