DETAIL OF ESTIMATE

Providing & fixing of A.P.M. for chak


Technical Data's
1 Name of chak :- KM off take :-

2 F.S.D. of Canal (D) :-

3 Free board of Canal (F.B.) :-

4 Bank width of Canal :-

5 Height of dowel ( H.O.D.) :-

6 Width of dowel (W.O.D.) :-

7 Clear length of culvert (C.L.C..) :-

8 Bed width of water course (B.W.) :-

9 Bed width of A.P.M (Bt.) :-

W = D/2
Side slope of Canal =
10 Effected width of Canal (E.W.C.)

(i) For Canal Having side slope :- 1.5:1

(ii) For Canal Having side slope :- 2:01

(4.4721 D +4xFB/2)

11 Effected perimeter of lining (E.P.L.)

(i) For Canal Having side slope :- 1.5:1

(ii) For Canal Having side slope :- 2:01

(1/2 x 0.9277(D+thickness of
lining /2)+4D + 4.4721 FB)

12 Bed Level of water course :-

13 Top level of lining

14 Crest level of A.P.M.

15 Y
16 Bed level of Canal :-

1 Dismantling stone rubble masonry including stacking of serviceable material and disposal of
unserviceable material within 50 meters lead.Stone masonry in cement mortar
3.00XWODXHOD = 3.00x.23x.23 = 0.16 Cum.
Total 1.16 Cum.
2 Dismantling of cement concrete and disposal of material with in a lead of 50 m Concrete 1:3:6 or
richer
3.00*(EPL+0.45)*0.075 3*(2.57+.45)*0.075 = 0.68 Cum.
Total 1.68 Cum.
3 Earthwork excavation in foundation, trenches or drains (not exceeding 1.5 m in width ) including dressing of
sides and ramming of bottom lift up to 1.5 m including getting out the excavated soil and disposal of surplus
excavated soil as directed with in a lead of 50 m all kind of soil
(i) 1/2x((.15+EWC)x(1.71+W+0.45)x(D+FB+0.45))x(D+FB+0.45))
1/2x(0.15+2.18)x(1.71+0.48+0.45)x(0.96+0.30+0.45))x(0.96+0.30+0.45) = 8.99 Cum.
(ii) ((1.22+W+CLC+0.45+width of toe
wall+0.15)x(1.71+BW+0.45)x(D+FB+0.45))x(D+FB+0.45)
((1.22+0.48+4.20+0.45+0.15)x(1.71+0.59+0.45)x(0.96+0.30+0.45))x(0.96+0.30+0.
52.27 Cum.
45)
Total 61.26 Cum.
4 Providing and laying cement concreting including curing, compaction etc. complete using stone aggregate 20
mm nominal size in foundation and plinth, excluding cost of shuttering using.M-10 grade mix 1:3:6
(1cement : coarse sand : 6 graded stone aggregate)
(i) (EWC+0.15)x2x(0.35+W+.15+.15)x0.23
(2.18+0.15)x2x(0.35+0.48+0.15+0.15)x0.23 = 1.21 Cum.
(ii) Wx((W+2x(0.35+0.15+0.15))x0.23
0.48x((0.48+2x(0.35+0.15+0.15))x0.23 = 0.20 Cum.
(iii) 2x(0.35+Bt+0.15+0.15)x4x0.23
2x(0.35+0.061+0.15+0.15)x4x0.23 = 1.31 Cum.
(iv) 2x(0.35+Bt+0.15+0.15)x0.35x0.23
2x(0.35+0.061+0.15+0.15)x0.35x0.23 = 0.11 Cum.
(v) 0.35x(0.35+0.15)x0.23 = 0.04 Cum.
(vi) 2x((0.15+0.35+Bt+0.35+0.15)+(0.15+0.35+Bt+0.35+0.15))/2x0.23
2x((0.15+0.35+0.061+0.35+0.15)+(0.15+0.35+0.061+0.35+0.15))/2x0.23 = 0.49 Cum.
(vii) (CLC+0.45-FB)x(0.15+0.35+Bt+0.35+0.15)x0.23
(4.20+0.45-0.30)x(0.15+0.35+0.061+0.35+0.15)x0.23 = 1.21 Cum.
(viii) 2x(0.35+0.15)x(0.15+0.35+0.15)x0.23
2x(0.35+0.15)x(0.15+0.35+0.15)x0.23 = 0.15 Cum.
(ix) (0.35+BW+0.35)x(0.35+0.15)x0.23
(0.35+0.59+0.35)x(0.35+0.15)x0.23 = 0.15 Cum.
CULVERT ARCH
(i) 2x((0.91+Bt)+(0.91+BW))/2x0.30
2x((0.91+0.061)+(0.91+0.59))/2x0.30 = 0.58 Cum.
(ii) (CLC+0.45-FB)x(0.91+BW)x0.30
(4.20+0.45-0.30)x(0.91+0.59)x0.30 = 1.96 Cum.
C.C. FOR COPING
(i) ((3.00-(1.40+W))x(0.30+0.26)/2x0.075
