Suitable and easily accessible space near the main entrance shall be
provided at a height of 0.6 Mt to 1.6 Mt above the ground level for
energy metering at the ground floor only. However, this is not applicable to
the existing installations where power supply has already been provided.
Old version: Suitable and easily accessible space near the main entrance shall
be provided at a height of 0.6 mtrs to 1.6 mtrs above the ground level for energy
metering at the ground floor / cellar floor.
Separate circuit for each installation shall be laid and terminated at the
common point of supply. The panel board and bus bar arrangements
shall be as approved by the Licensee which shall be arranged by the
Applicant at his cost.
6. Amended Version vide Notification No. K.E.R.C./COS/D/02/16-17 Dated:
22.11.2016 published in Karnataka Gazette dated: 22.11.2016
8. MCCB & ELCB shall be installed for the individual installations by the
Applicant / Consumer to have better selectivity. ELCB mentioned above
shall be installed at the entrance of the Individual premises.