NR Identification Code

SPECIAL PREAMBLES AND MEASUREMENT


METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 1 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

SPECIAL PREAMBLES AND MEASUREMENT


METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT

Firma electrónica avanzada


ARTURO ESTEBAN
GALVEZ MARIN
2023.04.23 19:32:24 -0400

filename: N046-YX-EM-A00001-05_Special Preambles and Measurement Method

05 06.04.2023 Review L. Fariello M. Zagaria I. Colladon


04 12.12.2022 Review L. Fariello M. Zagaria I. Colladon
03 10.11.2022 Review L. Fariello M. Zagaria I. Colladon
02 09.09.2021 Review L. Fariello A. Beltrame N. Colacino
MOD-A4DP-E is.4

01 30.07.2021 First issue L. Fariello A. Beltrame N. Colacino


Issue Date Reason for Issue – Revision Description Prepared Checked Approved

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 2 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

CONTENTS
1 INTRODUCTION...................................................................................................... 3
2 GENERAL CHARGES APPLICABLE TO ALL WORKS UNIT PRICES........... 3
3 CIVIL WORKS .......................................................................................................... 6
3.1 CODES A00 WORK AREA PREPARATION, GRUBBING AND SCRAPING, LIVELLING AND
COMPACTION ................................................................................................................................... 6
3.2 CODES A02 EXCAVATIONS .......................................................................................... 6
3.3 CODES A03 - A04 DEMOLITIONS AND DISMANTLING ................................................ 10
3.4 CODES A05 - EMBANKMENT – BACKFILLING .............................................................. 12
3.5 CODES A06 - TRANSPORTS OF EXCEEDING OF MATERIAL .......................................... 15
3.6 CODES A08 - CONCRETE WORKS .............................................................................. 16
3.7 CODES A09 - FORMWORKS ....................................................................................... 19
3.8 CODES A10 – REINFORCEMENTS ............................................................................... 20
3.9 CODES A11 - ANCHOR BOLTS AND EMBEDDED ITEMS ............................................... 22
3.10 CODES A12 - GROUTING AND WATER STOP JOINTS .................................................. 23
3.11 CODES A13 PROTECTION/WATERPROOFING FOR R.C. WORKS .................................. 24
3.12 CODES A14 - ROADS, YARDS AND UNPAVED AREA .................................................... 25
3.13 CODES A15 - PERMANENT FENCES AND GATES ......................................................... 27
3.14 CODES A16 - UNDERGROUND EARTHING SYSTEM (ONLY INSTALLATION) ................... 28
3.15 CODES A17 - UNDERGROUND DRAINAGE AND ELECTRICAL WORKS ........................... 29
3.16 CODES A18 CONCRETE BLOCK WALL ........................................................................ 32
4 ELECTRICAL WORKS ........................................................................................... 33
4.1 CODES B00 – CABLES INSTALLATION ........................................................................ 33
4.2 CODES B01 – EQUIPMENT CONNECTION ................................................................... 36
4.3 CODES B02 – SITE ELECTRICAL TESTS ..................................................................... 36
5 MECHANICAL WORKS ......................................................................................... 37
5.1 CODES C00 – PV TRACKERS INSTALLATION .............................................................. 37
5.2 CODES C01 – EQUIPMENT INSTALLATION .................................................................. 40
5.3 CODES C02 – ELECTRICAL OVERHEAD LINE INSTALLATION ........................................ 43
6 COMMISSIONING AND START-UP.................................................................. 44
6.1 CODES D00 – PV PLANT COMMISSIONING AND START-UP ACTIVITIES ...................... 44
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 3 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

1 INTRODUCTION

The present document is part and is intended to be used in conjunction with the other
documents included in the CONTRACT and in the TECHNICAL DOCUMENTATION.
Scope of the present document is to define all costs and charges included in the Unit Prices
and the relevant Method of Measurement.

2 GENERAL CHARGES APPLICABLE TO ALL WORKS UNIT PRICES

The Prices for CIVIL WORKS include also the cost for:
a) Mobilization and demobilization (assembly and disassembly) of all equipment, including
maintenance, spare parts, energy (electric and fuel).
b) Supply of all material necessary for the execution of the WORKS in accordance with
TECHNICAL DOCUMENTATION, except where expressly indicated to be supplied by
Others.
c) Executing and maintaining temporary roads and ramps to the working areas from the
existing roads works.
d) Cleaning and maintaining any permanent roads used by vehicles and equipment involved
with earth moving operations and construction works.
e) Maintaining the working area and excavations free from rain water and run-off water
(and sand deposited by sandstorms) in order to allow the operability of the construction
equipment during all the duration of the work. In particular, the execution of appropriate
temporary provisions (i.e.: slopes, earth ditches, earth containing walls, pits, etc.) in
such a way to collect water for its disposal, including the use of motor pumps where and
when necessary.
f) Replacing items belonging to SUBCONTRACTOR’s supply with any equivalent or higher
quality sort, subject to CONTRACTOR’s prior authorization, and without additional cost.
g) Execution of all engineering activities at SUBCONTRACTOR’s care as per Work
Requisitions
h) Wastages and extra material to comply with methods of measurement.

i) Protection of adjacent equipment, piping, facility (in particular electrical and instrument
installations) by suitable means during execution of SUBCONTRACTOR activities.
j) Removal, loading, transport, unloading and disposal to authorized dumping area
(including dumping fee) of any, scraps, waste and residual materials generated by
SUBCONTRACTOR.
k) Supply of all documents, certificates and execution of tests (including test in situ) as per
TECHNICAL DOCUMENTATION.
MOD-A4DP-E is.4

The Prices for ELECTRICAL WORKS include also the cost for:
a) Mobilization and demobilization (assembly and disassembly) of all equipment, including

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 4 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

maintenance, spare parts, energy (electric and fuel).


b) Supply of all material necessary for the execution of the WORKS in accordance with
TECHNICAL DOCUMENTATION, except where expressly indicated to be supplied by
Others.
c) Internal cleaning of all equipment and materials before and after installation.

d) Touch-up of equipment and materials if damaged during handling and installation.

e) Collection of cable drums and delivery back to SUBCONTRACTOR warehouse with the
list of cable quantities left on each drum, after work completion.
f) Limiting scrape/wastage within 3% of the total drum quantity for each drum of untagged
cables.
g) Supply and installation of nameplates/labels for the Equipment, where lacking.

h) Removal, loading, transport, unloading and disposal to authorized dumping area


(including dumping fee) of any, scraps, waste and residual materials generated by
SUBCONTRACTOR.
i) Supply of all documents, certificates and execution of tests (including test in situ) as per
TECHNICAL DOCUMENTATION.
j) Any other activity described in the work requisition and relevant attachments.

The Prices for MECHANICAL WORKS include also the cost for:
a) Mobilization and demobilization (assembly and disassembly) of all equipment, including
maintenance, spare parts, energy (electric and fuel).
b) Consumable materials, required for installation according to CONTRACTOR’s erection
drawings and specifications.
c) Coated slings to be used for handling and lifting activities in order to avoid any damages
to the paint protection.
d) Cleaning the material before erection.

e) Checking of the material integrity and conformity and informing CONTRACTOR about the
result.
f) Small adjustment of steel items such as steel members, ladders, gratings etc. if
necessary.
g) Connection
to earthing system according to local laws and regulation and/or
SUBCONTRACTOR's specifications.
h) Executing the work within the erection tolerances specified in the TECHNICAL
DOCUMENTATION.
i) Painting/galvanizing touching-up of parts damaged during transport and/or erection,
Including supply of painting/galvanizing material.
MOD-A4DP-E is.4

j) Erection and installation at any elevation in accordance with the drawings issued for
Construction
k) Execution of masks and spool pieces to replace parts not available when erecting.

l) Utmost care to the transport and erection of pieces, to avoid paint damaging as far as

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 5 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

possible (suitable hemp ropes, etc.)


m) Before beginning any work, SUBCONTRACTOR shall hand over all necessary documents
requested by Local Rules or Authority (safety documents, etc.) at CONTRACTOR’s care.
n) SUBCONTRACTOR shall supply all tests certificates relevant to all material requested by
Local Rules or Authority.
o) Any other activity described in the work requisition and relevant attachments.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 6 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3 CIVIL WORKS

3.1 CODES A00 Work Area Preparation, Grubbing and Scraping, Leveling and
Compaction

Work Area Preparation (Code A00AA)


a) Removal of stones and any obstacles from the work area, including superficial soil
(5cm).