((3.00-(1.40+0.48))x(0.30+0.26)/2x0..075 = 0.03 Cum.
(ii) ((3.00-(1.40+W))x0.26x0.075
((3.00-(1.40+0.48))x0.26x0.075 = 0.02 Cum.
Total 7.46 Cum.
5(A) Brick masonary in foundation and plinth with brick class designation 100 In cement sand mortar 1:5( 1
cement : 5 Bajari )
(i) 4x((2x(0.35+Bt)x0.23
4x((2x(0.35+0.061)x0.23 = 0.76 Cum.
(ii) (w+EWC)x(W+2x0.35)x0.23
(0.48+2.81)x(0.48+2x0.35)x0.23 = 0.89 Cum.
(iii) 0.35x0.35x0.23 = 0.03 Cum.
(iv) 0.70x0.35x0.23 = 0.06 Cum.
(v) 2x(2x0.35+Bt+BW+2x0.35)/2x0.23
2x(2x0.35+0.061+0.59+2x0.35)/2x0.23 = 0.47 Cum.
(vi) (CLC+0.45-0.23)x(2x0.35+BW)x0.23
(4.20+0.45-0.23)x(2x0.35+0.59)x0.23 = 1.31 Cum.
(vii) (0.70+BW+0.70)x0.35x0.23
(0.70+0.59+0.70)x0.35x0.23 = 0.16 Cum.
Total 3.68 Cum.
5(B) Brick masonary in super strecture with brick class designation 100 In cement sand mortar 1:5( 1 cement : 5
Bajari )
Main wall U/S
(i) EWCx(W-Bt+0.35)x(D+FB)/2
2.18x(0.48-0.061+0.35)x(0.96+0.30)/2 = 1.22 Cum.
(ii) 2x0.35x(D+FB+HOD)
2x0.35x(0.96+0.30+0.23) = 1.04 Cum.
Main wall D/S
(i) EWCx0.35x(D+FB)/2
2.18x0.35x(0.96+0.30)/2 = 0.48 Cum.
(ii) (0.60+W)x0.35x(D+FB+HOD)
(0.60+0.48)x0.35x(0.96+0.30+0.23) = 0.56 Cum.
Dowel Portion U/S & D/S
U/S 0.70x0.35x(D+FB+HOD)
0.70x0.35x(0.96+0.30+0.23) = 0.37 Cum.
D/S 0.70x0.35x(D+FB+HOD)
0.35x0.35x(0.96+0.30+0.23) = 0.18 Cum.
Block Portion
2x2x0.35x(D+FB+HOD)
2x2x0.35x(0.96+0.30+0.23) = 2.09 Cum.
Culvert Portion
(i) 2x2x0.35xD = 2x2x0.35x0.96 = 1.34 Cum.
(ii) 2x(CLC+0.45-Fb)x0.35xD
2x(4.20+0.45-0.30)x0.35x0.96 = 2.92 Cum.
(iii) 2x0.35xCLCxFB
2x0.35x4.20x0.30 = 0.88 Cum.
Tail wall of outlet
2x0.70x0.35xD = 2x0.70x0.35x0.96 = 0.47 Cum.
Lining
(3.00-W-2x0.35)xEPLx0.12 = ( 3.00-0.48-2x0.35)x2.57x0.12 = 0.56 Cum.
Dowel
((3.00-(1.40+w))xWODxHOD = ((3.00-(1.40+0.48))x0.23x0.23 = 0.05 Cum.
For Arch
(i) 2x(0.90+Bt+0.90+Bt)/2x0.12 = 2x(0.90+0.061+0.90+0.061)/2x0.12 = 0.23 Cum.
(ii) (0.90+BW)x(CLC+0.45-FB)x0.12 = (0.90+0.59)x(4.20+0.45-0.30)x0.12 = 0.78 Cum.
Parapet
(i) (2xBtx0.35)x0.23x1.00 = (2x0.061x0.35)x0.23x1.00 = 0.01 Cum.
(ii) (2xBWtx0.35)x0.23x1.00 = (2x0.59x0.35)x0.23x1.00 = 0.09 Cum.
Cover APM portion
(Top of lining+HOD-C.R. level-Y)xBtx1
(182.26+0.23-181.066-0.16)x.061x1 = 0.08 Cum.
Total 13.35 Cum.
Ded. For C.C. 2x0.90x1.07x0.23 = -0.44 Cum.
Nett Qty. 12.91 Cum.
6 Supply and fixing in position of APM block made of CI as per standard specification with adjustable
arrangement and required fixtures including transportation to site second stage concreting in CC 1:2:4
centering shuttering painting with red oxide finishing etc. complete in all respect cost of APM block (all size)
per block
Supplying and fixing APM blocks 1 No
7 Providing and laying cement concreting including curing, compaction etc. complete using stone aggregate 20
mm nominal size in foundation and plinth, excluding cost of shuttering using.M-15 grade mix 1:2:4 (1 cement
:2 coarse sand : 4 graded stone aggregate)
(i) 3x(0.23+Bt+0.23)x0.23 = 3x(0.23+0.061+0.23)x0.23 = 0.36 Cum.
(ii) 2x3x1.07x0.23 = 1.48 Cum.
Total 1.84 Cum.
8
Cement plaster with cement sand mortar (1:3) including racking of joints, smooth finishing and curing
etc.complete including all leads of all construction materails of thickness. 12 mm thick in 1 coats.

