Professional Documents
Culture Documents
Design Calculation For Table Form and Loose Form - Signed
Design Calculation For Table Form and Loose Form - Signed
Reference No : RWTP-GB-PMD-DCL-000008
Revision : 00
Consultant
Approved by Tan Jin Soon (Sepakat Setia
Perunding)
Construction
Reviewed by Suzanne Ng.
Manager
TABLE OF CONTENTS
1 Introduction ......................................................................................................................... 1
2 Design Code and Reference ................................................................................................ 1
3 Design Criteria and Assumptions........................................................................................ 1
4 Design Calculations............................................................................................................. 2
5 Conclusion........................................................................................................................... 2
APPENDIX
Appendix A Analysis Result from Staad Pro
Appendix B Formwork Calculations
Appendix C Drawing
Appendix D Catalogue
SG. RASAU TEMPORARY WORK – STRUCTURAL CALCULATION
1 Introduction
The construction takes place at Sg. Rasau, and to construct reinforced concrete slab and beam. There
are two types of formwork system with varied materials. The aluminum formwork system consisted
of aluminum panel, c-channel, peri-up tower and jack base; whereas, timber formwork system
consisted of timber panel, c-channel, steel sections, peri-up tower and jack base, as well as aluminum
panel and nails as propping. This report will check the structural capacity of the proposed formwork.
1
SG. RASAU TEMPORARY WORK – STRUCTURAL CALCULATION
i. Fb = 13.2 N/mm2
ii. Fc = 11.1 N/mm2
8.1.4 Steel member size used
i. 100 × 50 × 5 mm @ 9.36 kg/m (py = 275 N/mm2)
ii. 75 × 50 × 3 mm @ 5.59 kg/m (py = 275 N/mm2)
iii. 75 × 40 × 5 mm @ 6.92 kg/m (py = 275 N/mm2)
iv. 38 × 38 × 2.3 mm @ 2.54 kg/m (py = 275 N/mm2)
11.0 Loading Data
i. Dead load (DL)
Self-weight - Varied according to frame sections
ii. Imposed load (LL)
Construction Load - 1.5 kN/m2
iii. Combination Load
Combination Load 1 - 1.2 DL + 1.2 LL
4 Design Calculations
The design calculations for the formworks are exhibited in the Appendix A.
5 Conclusion
From the design calculation, the proposed formwork system is safe to be used for the casting of beam
and slab. The erection of the formwork must ensure the use of materials and accessories are comply to
the technical data or specification provided by respective manufacturer/supplier and should be in good
working condition. After the erection of formwork system, it must be inspected by site safety officer
before used by the workers.
2
SG. RASAU TEMPORARY WORK – STRUCTURAL CALCULATION
Appendix A
Table Form & Loose Form Calculations
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Formwork
Rasau Temporary Work - Formwork Calculation for Table Form/Table Form_slab 1/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Rasau Temporary Work - Formwork Calculation for Table Form/Table Form_slab 2/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
ACI Committee 347 Rasau Temporary Work - Table Form (Beam & Slab)
BS5950
Formwork
DL Factor = 1.2
Factored DL = 7.992 kN/m
Rasau Temporary Work - Formwork Calculation for Table Form/Table Form_s&b 1/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Rasau Temporary Work - Formwork Calculation for Table Form/Table Form_s&b 2/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Formwork
Rasau Temporary Work - Formwork Calculation for Loose Form/Loose Form_Slab 1/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Rasau Temporary Work - Formwork Calculation for Loose Form/Loose Form_Slab 2/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
ACI Committee 347 Rasau Temporary Work - Loose Form (Beam & Slab)
BS5950
Formwork
DL Factor = 1.2
Factored DL = 7.992 kN/m
Rasau Temporary Work - Formwork Calculation for Loose Form/Loose Form_S&B 1/2
SG. RASAU TEMPORARY WORK - STRUCTURAL CALCULATIONS
Rasau Temporary Work - Formwork Calculation for Loose Form/Loose Form_S&B 2/2
SG. RASAU TEMPORARY WORK – STRUCTURAL CALCULATION
Appendix B
Drawings
5.02.24
KP
KP
KP
GEN
KP
GEN
KP
GEN
KP
GEN
KP
GEN
KP
KP
KP