Grubbing and scraping (Code A00AB)


a) Cut and removal of plants and heavy vegetation (if any);
b) Topsoil removal, including removal of roots and bushes, leveling and compaction;

Levelling and Compaction (Code A00AX)


Leveling and compaction and relevant test of bottom of excavation up to compaction value
in accordance with TECHNICAL DOCUMENTATION.

A. The Prices for CODE A00 include also the cost for:
Removal of existing obstacles / obstructions (i.e.: rocks, rip raps, etc.) visible or under
the actual soil level, which must be removed for the execution of the works.

B. METHOD OF MEASUREMENT
For Codes A00 (m2)
The area shall be calculated considering the horizontal surface of the perimeter of the area
to be scraped indicated in the drawings IFC. Soil natural profiles shall not be considered.

3.2 CODES A02 Excavations

DEFINITIONS
This work is applied to any kind and depth of excavation, by means of any kind of machine
or by hand, with or without the usage of explosive, irrespective of ground working
conditions and soil classification, with or without presence of water table.

Soil Classifications
Type A - Normal to strong consistency
MOD-A4DP-E is.4

Normal to strong consistency soils, such as loose material and/or grass roots, sand,
embankment, all clays such as short gravelly clay, common light clay, compact clay peat
and similar, moraine detritus, and all other soils which excavation and loading can be
carried out directly by hand or by mechanical excavator.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 7 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

Type B - Soft rock


Soft and friable rocks, such as normal schists, tuffs, soft tufaceous limestone, friable
sandstone and similar.
The excavation is normally carried out in two phases: at the beginning the soft rock is in-
situ crumbled by means of ripper-equipment, pneumatic hand drills or pneumatic hammer
excavator and afterwards loaded.

Type C - Solid rock


Hard to very hard rocks such as compact and shell limestone, dolomite, hard sandstone,
granite, basalt, porphyry and similar. The excavation is normally carried out in two phases;
at the beginning the solid rock is in- situ broken by blasting and/or special demolishing
tools and afterwards loaded.

Excavation Typologies
General excavation (Code A02AA)
General excavation is the type of excavation required to bring a defined area to a specific
level, on which the works are to be carried out for the piling work, foundation mats, road
trenches, etc. In detail, general excavations are those performed on an open area where
removal vehicles can operate at the same level of the excavation bottom, even using
temporary access ramps.
An excavation is considered general excavation when the planimetric surface is greater
than 100 m2 and the minimum width is greater than 3.5 m. up to any depth.

Limited section excavation (Code A02AB)


Limited section excavation means any excavation with reduced width (equal/less than 3,5
meters width and surface less than 100 m2) for foundations, walls, basins, ditches, pipe
systems, electrical trenches, etc. showing characteristics other than those under paragraph
A) and B) above.

A. The Prices for CODE A02 include also the cost for:
1. Extra excavation over the dimensions shown on the drawings for the execution of
formwork, shoring, trimming, slopes execution and protection, access ramps, planking,
structuring, supporting and underpinning, if necessary, clearing, and restoring till
backfilling works
2. Temporary supports as per safety requirements.
3. Surveying and detecting of existing underground obstacles either of natural or artificial
nature if specified in the TECHNICAL DOCUMENTATION.
4. Removal of existing obstacles / obstructions (i.e.: rocks, rip raps, etc.) visible or under
the actual soil level, which must be removed for the execution of the works.
MOD-A4DP-E is.4

5. Execution of finishing work by hand for excavations executed by machine, also in


presence of driven piles, existing foundations, etc.
6. Preservation of existing structures/plants, above ground and/or underground, if any.
7. On-site soil handling for the sampling and laboratory analysis activities.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 8 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

In particular for code A020A01– Overprice to general excavations for compaction of bottom
excavation- following costs are also included:
8. Leveling and compaction of bottom of excavation up to compaction value in accordance
with TECHNICAL DOCUMENTATION.

In particular for codes A02AB– Limited section excavation- following costs are also
included:
9. Temporary supply and installation of steel plates to be placed over road crossing
excavations to allow vehicular traffic.

In particular for code A020B01– Overprice to limited section excavations for compaction of
bottom excavation- following costs are also included:
10. Leveling and compaction of bottom of excavation up to compaction value in accordance
with TECHNICAL DOCUMENTATION.

In particular for codes A020B02 – Overprice for water table dewatering- following costs are
also included:
11. Submitting of design, calculation, drawings, chemical analysis, water table monitoring
and installation method to CONTRACTOR’s approval, Installation of any dewatering
system including supply and installation of all equipment such as, but not limited to,
pumps, well points, any type of pipes connections, inlet and outlet to the point of
discharge and relevant facilities for evacuation.
12. Transport, installation, maintenance of the system by specialized personnel, supply of
consumable material.
13. Maintenance the excavated area free from water table for execution of the required
works until the authorization of backfilling by CONTRACTOR and following removal of
the system and cleaning of the area.
14. Any damage to existing items or items under construction due to water drainage shall
be restored at SUBCONTRACTOR’s charge and expense.
In particular for codes A02AC– Excavated material characterization- following costs are
also included:
15. Site and laboratory tests to determine the chemical contents when requested by to
TECHNICAL DOCUMENTATION and local law, including the issue of relevant
documentation (final report and official certifications).

16. Equipment set up and coordination.

17. On-site operations carried out by specialized technicians.

B. METHOD OF MEASUREMENT
For Codes A02AA - General Excavations – (m3)
MOD-A4DP-E is.4

The surface area of the excavation shall be calculated on the basis of the planimetric
dimensions shown in construction drawings. The depth of excavation shall be the average
of the values measured between the original ground level (after scraping, if any) and the
bottom elevation of excavation shown on drawings issued for construction.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 9 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

The original ground level (after scraping if any) shall be defined by topographic survey (by
other) and verified by SUBCONTRACTOR and CONTRACTOR’s supervisor.
The extra excavation for slopes, access ramps, etc. shall not to be accounted.
The volume of existing foundations, piles, etc. present in the excavation shall not be
deducted.

For Codes A02OA01 - Overprice for compaction of bottom excavation– (m2)


The area shall be calculated considering the horizontal surface of the perimeter of the area
to be compacted indicated in the drawings IFC. Soil natural profiles shall not be considered.

For Code A02AB - Limited section excavation – (m3)


The volume of excavation for items as R.C. foundations, basins, concrete trenches, duct
banks, open ditch, etc., shall be calculated on the basis of the planimetric area of the item
(concrete, no lean concrete, plan surface as shown on construction drawings) multiplied
by the average depth taken between the ground elevation (NGE or PTS or PSG) and bottom
design elevation of the concrete item, included lean concrete thickness if any (regardless
to actual volume excavated). See ANNEX 1.
In case of soil improvement below foundations the volume shall be calculated on the basis
of the planimetric area of the soil improvement as shown on construction drawings
multiplied by the average depth taken between the ground elevation (NGE or PTS or PSG)
and bottom of the soil improvement (regardless to actual volume excavated). See ANNEX
2.
The excavation volume for underground pipes shall be calculated using the ANNEX 3 for
the definition of the width and the drawings issued for construction for the heights
considering the different elevations, if any, of the top and bottom of excavations.
The excavation volume for underground buried cables shall be calculated on the dimensions
shown in the drawings issued for construction.

For Code A02OB01 - Overprice for compaction of bottom excavation– (m2)


The area shall be calculated considering the horizontal surface of the perimeter of the area
to be compacted indicated in the drawings IFC. Soil natural profiles shall not be considered.

For Code A02AC - Excavated material characterization – (Lump Sum)


The unit price is applicable in a single solution for the whole project.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 10 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.3 CODES A03 - A04 Demolitions and Dismantling

DEFINITIONS
Demolition, dismantling and landfill transport of existing works (roads, buildings, ..) in
interference, according to TECHNICAL DOCUMENTATION.