Lining side
2xEPLx0.35 = 2x2.57x0.35 = 1.80 Sqm.
Inner side
(i) 2xEWCx(D+FB)/2 = 2x2.18x(0.96+0.30)/2 = 2.75 Sqm.
(ii) (W+1.22)x(D+FB+HOD) = (0.48+1.22)x(0.96+0.30+0.23) = 2.53 Sqm.
(iii) 4x(D+FB+HOD) = 4x(0.96+0.30+0.23) = 5.96 Sqm.
Lining side
(3.00-W-2x0.35)xEPL = ( 3.00-0.48-2x0.35)x2.57 = 4.68 Sqm.
Culvert
(i) 2x2xD = 2x2x0.96 = 3.84 Sqm.
(ii) 2x(CLC+0.45-Fb)xD = 2x(4.20+0.45+0.30)x0.96 = 9.50 Sqm.
Toe wall
2x0.35xD = 2x0.35x0.96 = 0.67 Sqm.
Ends
2x0.70xD = 2x0.70x0.96 = 1.34 Sqm.
Top
2x0.70x0.35 = 0.49 Sqm.
Sides
2x0.35xD = 2x0.35x0.96 = 0.67 Sqm.
Parapet
Inner side
(i) 1x(0.90+Bt)x0.60 = 1x(0.90+0.061)x0.60 = 0.58 Sqm.
(ii) 1x(0.90+BW)x0.60 = 1x(0.90+0.59)x0.60 = 0.89 Sqm.
Outer side
(i) 1x(0.90+Bt)x1.22 = 1x(0.90+0.061)x1.22 = 1.17 Sqm.
(ii) 1x(0.90+BW)x1.22 = 1x(0.90+0.59)x1.22 = 1.82 Sqm.
Sides
(i) 4x1.22x0.23 = 1.12 Sqm.
Top
(i) 1x0.23x(0.90+Bt) = 1x0.23x(0.90+0.061) = 0.22 Sqm.
(ii) 1x0.23x(0.90+BW) = 1x0.23x(0.90+0.59) = 0.34 Sqm.
Dowel
(i) ((3.00-0.35x(0.60-W))x(HOD+WOD+Bt) =((3.00-0.35(0.60-
0.48))x(0.23+0.23+0.061) =
1.54 Sqm.
Top
(i) (1.22+W)x0.35 = (1.22+0.48)x0.35 = 0.6 Sqm.
(ii) 1.22x0.35 = 0.43 Sqm.
(iii) 0.35x0.35 = 0.12 Sqm.
Sides
(1.22+W-0.35)x0.075 = (1.22+0.48-0.35)x0.075 = 0.10 Sqm.
(0.35+1.22)x0.23 = 0.36 Sqm.
Total 43.52 Sqm.
9 Earth work excavation in Ordinary soil, undressed with combined lead up to 50 mtrs
Ramp
2x5.00x18.00x0.60 = 108.00 Cum.
Total 108.00 Cum.
IRRIGATION DEPARTMENT
Canal :- I.G.N.P. Branch :- G.J.L.C. Distributary :- Bhadlo Disty. Minor :-
Canal Outlet Bed Bed f. S. D. Designed
Name C. C. F. S. L. R. L.
S Type of RD Dischar Level Level of F. S. L. in F. S. L. as Q in Setting of
of A. in in of H Bt. Y Hs. H. M. W. H.
No. Outlet and ge in in in Canal W/C per Reach Outlet
Outlet Ha. Canal Crest
side Cs. Canal W/C (D) Capacity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
ABSTRACT OF COST
Name of Work :- Providing and Fixing of APM for Chak 1 NKD of Nokh Disty of GJLC System.

