CSP # 1610 Project Name New Satellite Plants water transmission system (NSPWTS) Related Documentation/ Legislation
3 Loading & Unloading General site workers Falling of the load, 4 2 8 Placed the certified crane as per required load 4 1 4
of transformer Site Staff serious injury Assigned the competent rigger (certified)
Unloading must be under fully supervision as per safe work
procedure
IF THE RESIDUAL RISK RATING IS 16 OR ABOVE, then additional controls need to be developed for the activity
Legend: S àSeverity and LàLikelihood: Hierarchy of Controls: Elimination, Substitution, Engineering, Administrative, PPE
LIKELYHOOD
RA Team Name 1 2 3 4
Very Unlikely Unlikely Likely Very Likely Almost Certain
SEVERITY 1 2 3 4 5 Designation
Catastrophic 5 5 10 15 20 25
Critical 4 4 8 12 16 20 Prepared By: Approved By:
Serious 3 3 6 9 12 15
Medium 2 2 4 6 8 10 Engr. Sajid Hussain 16-08-2021
Minimal 1 1 2 3 4 5 HSE DEPARTMENT DATE HSE DEPARTMENT DATE
REV-03 Page 1 of 2
Hazard Identification and Risk Assessment – HIRA SF09-01
Routine Non Routine Task/Activity: Installation of Transformer RA No: RA-CVL/ELC_001 REVISION 0
RISK ASSESSMENT RISK CONTROLS
Original Risk Original Risk With Residual Risk With
Without Controls Present Control Additional Control Measures Additional Control
SN Hazard Identified Affected Person Risk Risk Control Measure Already in Use
S L Rate
S L Rate
Needed S L Rate
(1-5) (1-5) (1-5) (1-5) (1-5) (1-5)
Checked all parts of the crane prior to start the activity
Use mandatory PPE’s
REV-02 Page 2 of 2