A. The Prices for CODES A03 include also the cost for:
1. Any document to be issued by SUBCONTRACTOR and approved by CONTRACTOR,
according to project demolition/dismantling methods and procedures (calculation
report, drawings, method of statement etc).
2. Supply and install any means necessary to the stability of the structures during the
demolitions stage, in order to avoid sudden collapses of the structures themselves or
nearby; including any installation of protections for facilities beneath the demolishing
works.
3. Removal by any mean, loading, unloading and transport of demolished materials to
authorized dumping area
4. Any facilities and means (to be agreed with CONTRACTOR) to prevent dust formation
(including wetting prior to do), and during demolition or dismantling works.
5. Assistance to CONTRACTOR for obtaining any necessary authorization by Local
Authorities.
6. Cutting off and restoring, according to CONTRACTOR request, of existing systems of:
power, drinking water or supply/drain system, etc. Properly sealing of cut pipes both
temporary than permanently.
7. Removing and cutting of any items (which existence is known by SUBCONTRACTOR),
according to procedure to be agreed with CONTRACTOR.
8. Any excavation necessary for demolition activities. Filling activities after demolition
shall be accounted separately.

In particular for codes A03AB – Demolition of Fence and Gates - following costs are also
included:
9. Any cost for demolition and dismantling of relative concrete foundation including
excavation and following backfilling.

B. METHOD OF MEASUREMENT
The demolition/dismantling works shall be measured only on the basis of each volume
(m3) or surface calculated by the dimensions (width, length and height) as shown in the
drawings issued for construction or taken at site before demolition (in the latter case
dimensions must be countersigned by CONTRACTOR).
For Codes A03AA – (m3)
MOD-A4DP-E is.4

The volume shall be measured as per drawings issued for construction or measured in site
before demolition
For Codes A03AB - demolitions of fences and gates – (m)

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 11 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

The quantity to be paid for shall be the linear meters (m) as indicated into the drawings
issued for construction or measured in site before demolition, for any height (in the latter
case dimensions must be countersigned by CONTRACTOR).
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 12 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.4 CODES A05 - Embankment – Backfilling

DEFINITIONS
Embankment (or Fillings): means, but not limited to, the following:
a. Any filling for roads, yards, retaining earth dikes, dam, etc. (codes A05AA)

b. Any filling for roads sub-base and base (codes A05AB, A05AC)

Backfilling: means, but not limited to, the following:


c. Any backfilling of large area, when the planimetric surface is greater than 100 m2 and
the minimum width is greater than 3.5 m. (codes A05AD)
d. Any backfilling of limited section excavation (codes A05AE)

A. The Prices for CODES A05 include also the cost for:
1. Filling/backfilling using:

• approved excavated material on site or stockpiled in temporary deposit area


within the boundary of WORK SITE
• or excavated material treated in crushing and screening plant
• or material supplied by SUBCONTRACTOR from borrow pit
including loading, transport, unloading, levelling and compaction in accordance with
TECHNICAL DOCUMENTATION. If required, before filling / backfilling execution the
existing soil shall be compacted (see codes A020A and A020B).
2. In case of material treated in crushing and screening plant, shall be include power
(electrical and fuel) and any consumptions (water, lubricants) of plant.
3. Spraying of water to maintain the optimum moisture content, making slope profiling by
hand or mechanically as per project drawings.
4. Filling/Backfilling in presence of any construction works, pipes, etc. inside excavation
and preserving them from any damages deriving from this activity.
5. Supply CONTRACTOR with certificates of the material supplied by SUBCONTRACTOR.

6. Execution of the work by hand where the machine cannot be used or for finishing work.

7. Execution of site and laboratory tests on filling/backfilling material, roads, yards, earth
dikes, etc. according to TECNICAL SPECIFICATIONS and LOCAL REGULATIONS. On site
sampling and testing operations carried out by specialized technicians. Tests, analysis
and classifications by licensed laboratory. Final stamped technical report (including
official certifications).

For code A05A0 – Preparation of Subgrade


MOD-A4DP-E is.4

8. Leveling and compaction of subgrade before filling / backfilling soil layers.

For codes A05AB and A05AC - Sub-base / base course for road
9. Supply and execution by mixing in situ the materials in accordance with TECHNICAL
This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 13 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

DOCUMENTATION.

For codes A05AE04, A05AE05 – Backfill without compacting, for cables trenches:
10. Screening treatment of the excavation soil before filling the cable trenches.

11. For those codes, do not include compaction of the filling material

For codes A05AF - Crushing and screening plant - following costs are also included:
12. Costs arising from sizing and any permits/licenses.

13. Equipment mobilization, loss/wear & tear, maintenance, dismantling, moving and
positioning around the site.
14. The material treated, the power (electrical and fuel) and any consumptions (water,
lubricants) of crushing and screening plant is accounted for separately, it should not be
included in this item.

B. METHOD OF MEASUREMENT
For Codes A05AA, A05AB, A05AC Embankments – (m3)
The surface area of the filling shall be calculated on the basis of the planimetric dimensions
shown in construction drawings. The depth of filling shall be the average of the values
measured between the final filled level and the starting filling levels shown on drawings
issued for construction. If levels are not indicated in the drawings issued for construction,
the same shall be surveyed by SUBCONTRACTOR and certified by CONTRACTOR.
The slopes shall not to be accounted.
The volume of existing foundations, ditches, pits, catch basins, pipes (8” and over), ducts,
etc. shall be deducted.

For Code A05A0 – Preparation of subgrade– (m2)


The area shall be calculated considering the horizontal surface of the perimeter of the area
to be leveling and compacted indicated in the drawings IFC. Soil natural profiles shall not
be considered.

For Codes A05AD - Backfilling of large areas – (m3)


The surface area of the backfilling shall be calculated on the basis of the planimetric
dimensions shown in construction drawings. The depth of backfilling shall be the average
of the values measured between the final backfilled level and the starting backfilling levels
shown on drawings issued for construction. If levels are not indicated in the drawings issued
for construction, the same shall be surveyed by SUBCONTRACTOR and certified by
CONTRACTOR.
The slopes shall not to be accounted.
MOD-A4DP-E is.4

The volume of existing foundations, lean concrete, ditches, pits, catch basins, pipes (8”
and over), ducts, etc. shall be deducted.

For codes A05AE Backfilling limited section– (m3)

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 14 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

The volume of backfilling for items as R.C. foundations, basins, concrete trenches, duct
banks, open ditch, etc., shall be calculated deducting from the volume of the excavation,
the volume of the relevant concrete foundation and lean concrete, up to the grade level or
sub base of paving. See ANNEX 1.
In case of soil improvement below foundations the volume of backfilling shall be calculated
as above deducting also the volume of soil improvement. See ANNEX 2.
The backfilling volume for underground pipes shall be calculated deducting from the volume
of excavation the volume of the sand, pipes and other mechanical protection, if any.
The backfilling volume for underground buried cables shall be calculated deducting from
the volume of excavation the volume of the sand, pipe conduit and other mechanical
protection, if any.

For codes A05AF - Crushing and screening plant – (Lump Sum)


The following rules shall be applied to compensate the equipment mobilization. The price
list is fixed irrespective of the technology, the equipment features, set- up and capacity.
The unit price is applicable in a single solution for the whole project.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 15 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.5 CODES A06 - Transports of Exceeding of Material

DEFINITIONS
The exceeding excavated materials, from limited and general excavation, shall be disposed
to authorized dumping areas outside the boundary of site area, only if request by project
documentation or upon CONTRACTOR request.

A. The Prices for CODES A06 include also the cost for:
For codes A06AA01 - Transport outside the CONTRACTOR's factory of exceeded excavated
1. Transport of materials to authorized dumping areas outside boundaries including all
Dumping fees and submission to CONTRACTOR of the relevant to Dumping certificate
(loading and unloading included in the excavation prices).

B. METHOD OF MEASUREMENT
For codes A06AA01 - Transport outside the CONTRACTOR's factory of exceeded excavated
- (m3)
The same volume already calculated for the execution of excavation shall be used or part
of it, according technical documents.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 16 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.6 CODES A08 - Concrete Works

DEFINITIONS
Lean concrete (A08AA)
Lean concrete means any concrete with a low nominal strength used such as, bedding for
foundation, casing for underground piping, excavation filling, trust blocks, cable ducts, etc.

Structural concrete (A08AB)


Structural concrete means any concrete item with a nominal strength not less than 20
N/mm² (cylinder test).

A. The Prices for CODES A08 include also the cost for
1. Supply and transport of concrete to the casting point.

2. Concreting by means of concrete pumps, crane with bucket, belt and pipe conveyors,
and or any other suitable mean, at any height or depth.
3. Executing temporary props, walkways, protections, etc. of any height, dimension and
size and at any elevation necessary to implement the job.
4. Surface preparation (laitance removing, chipping, cleaning etc.)

