NO DOCUMENTS DISCRIPTION RESPONSIBILITY AVAILABILE REMARK


1 Copy of approved Architect drawing( If not Consultant design )) Consultant -
2 Copy of construction plan ( By Contractor ) Contrator Stamped copy
3 Identity card copy of the owner and the applicant Contrator
4 Certificate of conformity of materials and specifications used in construction Contrator if applicable ( fro example , blocks , bricks , etc. )
5 Image of the site and sample the outer pigment Contrator if applicaple, pictures of the buildings Pigment and to provide the sample of paint on a plate
6 Re-marking cadastral Contrator through Third Party
7 Census forms - Estimaraa A4 & A3 filled and stamped by Contractor/Consultant Consultant -
8 list of all approved materials installed and their QCDD certificates numbers Contrator& MEP Subcontractor -
9 Certificates: Qualification Certificate Contrator& MEP Subcontractor -
10 Certificates: fire rated materials Contrator& MEP Subcontractor -
11 Certificates : Fire Alarm system materials Contrator& MEP Subcontractor -
12 Certificates : Others (Emergency Light) Contrator& MEP Subcontractor -
13 Reports : letter and report of confirmation that all openings sealed with approved fire rated materials Contrator& MEP Subcontractor -
MEP Contracting Company Qualification Certificate / Municipality license / CR Copy / Company ID/Personal
14 QID ( signatory )
Contrator& MEP Subcontractor -
15 Reports : smoke control, ventilation and pressurization systems If Applicaple
Reports : letter confirms that all fire rated drywalls and ceiling board assemblies are installed as manufacturer
16 listing catalogue
Contrator& MEP Subcontractor -
17 Reports : Lux reading Contrator& MEP Subcontractor
18 Reports : Emergency power supply systems InfraRoad Third Party
19 Reports : fire alarm systems and sound level (InfraRoad to complete testing & commissioning before it) Contrator& MEP Subcontractor -
20 Reports : other systems (Emergency Lights) Contrator& MEP Subcontractor -
21 Service request application Contrator -
22 Contracting Company Undertaking Contrator -
23 Consultant Engineering Office Undertaking Consultant -
24
25 Reports : Fire Fighting systems If Applicaple
26 letter confirms that the project has been complied as per QCDD approved drawings and all
systems have been installed and tested -