Professional Documents
Culture Documents
T TE 251 oRT
TRNDAT
27|12/22
C
Cno qA
A HR-02
el i W.C.R.
R & - 0 2 W.C.R.
21 22
T.02
Selsleun
-3-03
712 22 W.C.R.
34 R D3K n AXT(A), 1l AXT (8), Up AXT CBD,
PTgARKZE 3RSMKaS
ITSORT
PTS(IR )
yukr ISTORT
w.c.R.
F S
3
t
at
T
Joint Survey Report
Date: 06-01-2023
Sub: Joint site survey to increase CSL UP
to 720 mt. at ADTL statioon.
Ref:- L.No. CHCIJBP/P/12/82
Date:24.12.2022.
As per above
message, we the undersigned, conducted
station in view of joint site of ADTL
increasing CSL of DN MIL, DN LIL and UP LL tosurvey 720 mt. The
observation and suggestions are as
1. UP M/L existing CSR under.
808 m CSL 772 m: No action
2. UP LIL
existing CSR 808 m CSL 675 m: 45 mt. Shortrequired
3. DN M/L
existing CSR 738 m CSL 708m: 12 mt. Short
4. DN LAL
existing CSR 738 m CSL 679m:41 mt. Short
DNM/L and DN LIL
Engineering work Required
() PT 105 A&B
shifting 35 m toward JBP end.
(I1) SEJ shifting 35 m toward
JBP end.
Il) G/J DN M/L
shifting 12 m toward JBP end.
(IV) G/J DN LIL
Shifting 44 m toward JBP End.
Required material::
(1) T-28 machine required for shifting the T/Out with four
hrs. Engineering block.
(11) Agency required with all tools &
(1) 4 No. 60 kg G/J plants execution of
for work.
(IV) 2 No. 52 kg G/J
(V 160 mt. 60 kg Rail
(VI) 120 mt. 52 kg Rail
(VII) 14 Set 60 kg Welding Potion
(VII) 10 Set 52 kg VWelding Portion
7 6 7 / 2 3
UP M/L & UP L/L JBP end turnout of point no. 113 A & 113 B can be shifted up to 40.0 Meters towards
JBP end.
s&T-1. Point no. 113 both ends cable shifting work required.
ENG. 1. UP M/L& UP L/L Glued joint will be shifted up to 45.0 m, towardsJBP end.
2.UP M/L&UP L/L SEJ will be shifted up to 45.0m, towards JBP end.
3. Point no. 113 A & 113 B will be shifted up to 45.0 m, towards JBP End.
both end.
4.DN/L/L glued joint will be shifted up to 10m
I/02
5. Earth
filling and rerturing wall work required for sand hump.
IRDWORK
1. Dismantle work required at
location:
LOcanion 1006/29 01-No portal, DA-02 No. , BKT-5 No, SI-01 no., T/o-01 No. Anchor-01 No., FTA-01 NO,
of CSL of
As per above message, we the undersigned, conducted joint survey of MYR Station in view increase
c)To achieve 720mtr CSL, Point No. 132 A&B will have to be shifted.
4. UP L/L-Existing cSR-673.mtr., Existing CSL- 660mtr. i.e. 60 mtr Short.
Suggestion to increase CSL 720mtr.
Option 1- UP Loop Starter Signal S-49 & Glued joint can be shifted up to 9.00mtr only at katni end. No
2- a-To achieve 720mtr CSL, Point No. 132 A & B will have to be shifted by 48-55mtr at STA
Option
END. This shifting will not disturb any other engg point, but length of existing dead end will be
reduced to 78-71mtr, .It may be converted as Sand Hump for purpose of isolation.
at satna end will be shifted accordingly and UDL-2 axle counter
a) UP &DN Loop Starter signal No.S-7
and Up Mn line track circuit 240T will be also be shifted towards STA end,
vi. If required the Dismantling and shifting of following strutctures and associated work estimation ie.
MYR/2017-3017,1143/33-34,MYR/2019-3019,MYR/1181, MYR/2021-3021, and UP AT mast will be
decided after marking/drawing of track given by PWAY Dpt.
Note- If point No. 132 A & B ls shifted up to 48-55 mtr, then CSL of Up loop & UP Main will be
available up to 720 mtr. & No any shifting of Starter Signal & Glued Joint at KTE end will be
required.