5. Construction joints and shear keys for second phase pouring, including temporary
shuttering/formwork, including also the use of bond agent and any type of sealant if
necessary.
6. Formation of inclined planes such as the upper face of footings, sleepers, sloped paving
etc. cast without formwork.
7. Cleaning and draining of surfaces before and during pouring of concrete foundations
and/or other structures.
8. Cleaning of formworks and reinforcement, removing also mortar scattered due to
previous cast, before concrete pouring.
9. Cement.

10. Fine and coarse aggregates, including delivery of samples, and drying if necessary.

11. Water, including delivery of samples, and heating or cooling.

12. All necessaries admixtures to obtain and maintain the required properties of the
concrete, such as curing compounds, retarders, accelerators, waterproof etc. excluding
only: sulphate resistant, micro silica, fibers and hardeners, which shall be accounted
separately by dedicated unit rates.
13. Design of concrete mixes, preparation of laboratory and field trial mixes, submission of
detailed report to CONTRACTOR.
14. Provide, operate and maintain the concrete testing laboratory (in-situ or by third party).

15. Concrete batching, mixing, transporting, pouring, vibrating, working into Formwork and
MOD-A4DP-E is.4

around reinforcement and embedded items.


16. Any method required to execute concrete pouring during any weather conditions.

17. Concrete curing and protection including the provision of temporary impermeable
sheets, use of water sprays, any methods to limit temperature differential, any method
This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 17 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

to protect from wind and adverse weather condition.

In particular for codes A08AA – Lean concrete – the following costs are also
included:
18. Formwork, when necessary, for lean concrete, duct bank, pipe bedding and backfilling
concrete.
19. Preliminary sealing of the pipe ends to prevent obstruction and for visual inspection of
the pipe integrity after the construction of the concrete blocks and duct banks.
20. Painting of top of concrete or use of colour additive admixture as per TECHNICAL
DOCUMENTATION.
21. Any reinforcement steel for concrete duct bank if required in the TECHNICAL
DOCUMENTATION and drawings issued for construction.

In particular for codes A08AB – Structural Concrete - the following costs are also
included:
22. Any finishing work to concrete surface to achieve the finishing level as per TECHNICAL
DOCUMENTATION including formation of chamfers.
23. Executing the installation of suitable protections in order to avoid any damages and
moving during concreting to embedded plates, anchor bolts, pipes, etc.
24. Executing of concrete works of any shape, dimension and at any elevation.

25. Using of suitable material and construction method to obtain water tightness of concrete
elements where required into TECHNICAL DOCUMENTATION.
26. Watertight sealing of any holes done for construction purpose of concrete elements with
watertight characteristics
27. Concreting in presence of piles, pipes, embedded inserts, etc.

28. Execution by precast elements (either if required by CONTRACTOR or proposed by


SUBCONTRACTOR), including lifting lugs and any other ancillary material and activity
to complete the work.
15. Execution of site and laboratory tests on structural concrete and component materials,
according to TECNICAL SPECIFICATIONS and LOCAL REGULATIONS. Equipment
mobilization, setting up, coordination, dismantle activities. On site sampling and testing
operations carried out by specialized technicians. Tests, analysis and classifications by
licensed laboratory. Final stamped technical report (including official certifications).
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 18 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

B. METHOD OF MEASUREMENT
For Codes A08AA - Lean concrete
The concrete volume is to be calculated on the basis of the dimensions indicated on
drawings issued for construction.

For Codes A08AB – Structural concrete - (m3)


The Structural concrete volume shall be calculated on the basis of the dimensions indicated
in the drawings issued for construction.
The volume of embedded items, anchor bolts and anchor bolts sleeves shall not be
deducted.
The volume of embedded pipes, ducts, etc., over 16cm diameter or equivalent individual
surface shall be deducted from calculation of the concrete volume. See ANNEX 4
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 19 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.7 CODES A09 - Formworks

DEFINITIONS
Formwork for concrete is defined in accordance with the definition of “Structural Concrete
(A08AB)” set forth in chapter 8).

A. The Prices for CODES A09 include also the cost for
For Codes A09AA
1. Design, supply, fabrication and installation (at any height) of formwork system (of any
material) for concrete works according to TECHNICAL DOCUMENTATION, including
special formwork system requiring permitting.
2. Formwork surface finishing and/or treatment to obtain concrete surface finishing as per
TECHNICAL DOCUMENTATION.
3. Any necessary accessories (supports, props, brackets, nails, wires etc.), ancillary works
(including ground preparation) and sealing.
4. Any adjustment to allow embedded items installation.

5. Temporary openings (side ports), if necessary, for cleaning, inspection before and during
concrete pouring and/or to allow concrete pouring.
6. Dewatering, if necessary, in order to permit the dry work execution

7. Removal of formworks.

B. METHOD OF MEASUREMENT
For Codes A09AA - Formwork - (m2)
The formwork surface area to be considered shall be the surface wetted by the concrete
which dimensions are indicated on drawings issued for construction.
The formwork of boxes for anchor bolts shall not be accounted. Areas of opening less than
0,25 m2 shall not be deducted.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 20 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.8 CODES A10 – Reinforcements

DEFINITIONS

A. The Prices for CODES A10 include also the cost for:
1. Supply, transportation in site, fabrication and erection at any elevation.

2. Cleaning of the reinforcement from calamine, oil, grease loose rust etc. that may impair
the bond between the concrete and the reinforcement.
3. Scrap, joints and any bar used to maintain the reinforcements in their correct position
during concrete casting.
4. Supply, place and fix spacers, spiral cages, stirrups and supports for reinforcements as
well as spacers between formworks and bars according to TECHNICAL DOCUMENTATION.
5. Execution of electrical continuity, as per TECHNICAL DOCUMENTATION or local law,
including supply and installation of relevant connectors and embedded plates.
6. Preparation and issue of the reinforcement Bars Bending Schedule on the basis of
reinforcement / formwork drawings issued for construction by CONTRACTOR.
Bar Bending Schedules (B.B.S) may also be issued by CONTRACTOR but in this case shall
only be for reference.
7. Execution of tests on steel reinforcements and component materials, according to
TECNICAL SPECIFICATIONS and LOCAL REGULATIONS.7 Tests, analysis and
classifications by licensed laboratory. Final stamped technical report (including official
certifications).

In particular for codes A10AB – Wire welded mash - following costs are also included:
8. Any overlap.

B. METHOD OF MEASUREMENT

For Codes A10AA - Rebars - (Kg)


Rebars weight shall be calculated on the basis of the conventional steel bar weight per
meter as per ANNEX 5, of each diameter multiplied by reinforcement total length
(calculated as per below figure 1) resulting from SUBCONTRACTOR Bar Bending Schedule
by considering that overlaps not foreseen on drawings or Bar Bending Schedule issued by
CONTRACTOR shall not be accounted.
Wires, spacers, connectors and embedded plates for electrical continuity and other ancillary
material shall not be accounted.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 21 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

Figure 1

The unit length shall be calculated as follow:


- rebar with bends at 90° = straight bar length + hook(s) length – (2 rebar dia. for each
bend)
- rebar with bends at 45° = straight bar length + hook(s) length – (1 rebar dia. for each
bend)

Example calculation of unit net length : (1000 + 300 + 300) – [( 2 x 20 ) x 2] = 1520 mm

For Codes Wire A10AB - Welded Mesh - (Kg)


The weight of shall be calculated on the basis of conventional weight per square meter, as per
table ANNEX 5, multiplied by square meter of paving or other surface, as indicated on drawing
issued for construction by CONTRACTOR. The overlapping shall not be accounted.
Wires, spacers and other ancillary material shall not be accounted.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 22 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.9 CODES A11 - Anchor Bolts and Embedded Items

DEFINITIONS

A. The Prices for CODES A11 include also the cost for:
1. Cleaning of material before installation.

2. Checking of their position before and immediately after the cast, issuing the relevant
report.
3. Installation including any fixing method to maintain the items in position during casting
and further concrete curing.

In particular for codes A11AB – Embedded steel items - following costs are also included:
4. Supply of material in accordance with drawings issued for construction and TECHNICAL
DOCUMENTATION
5. Execution of coating and finishing (such as painting system, hot dip galvanization etc.)
as per TECHNICAL DOCUMENTATION.

