DAILY ACTIVITIES REPORT

Title of Project: Three Storey Multipurpose Building


Location: Brgy. Balabag Pavia, Iloilo
Owner: Ann Fritzie G. Ras

Date: 4/25/2024 THURS

Weather:
A.M Sunny with 35% chance of Rain
P.M Partially Cloudy with 35% chance of Rain

MANPOWER SCHEDULE
DESIGNATION NUMBER OF PERSON ACTIVITY DESIGNATION NO. OF HOURS
Foreman 1 Overall Activities 8
Skilled Laborer 2 Excavation 8
Unskilled Laborer 2 Excavation 8
Unskilled Laborer 2 Fabrication of Footing RSB 8
Operators/Drivers 1 Backhoe - Excavation 8
Operators/Drivers 2 Dump Truck - Excavation 10

ACTIVITIES
ACTIVITIES TARGET ACCOMPLISHMENT ACTUAL ACCOMPLISHMENT
Excavation 6.27% 5.23%
Fabrication of Footing RSB 1.23% 1.23%

TOTAL 7.50% 6.46%


STATUS 1.04% DELAY
DELAY ON TIME ADVANCED
EQUIPMENT USED
EQUIPMENT NO. OF UNITS ACTIVITY DESIGNATION NO. OF HOURS
Backhoe (0.80m³)-SE 130 LC-2 1 Excavation 8
Dump Truck (12 yd³) 2 Excavation 10

OFFICIAL VISITORS REMARKS


Construction Chief Executive - Engr. L. S. Gunay Reinspection of RSB for Footing
Safety Officer - Engr. A.R. Belarga Installation of additional signs for excavation area

OTHER REMARKS
Engr. A.G. Ras All work suspended (3pm -5pm) due to rain

ENGR. ANN FRITZIE G. RAS