BSR ref
S No Item No. Particulars Quantity Unit Rate Amount
Ch No/Page No

Dismantling stone rubble masonry including stacking of serviceable material and disposal
IGNP BSR 2021 of unserviceable material within 50 meters lead.Stone masonry in cement mortar
1 Item No 1.4 1.16 /Cum. 1032 1197.12
Ch No XV

IGNP BSR 2021 Dismantling of cement concrete and disposal of material with in a lead of 50 m Concrete
2 Item No 9.1 1.68 /Cum. 1019 1711.92
Ch No XV 1:3:6 or richer

Earthwork excavation in foundation, trenches or drains (not exceeding 1.5 m in width )


IGNP BSR 2021 including dressing of sides and ramming of bottom lift up to 1.5 m including getting out
3 Item No 18 61.26 /Cum. 104 6371.04
Ch No VII the excavated soil and disposal of surplus excavated soil as directed with in a lead of 50 m
all kind of soil

IGNP BSR 2021 Providing and laying cement concreting including curing, compaction etc. complete using
4 Item No 3.4 stone aggregate 20 mm nominal size in foundation and plinth, excluding cost of shuttering 7.46 /Cum. 4904 36583.84
Ch No IX using.M-10 grade mix 1:3:6 (1cement : coarse sand : 6 graded stone aggregate)

IGNP BSR 2021 Brick masonary in foundation and plinth with brick class designation 100 In cement sand
5 (A) Item No 6(d)+7(a) 3.68 /Cum. 4781 17594.08
Ch No X mortar 1:5( 1 cement : 5 Bajari )

IGNP BSR 2021


Brick masonary in super strecture with brick class designation 100 In cement sand mortar
5 (B) +(b) No 6(d)+7(a)
Item
Ch No X 1:5( 1 cement : 5 Bajari )
12.91 /Cum. 4903 63297.73
Supply and fixing in position of APM block made of CI as per standard specification with
IGNP BSR 2021 adjustable arrangement and required fixtures including transportation to site second
6 Item No 1 Ch 1 Each 7484 7484
No XVI stage concreting in CC 1:2:4 centering shuttering painting with red oxide finishing etc.
complete in all respect cost of APM block (all size) per block

IGNP BSR 2021 Providing and laying cement concreting including curing, compaction etc. complete using
7 Item No 3.3 stone aggregate 20 mm nominal size in foundation and plinth, excluding cost of shuttering 1.84 /Cum. 5403 9941.52
Ch No IX using.M-15 grade mix 1:2:4 (1 cement :2 coarse sand : 4 graded stone aggregate)

IGNP BSR 2021 Cement plaster with cement sand mortar (1:3) including racking of joints, smooth finishing
8 Item No 2.3 and curing etc.complete including all leads of all construction materails of thickness. 12 43.52 / Sqm. 194 8442.88
Ch No XI mm thick in 1 coats.

IGNP BSR 2021


9 Item No 2 Ch Earth work excavation in Ordinary soil, undressed with combined lead up to 50 mtrs 108.00 / Cum. 84 9072
No VII
TOTAL 161696.13
DESIGN CALCULATION FOR APM
1 Name of chak :- KM off take :-

2 CCA of Chak Ha.

3 Discharge of W/C Cummecs

4 Discharge of Canal Cummecs

5 Design FSL of Canal Meter

6 Design FSL of W/C Meter

7 Working Head (hw) Meter

8 FSD of Canal Meter

9 FSD of W/C Meter

W = D/2 Meter
Bed level of Canal Meter
10 Bed level of W/C Meter

Width of W/C Meter


1 Assume Bt. = and Y = (Y Should be between 2 to 3 Bt.)
2 q= 4.03X Bt. X Y X v Hs
or Hs = (q/4.03 x Bt.x Y )
Hs > Y = Hence O K
3 H the head measured from F.S.L in Canal to the crest of APM
i.e. H = Hs +Y = ( Hs+Y < F.S.D. ) Hence O K
4 Hm. The minimum modular working head is as follow :
0.82 Hs-Bt./2
Hm+Bt. < Hw
Check the difference of working (Hw) and Hm should not be less then 0.25 feet
Hw-Hm>0.25
5 Setting of outlet
s = H/D (It should be between 0.8 to 1.00 Hence O.K. )
6 The crest level of APM
Ext. F.S.L. of Parent Chanel - H
7 The rise of crest above the bed of W/C
Crest Level-Bed Level of W/C