B. METHOD OF MEASUREMENT
For Codes A11AA - Anchor Bolts - (Kg)
a. Supply and/or installation
b. The weight shall be calculated considering the length and diameter of the bolts as indicated
on the drawings issued for construction and the specific weight of steel (7.85 kg/dm3).
c. The nuts and washer weight shall not be accounted. Plates and sleeves, if any, shall be
accounted.

For Codes A11AB - Embedded steel items - (Kg)


Steel plates – supply and/or installation
The relevant weight is to be calculated using the dimensions shown in construction drawing
multiplied by the specific conventional weight of steel (7.85 kg/dm3).
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 23 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.10 CODES A12 - Grouting and Water Stop Joints

DEFINITIONS

A. The Prices for CODES A12 include also the cost for:
Codes A12AA – Grouting
1. Supply of material and execution of grouting (including pressure filling, if necessary) at
any elevation in accordance with TECHNICAL DOCUMENTATION, drawings issued for
construction and grouting supplier material instructions.
2. Preparation of surfaces to be grouted including cleaning and chipping. Cleaning of pockets
and boxes.
3. Obtain CONTRACTOR's authorization before carrying out any grouting.

4. Formworks, including any chamfer.

B. METHOD OF MEASUREMENT
For Codes A12AA - Grouting - (m3)
The volume shall be calculated on the basis of the dimensions indicated in the drawings
issued for construction and/or equipment vendor drawings, regardless of the actual volume
of grouting executed.
The volume of anchor bolts and key shear shall not be deducted.
Grouting inside anchor bolts sleeves shall not be accounted.
The anchor bolts pocket/boxes volume shall be accounted.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 24 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.11 CODES A13 Protection/Waterproofing for R.C. Works

DEFINITIONS

A. The Prices for CODES A13 include also the cost for:
1. Supply (including relevant certificates) and installation, at any elevation, in accordance
with TECHNICAL DOCUMENTATION and material supplier prescriptions including any
ancillary material and activity to complete the work.
2. Surface cleaning and preparation including dewatering and removal of all fins, sharp
edges, oil, grease and other loose foreign materials from all surfaces before installation.
3. Overlapping and edge sealing.

4. Execution on foundation and/or elevated concrete.

B. METHOD OF MEASUREMENT
The surface area (m2) shall be calculated on the basis of the dimensions, indicated in the
drawings issued for construction, relevant to the surface to be protected regardless the
overlapping.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 25 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.12 CODES A14 - Roads, Yards and Unpaved Area

DEFINITIONS
The codes A14 cover the bituminous layer courses, road protection, shoulders, curbstones,
signal, safety barrier, unpaved areas and all other accessory activities.
Excavations, sub-grades, embankment, sub-base and base course works are covered by
other codes’

A. The Prices for CODES A14 include also the cost for:
For codes A14AA and A14AB – bituminous layer courses and emulsion - following costs are
also included:
1. Execution of courses in accordance with TECHNICAL DOCUMENTATION including any
necessary ancillary works also manually executed where equipment cannot operate.
2. Execution and shaping of road levels and slopes.

3. Submission for CONTRACTOR approval of detail design and material characteristic and
mixtures of bituminous layer.
4. Any surfaces treatment including the supply and spreading of the primer coat and tack
coat for binder and wearing courses.
5. Execution of horizontal signals in accordance with drawings issued for construction.

6. Verification of levels and slopes according to TECHNICAL DOCUMENTATION and drawings


issued for construction, including the issue by SUBCONTRACTOR of final topographic
survey.
For codes A14AC – Slope protection - following costs are also included:
7. Surface preparation and installation of the required slope protection in accordance with
the technical documentation, including any ancillary works such as drainages, joints, etc.
For codes A14AD – Vertical Signals for roads and yards - following costs are also included:
8. Installation of vertical traffic signs, supplied according to drawings issued for construction
and local regulations, including earthworks, concrete foundations or fixing on paving or
existing concrete items, including painting or galvanization, if any.
For codes A14AE – Safety barriers for roads and yards - following costs are also included:
9. Installation of safety barriers, supplied according to drawings issued for construction and
local regulations, including earthworks, concrete foundations or fixing on paving or
existing concrete items, including painting or galvanization, if any.
For codes A14AF – Precast concrete curb for roads and yards - following costs are also
included:
10. Installation of precast concrete curb for roads and yards, supplied according to drawings
issued for construction and local regulations, including earthworks.
For codes A14AG – Geosynthetics - following costs are also included:
11. supply of the geosynthetic and supply of all the materials and equipment necessary for a
MOD-A4DP-E is.4

complete installation.
12. leveling and preparation of the installation surfaces;

13. execution regardless the slope and the shape of the installation surface;

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 26 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

14. joints between sheets, any type as per the design or NRN approval;

15. additional material due to overlapping and joints;

16. anchoring/linking to the surfaces, any type as per the design or NRN approval;

17. waste material resulting from jointing and shaping and relevant disposal.

B. METHOD OF MEASUREMENT
For codes A14AA and A14AB – bituminous layer courses and emulsion - (m2)
The surface area shall be calculated on the basis of the drawings issued for construction.
For codes A14AC – Slope protection – (m2)
The surface area shall be calculated on the basis of the drawings issued for construction.
For codes A14AD – Vertical Signals for roads and yards – (No.)
The works will be compensated according to the quantities (No.) of vertical signals on the
basis drawing issued for construction.
For codes A14AE – Safety barriers for roads and yards – (No.)
The works will be compensated according to the quantities (No.) of safety barriers on the
basis drawing issued for construction.
For codes A14AF – Precast concrete curb for roads and yards – (m.)
The works will be compensated according to length (m.) of safety barriers on the basis
drawing issued for construction.
For codes A14AG – Geosynthetics – (m2).
The price list is subdivided on the basis of the weight per unit area. The unit price shall be
applied to the area of the surface (m2) calculated on the base of the design dimensions..

Note
Other activities necessary for the execution of the works are compensated with different
codes as follows:
Excavation: see codes A02AA
Embankments: see codes A05AB
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 27 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.13 CODES A15 - Permanent Fences and Gates

A. The Prices for CODES A51 include also the cost for:
For codes AA15AA - following costs are also included:
1. Any earthworks (excavation, compaction, filling / backfilling, finishing works, if any, etc.)
and relevant foundations.
2. Any required painting.

3. Barbed wire and relevant supports.

4. Assure electrical continuity and installation of required elements to allow earthing


connections.
5. Execution of Permanent steel Fence as required in TECHNICAL DOCUMENTATION,
foundations, including wiring mesh, anti-thief fixing system, etc., and any necessary
ancillary material and activity to complete the work.
In particular for codes A15AB – Gates - following costs are also included:
6. Execution of Gates and Entrance Bar as required in TECHNICAL DOCUMENTATION and
any necessary ancillary material and activity to complete the work.
7. Electrical and instrument cables and devices, relevant connections and civil works up to
local control panel to be located within 15m from the gate / entrance bar (the local control
panel is included in the costs of these codes).

B. METHOD OF MEASUREMENT
For codes A15AA – (m)
The length shall be calculated on the basis of the drawings issued for construction.
See ANNEX 6

For codes A15AB – Gates of steel frame – (No.)


The works will be compensated according to the quantities (No.) of Gates on the basis
drawing issued for construction.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 28 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.14 CODES A16 - Underground Earthing System (only installation)

A. The Prices for CODES A16 include also the cost for:
1. Installation as required in TECHNICAL DOCUMENTATION, including any necessary supply
of ancillary material and activity to complete the work.
In particular for codes A16AA – Installation of earthing conductors - following costs are also
included:
2. Excavation and backfilling, including supply and laying of sand, if required by TECHNICAL
DOCUMENTATION.
3. Installation of earthing conductors in accordance with drawings issued for construction
including any required connection to earthing rods, equipment, steel structures,
foundations and intermediate joints connection of any type, any pvc/galvanized steel
conduit (including supply) for conductor protection.
In particular for codes A16AB – Installation of earthing bars - following costs are also
included:
4. Installation of earthing bars for earthing connection including supply and installation of
any fixing system (mechanical anchor, chemical anchor etc.) as per TECHNICAL
DOCUMENTATION.
In particular for codes A16AC – Installation of earthing rods - following costs are also
included:
5. Installation of earthing rods including supply and installation of relevant concrete pit and
any required civil works.

