 Watchmen Shed Labour + Materials 12000

 Under Ground Demolish + Footing Materials Cost 35000

 Extra Bathroom 23000

 Elevation Glass 23500

 Elevation Slab For Entire Building ( Centring Work ) 30000

 Padauk Door Frame ( 2 Aero Frame With 2 Window ) 26000

 Exahust Fan 1260

 Bathroom Under Stair Case Labour + Materials and PVC Door 8500

 Bathroom Tile Laying Cost Material + Labour 9000

 Chamber Box ( Slab + Labour Charge ) 800

 Pesticide ( Material + Labour ) 6000

 Kitchen Teak Wood Frame 5400

 Upvc Window 3D Type 2500

 Cooling Tile Labour + Materials 35000

 Steps Tile Laying Labour + Material Cost 10000

 Elevation Tile Laying Labour + Material Cost 4500

 Burgalow for Elevation & Over Head Elevation Centring Work 30000

 Padauk Door + Window with Grill & (Flush Door For Kitchen) 53500

 Removed Kadapa Alter in Bedroom ( Labour + Material ) 2000

 Motor room Material + Labour Cost 4000

 Ramp Extra Cost 2 times Altered Labour + Materials 2000

 Electric Switch Alter For TV Unit 800

 Parapet Wall Altered in 1st Floor 4500

 Elevation SS Steel material + Labour G + 1 30000


 Padi Koondu 40000

 1st Floor Tiles Altered From Client Side ( Materials + Labour Loss ) 10000

 Over Head Tank Position Change & Floor Plastering, Plumbing 1600

 TOTAL 410860/-