Weather:
A.M Sunny with 35% chance of Rain
P.M Partially Cloudy with 35% chance of Rain
MANPOWER SCHEDULE
DESIGNATION NUMBER OF PERSON ACTIVITY DESIGNATION NO. OF HOURS
Foreman 1 Overall Activities 8
Skilled Laborer 2 Excavation 8
Unskilled Laborer 2 Excavation 8
Unskilled Laborer 2 Fabrication of Footing RSB 8
Operators/Drivers 1 Backhoe - Excavation 8
Operators/Drivers 2 Dump Truck - Excavation 10
ACTIVITIES
ACTIVITIES TARGET ACCOMPLISHMENT ACTUAL ACCOMPLISHMENT
Excavation 6.27% 5.23%
Fabrication of Footing RSB 1.23% 1.23%
OTHER REMARKS
Engr. A.G. Ras All work suspended (3pm -5pm) due to rain