B. METHOD OF MEASUREMENT
For codes A16AA – Installation of earthing conductors - (m)
The length shall be calculated on the basis of the drawings issued for construction (earthing
system layout) regardless of the actual installed length. The length to execute connections
to earthing rods, equipment, steel structures and foundations shall not be accounted.
For codes A16AB – Installation of earthing bars - (No.)
The quantity of earthing bar shall be calculated by the number of earthing bar shown in the
drawings issued for construction.
For codes A16AC – Installation of earthing rods - (No.)
The quantity of earthing rods shall be calculated by the number of earthing rod shown in the
drawings issued for construction.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 29 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.15 CODES A17 - Underground Drainage and Electrical Works

A. The Prices for above works include also the cost for:
For codes A17AA, AA17AB e AA17AC – Supply and Installation of Underground piping -
following costs are also included:
a. Supply and installation as required in TECHNICAL DOCUMENTATION and drawings
issued for construction, including any necessary supply of ancillary material and activity
to complete the work.
b. Execution of extra excavation to allow execution of joints in trenches.
c. Keeping the excavations clean, preparing the subsoil with suitable supports to maintain
the pipe in correct position.
d. Internal cleaning of pipes and keeping clean and plugging the installed piping until the
systems have been accepted, in order to avoid the intrusion of foreign material.
e. Execution of isometrics if considered necessary by SUBCONTRACTOR for his own
convenience.
f. Supply and installation of "T", "Y", elbows, pipe/pipe branches, funnels etc., as per
TECHNICAL DOCUMENTATION and/or Vendor's instructions
g. Execution of any type of joints and sealing, as per TECHNICAL DOCUMENTATION and/or
Vendor's instructions.
h. Submitting, for CONTRACTOR's approval, the Method of Statements for the execution
of any type of joint.
i. Inserting of pipes inside sleeves previously installed including closing of the gap
between sleeves and pipes and supply and installation of spacers between pipes and
sleeves.
j. Supply and installation of valves, if required by TECHNICAL DOCUMENTATION,
including control part components such as handweels, levers, chains, extensions etc.
and cleaning and greasing of valve stems.

For codes A17AB – Underground conduits for electrical works - following costs are also
included:
k. Supply and installation as per TECHNICAL DOCUMENTATION and drawings issued
for construction, including any necessary supply of ancillary material and activity to
complete the work.
l. Spacers in case of multiple conduit to be installed in concrete encasement.
m. Proper fixing of the conduit before execution of the concrete casting or backfilling.
n. Any stub and relevant protection.
o. Any joints, fittings and special pieces to complete the works.
p. Sealing of the conduits at the departure from the concrete cable trench (or from the
MOD-A4DP-E is.4

cables pulling-pit) at paving crossing.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 30 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

For codes A17AD – Pits for sewer/drainage - following costs are also included:
a. Execution either cast in situ or precast as per TECHNICAL DOCUMENTATION and
drawings issued for construction, including any necessary supply of ancillary material
and activity (i.e. ladders, gratings, chequered plates, etc.) to complete the work.
b. Execution of incoming/outgoing holes and their sealing after pipes installation using
also non-shrink mortar as per TECHNICAL DOCUMENTATION.
c. Excavation (including leveling), compaction, backfilling, lean concrete, structural
concrete, formwork, reinforcement (including Bar Bending Schedule), any embedded
elements, structural steel elements etc.
d. Water proofing (inside and/or outside, by coating or membrane) including waterproof
joints as per TECHNICAL DOCUMENTATION.

For codes A17AE – Electrical and Instrument Pits - following costs are also included:
e. Execution either cast in situ or precast as per TECHNICAL DOCUMENTATION and
drawings issued for construction, including any necessary supply of ancillary material
and activity to complete the work.
f. Draining pipe, if necessary.
g. Execution of incoming/outgoing holes and their sealing after pipes installation as per
TECHNICAL DOCUMENTATION.
h. Excavation (including leveling), compaction, backfilling, lean concrete, structural
concrete, formwork, reinforcement (including Bar Bending Schedule), any embedded
elements, structural steel elements etc.
i. Any leveling, slope and finishing of the bottom slab.
j. Any kind of covers.
k. Water proofing (by coating or membrane) as per TECHNICAL DOCUMENTATION.

B. METHOD OF MEASUREMENT
For codes A17AA – Supply and Installation of Underground piping – (m):
The length of piping (m) through fittings, valves and flanges, if any, for each diameter, shall
be calculated from drawings issued for construction.
The reference line for the length is the center line of the pipe at the intersection of axis.
Starting and ending points of pipes shall be the internal side/surface of pits.
See ANNEX 7

For codes A17AB – Underground conduits for electrical works – (m):


The length of conduits (m) for each diameter, shall be calculated from drawings issued for
construction. The reference line for the length is the center line of the conduit at the
MOD-A4DP-E is.4

intersection of axis.
Starting and ending points of conduits shall be the internal side/surface of pits or at the
top of the paving. Any length above paving shall not be accounted.
See ANNEX 7

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 31 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

For codes A17AD – Sewer/drainage pits – (m3):


The volume (m3) shall be accounted on the basis of the internal dimension of the pit shown
on the drawings issued for construction. The height shall be measured by the difference
between the elevation of top surface of bottom of pit (without considering sump if any)
and the elevation of the bottom surface of the cover or cover slab.
Note: The prefabricated pits shall be accounted per number as indicated on drawing issued
for construction by CONTRACTOR.

For codes A17AE – Electrical and Instrument Pits – (No):


The prefabricated pits shall be accounted per number as indicated on drawing issued for
construction by CONTRACTOR.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 32 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3.16 CODES A18 Concrete Block Wall

DEFINITIONS

C. The Prices for CODES A18 include also the cost for:
a. Supply (including relevant certificates) and installation, at any elevation, in accordance
with TECHNICAL DOCUMENTATION and material supplier prescriptions including any
ancillary material and activity to complete the work, also in presence of obstacles,
constrains and particular shapes.
b. Surface cleaning and preparation including dewatering and removal of all fins, sharp
edges, oil, grease and other loose foreign materials from all surfaces before
installation.
c. Any accessories and provisions to obtain the horizontal/vertical flatness and the
regularity of the surface.
d. Any fasteners and/or bonding agents.
e. Using suitable sub-base, mortar and/or bonding agent according to the Manufacturer's
instructions.
f. Filling and sealing of joints in accordance with TECHNICAL DOCUMENATATION and
MANUFACTURER’s prescriptions.

D. METHOD OF MEASUREMENT
The surface (m2) will be calculated on the basis of the dimensions, indicated in the
drawings issued for the construction, relating to the surface to be closed.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 33 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

4 ELECTRICAL WORKS

4.1 CODES B00 – Cables Installation

The works in subject are relevant to medium and low voltage, solar and communication cable
laying and stringing, relevant connections and cable entry sealing.

A. The Prices for above works include also the cost for:
In particular, for CODES B00AA, B00AB, B00AC, B00AD – Laying of underground cables, the
following costs are included:
1. Technical assistance and supervision for civil works executed by Civil SUBCONTRACTOR
for underground cable trenches or duct bank.
2. Sealing of duct back conduits at both ends using PVC plugs.
3. Supply and installation of pulling cord in all spare conduits.
4. Withdrawal of all material from CONTRACTOR's warehouse and handling till the cable
is completely installed.
5. Handling and laying of all cables on drums or in hanks.
6. Laying of cables on cable trays, in concrete trenches or directly buried and in duct bank
(underground duct banks and manholes, underground PVC/PE conduits, underground
rigid steel conduit), once the relevant route is already completed, inspected and
released.
7. Supply, fastening and fixing of cables with cable ties, bands and galvanized steel
clamps (trefoil clamps) in accordance with TECHNICAL DOCUMENTATIONS (Typical
Installation Drawings).
8. Provision of cable mechanical protection, particularly for vertical runs close to the
working platforms whenever is required.
9. Supply and installation of tags fixed by suitable ties according to TECHNICAL
DOCUMENTATIONS (Cable List and Typical Installation Drawings), at both extremities,
in correspondence of each manhole/pit and along their route.
10. Clamp trefoil for cables, if applicable are in SubSUBCONTRACTOR scope of supply based
on typical installation.

In particular, for CODES B00AE, B00AF – Stringing of overhead cables, the following costs
are included:
11. Supply and installation of pulleys and all the equipment necessary for stringing the
cables.
12. Supply and installation of the guide wire

13. Handling and laying of all cables on drums or in hanks.


MOD-A4DP-E is.4

For CODES B00BA, B00BB, B00BC, B00BD, B00BE, B00BF – Installation of termination and
connections, the following costs are included:
14. Opening and closing of switchgears, panels, terminal boxes, junction boxes and

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 34 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

removal of shields and/or barriers where necessary, before and after connection.
15. Rotation of motor or equipment terminal boxes for a correct cable connection.

16. Drilling of gland plate/box for fixing cable gland.

17. Connection of cable to the equipment through cable glands or flexible conduit or directly
or through fireproof barrier.
18. Installation of ring type current transformer with suitable supports and connection to
their secondary circuits.
19. Sealing or installing fireproof barrier for cable inlet of the electric panels located in the
substations or buildings to avoid dust infiltration. The sealing procedure shall be agreed
with CONTRACTOR.
20. Supply and installation of suitable steel supports and clamps to hold the cables in place
under the electrical switchgears/panels and equipment.
21. Execution of all connections using tinned copper compression lugs by means of bolting
to be protected against corrosion.
22. For MV cables, execution of all connections using tinned copper compression lugs by
means of bolting for heat shrinkable kit and by plug-in type for elastimold type.
23. Depending from the wiring system requirements indicated in the project documents
and Typical Installation Drawings, connection activity includes the following, without
limitation:
• Cable sheath and armour cutting for cable gland installation.
• Replacement of cable glands sealing rings to fit the cable actual diameter if
required.
• Cable gland installation and tightening.
• Armour, shield and lead sheath grounding.
• Sealing fittings installation where required.
• Insulating tape wrap application
• Application of medium voltage cable termination kits on all MV electrical cables,
in accordance with Vendor’s instructions.
Medium voltage cable termination kits shall be executed by skilled staff.
24. Making or adjusting the incoming holes of the terminal box of the motors, panels,
power outlets and various Equipment in compliance with classified area restrictions to
connect the incoming threaded cable gland or conduit.
25. Replacing the screws and/or the fittings to obtain the correct cable tightening at the
incoming of all electrical equipment.
26. Cable core marking / identification:
MOD-A4DP-E is.4

• Identification of all cores of power and control cables with a non-adhesive label
near the terminal.
• Indication of all power conductor terminals by letters or phase colors by means
of plastic type wire markers (ring, tube, sleeve, etc.).

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 35 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

• Indicating the progressive number and other pertinent wiring information for all
other conductor terminals (control, signal, etc.) by means of plastic type wire
marker (ring, tube, sleeve, etc.).
Marking system, numbering and codification shall be in accordance with project
documents and CONTRACTOR requirements.
27. Sealing of terminals of cables to be jointed with suitable taping, immediately after cable
laying.
28. Preparation of cable leads to be jointed according to Vendor’s instruction.

29. Execution of cable joint, following Vendor's instructions, by skilled staff.

30. Supply and installation of marker plate (aboveground) in the exact position of each
joint. The plate shall show the cable marks according to the Electrical Cable List and
the laying depth of the joint.

B. METHOD OF MEASUREMENT
For codes B00AA, B00AB, B00AC, B00AD, B00AE, B00AF – Laying of cables - (m)
The length shall be calculated on the basis of the drawings issued for construction regardless
of the actual installed length.
For codes B00BA, B00BB, B00BC, B00BD, B00BE, B00BF – Installation of termination and
connections - (No.)
The quantity of terminations shall be calculated by the number of terminations and
connections shown in the drawings issued for construction.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 36 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

4.2 CODES B01 – Equipment Connection

The works in subject are relevant to Transformation Units and String Inverters cabling.

A. The Prices for above works include also the cost for:
In particular, for CODES B01AA01 – Connection of Cabins, B01AB01 – Connection of String
Inverters, the following costs are included:
1. All as reported in point 4.1
2. Unloading, storage and handling cables and accessories, provided by the
CONTRACTOR;
3. Connection of all applicable cables to Equipment, according to TECHNICAL
DOCUMENTATATION;

B. METHOD OF MEASUREMENT
For codes CODES B01AA01 – Connection of Cabins, B01AB01 – Connection of String
Inverters (No.)
The quantity of equipment connections shall be calculated by the number of connections
shown in the drawings issued for construction.

4.3 CODES B02 – Site Electrical Tests

The work in subject is relevant to all electrical control tests that SUBCONTRACTOR shall be
performed, according to TECHNICAL DOCUMENTATION.

A. The Prices for above works include also the cost for:
In particular, for CODES B02AA01 – Electrical Control Tests, the following costs are included:
1. Inspection and Testing activities of all the installed equipment and material as defined
in TECHNICAL DOCUMENTATIONS.
2. The supply of Test Equipment and Tools necessary to perform all the required test as
defined in TECHNICAL DOCUMENTATIONS, including certifications.
3. Skilled staff and certified for tests execution.
4. Final stamped technical report (including official certifications).

B. METHOD OF MEASUREMENT
For codes CODES B02AA01 – Electrical Control Tests (Lump Sum)
The unit price is applicable in a single solution for the whole project.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 37 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

5 MECHANICAL WORKS

5.1 CODES C00 – PV Trackers Installation

The works in subject are relevant to installation of tracker foundation piles installation, tracker
support structures and PV modules.

A. The Prices for above works include also the cost for:
In particular, for CODES C00AA01 - Installation of tracker foundation profiles, the following
costs are included:
1. Unloading, storage and handling of foundation profiles;
2. Topographies and staking of the foundation locations, according to design and technical
specifications;
3. Installation of the profiles driven directly into the ground, carried out with specialized
machinery (i.e. ramming machine);
4. Control of infixion depth and profile verticality, in accordance with the tolerances
foreseen in the design, including any corrective actions.
5. SUBCONTRACTOR shall be responsible for the damages caused during his work to the
steel structures paint protection and shall provide for promptly restoration.
6. Cold-galvanizing operations to restore surface protection where required.

For CODES C00AA02 - Tracker foundation profiles - Predrilling, the following costs are
included:
1. As for code C00AA01.
2. Predrilling carried out with specialized machinery, according to design.

For CODES C00AA03 - Tracker foundation profiles – Supply and placing the concrete in the
predrilling holes, the following costs are included:
1. As for code C00AA01.
2. Supply and placing the concrete in the predrilling holes, according to design.

For CODES C00AA04 - Installation of tracker support structures, the following costs are
included:
1. Unloading, storage and handling of support structures;
2. Supply, assembly and disassembly of provisional supports
3. Assembly of support structures and connection to foundation profiles, according to
tracker installation manual and TECHNICAL DOCUMENTATION;
4. Installation of tracker actuators and all accessories;
MOD-A4DP-E is.4

5. Control of installation, in accordance with the tolerances foreseen in the design and
agreed Quality Control Plan, including any corrective actions.
6. Tightening the high tension bolts with torque wrench or equivalent in order to reach
the required setting torque.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 38 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

7. Bolt tightening torque, according to TECHNICAL DOCUMENTATION;


8. Electrical continuity effectiveness shall be guaranteed during and after steel erection
works
9. Predisposition for grounding connection of the structures to the plant earthing grid.
10. SUBCONTRACTOR shall be responsible for the damages caused during his work to the
steel structures paint protection and shall provide for promptly restoration.
11. Cold-galvanizing operations to restore surface protection where required.

For CODES C00AB01 - Installation of PV Modules, the following costs are included:
1. Unloading, storage and handling of PV modules;
2. Supply, assembly and disassembly of provisional supports
3. Installation of PV modules, according to PV modules installation manual and technical
specifications;
4. Optical Reading and Recording of the serial number of each PV Module, according to
technical specification;
5. Control of installation, in accordance with the tolerances foreseen in the design and
agreed Quality Control Plan, including any corrective actions.
6. Tightening the high tension bolts with torque wrench or equivalent in order to reach
the required setting torque.
7. Bolt tightening torque, according to TECHNICAL DOCUMENTATION;
8. Electrical continuity effectiveness shall be guaranteed during and after steel erection
works
9. Predisposition for grounding connection of the structures to the plant earthing grid.
10. SUBCONTRACTOR shall be responsible for the damages caused during his work to the
steel structures paint protection and shall provide for promptly restoration.
11. Cold-galvanizing operations to restore surface protection where required.

For CODES C00AB02 - PV Modules cleaning, the following costs are included:
12. N.1 complete cleaning of all the PV modules before the PV power plant First
Electrification, as per TECHNICAL DOCUMENTATION.

A. METHOD OF MEASUREMENT
For codes C00AA01 - Installation of tracker foundation profiles (No.)
The quantity of installation of profiles shall be calculated by the number of profiles shown in
the drawings issued for construction.
MOD-A4DP-E is.4

For codes C00AA02 - Tracker foundation profiles - Predrilling (No.)


The quantity of predrilling to be carried out will be calculated from the number of predrilling
indicated in the documents issued for the construction.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 39 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

For CODES C00AA03 - Tracker foundation profiles – Supply and placing concrete in the
predrilling holes (m3)
The concrete volume is to be calculated on the basis of the dimensions indicated on drawings
issued for construction.

For codes C00AA04 - Installation of tracker support structures (No.)


The quantity of installation of support structures shall be calculated by the number of support
structures shown in the drawings issued for construction.

For codes C00AB01 - Installation of PV Modules (No.)


The quantity of installation of PV Modules shall be calculated by the number of PV Modules
shown in the drawings issued for construction.

For codes C00AB02 - PV Modules cleaning (Lump Sum)


The unit price is applicable in a single solution for the whole project.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 40 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

5.2 CODES C01 – Equipment Installation

The works in subject are relevant to installation of Transformer Unit and String Inverters.

A. The Prices for above works include also the cost for:
In particular, for CODES C01AA -Installation of Transformer Unit, the following costs are
included:
1. Installation in accordance with TECHNICAL DOCUMENTATIONS.
2. Supply, assembly and disassembly of provisional supports.
3. Checking of foundations, embedded steel materials, opening holes and the likes before
installation.
4. Checking the preservation of foundation bolts and restoring to their original conditions,
if required.
5. Checking of orientation before installation.
6. Positioning on foundation, leveling, fixing and alignment.
7. Final tightening of foundation bolts after concrete curing.
8. Installation of fittings and erection accessories.
9. Assembly of all those components that have been received disassembled
10. Restore of all the electrical connections among the assembled mechanical parts

11. Restore of all the grounding connection.

12. Cable entry sealing after cable pulling.

13. Cold-galvanizing operations to restore surface protection where required.

14. Handling, disposal and removal of waste.

In particular, for CODES C00AB01 - Installation of String Inverters foundation profiles, the
following costs are included:
1. Unloading, storage and handling of foundation profiles;
2. Topographies and staking of the foundation locations, according to design and technical
specifications;
3. Installation of the profiles driven directly into the ground, carried out with specialized
machinery (i.e. ramming machine);
4. Control of infixion depth and profile verticality, in accordance with the tolerances
foreseen in the design, including any corrective actions.
5. SUBCONTRACTOR shall be responsible for the damages caused during his work to the
steel structures paint protection and shall provide for promptly restoration.
MOD-A4DP-E is.4

6. Cold-galvanizing operations to restore surface protection where required.

For CODES C00AB02 - Installation of String Inverters foundation profiles - Predrilling, the
following costs are included:

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 41 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

3. As for code C00AB01.


4. Predrilling carried out with specialized machinery, according to design.

For CODES C00AB03 - Installation of String Inverters foundation profiles – Supply and
placing the concrete in the predrilling holes, the following costs are included:
3. As for code C00AB01.
4. Supply and placing the concrete in the predrilling holes, according to design.

For CODES C01AB04 -Installation of String Inverters, the following costs are included:
1. Withdrawal of all material from CONTRACTOR's warehouse and handling till to
installation site.
2. Checking of orientation before installation.
3. Assembly of all components that have been received disassembled.
4. Installation in accordance with TECHNICAL DOCUMENTATIONS.
5. Grounding connection to equipment.
6. Handling, disposal and removal of waste

In particular, for CODES C01AC -Installation of CCTV poles, the following costs are included:
1. Withdrawal of all material from CONTRACTOR's warehouse and handling till to
installation site.
2. Supply, assembly and disassembly of provisional supports.
3. Checking of foundations, embedded steel materials, opening holes and the likes before
installation.
4. Checking the preservation of foundation bolts and restoring to their original conditions,
if required.
5. Checking of orientation before installation.
6. Installation in accordance with TECHNICAL DOCUMENTATIONS.
7. Positioning on foundation, leveling, fixing and alignment.
8. Final tightening of foundation bolts after concrete curing.
9. Installation of fittings and erection accessories.
10. Assembly of all those components that have been received disassembled

11. Grounding connection

12. Cold-galvanizing operations to restore surface protection where required.

13. Handling, disposal and removal of waste..


MOD-A4DP-E is.4

B. METHOD OF MEASUREMENT
For code C01AA01 -Installation of Transformer Unit (No.)
The quantity of installation of equipment shall be calculated by the number of equipment

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 42 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

shown in the drawings issued for construction.

For codes C01AB01 - Installation of String Inverters foundation profiles (No.)


The quantity of installation of profiles shall be calculated by the number of profiles shown in
the drawings issued for construction.

For codes C01AB02 - Installation of String Inverters foundation profiles - Predrilling (No.)
The quantity of predrilling to be carried out will be calculated from the number of predrilling
indicated in the documents issued for the construction.

For CODES C01AB03 - Installation of String Inverters foundation profiles – Supply and
placing concrete in the predrilling holes (m3)
The concrete volume is to be calculated on the basis of the dimensions indicated on drawings
issued for construction.

For code CODES C01AB04 -Installation of String Inverters (No.)


The quantity of installation of equipment shall be calculated by the number of equipment
shown in the drawings issued for construction.

For code C01AC01 -Installation of CCTV poles (No.)


The quantity of installation of equipment shall be calculated by the number of equipment
shown in the drawings issued for construction.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 43 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

5.3 CODES C02 – Electrical overhead line installation

The works in subject are relevant to installation of Electrical Overhead Line Installation.

A. The Prices for above works include also the cost for:
In particular, for CODES C02AA - MV poles installation, the following costs are included:
1. Withdrawal of all material from CONTRACTOR's warehouse and handling till to
installation
2. Withdrawal of all material from CONTRACTOR's warehouse and handling till to
installation site.
3. Supply, assembly and disassembly of provisional supports.
4. Checking of foundations before installation.
5. Checking of orientation before installation.
6. Installation in accordance with TECHNICAL DOCUMENTATIONS.
7. Positioning, leveling, fixing and alignment.
8. Installation of fittings and erection accessories.
9. Assembly of all those components that have been received disassembled
10. Grounding connection

11. Handling, disposal and removal of waste.

In particular, for CODES C02AB - MV pole equipment installation, the following costs are
included:
1. Unloading, storage and handling of MV pole equipment;
2. Supply, assembly and disassembly of provisional supports
3. Installation of MV pole equipment, according to installation manual and technical
specifications;
4. Control of installation, in accordance with the tolerances foreseen in the design and
agreed Quality Control Plan, including any corrective actions.
5. Predisposition for grounding.
6. SUBCONTRACTOR shall be responsible for the damages caused during his work.

A. METHOD OF MEASUREMENT
For codes CODES C02AA - MV poles installation, C02AB - MV pole equipment installation
(No.)
The quantity of installation shall be calculated by the number of poles shown in the drawings
MOD-A4DP-E is.4

issued for construction.

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 44 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

6 COMMISSIONING AND START-UP

6.1 CODES D00 – PV Plant Commissioning and Start-Up activities

The works in subject are relevant to activities of Commissioning and Start-Up of photovoltaic
system.

A. The Prices for above works include also the cost for:
In particular, for CODES D00AA01 - PV Plant Commissioning and Start-Up activities the
following costs are included:
1. All equipment and measuring instruments necessary to carry out the required
activities;
2. Skilled and qualified personnel for carry out the required activities;
3. The fulfilment of all the Commissioning tests and checking as required by the
TECHNICAL DOCUMENTATION;
4. The fulfilment of Commissioning Performance test as required by the TECHNICAL
DOCUMENTATION;
5. All equipment and material necessary to guarantee temporary operation of photovoltaic
system during the execution of Performance Test as required by TECHNICAL
DOCUMENTATIONS.

B. METHOD OF MEASUREMENT
For codes D00AA01 - PV Plant Commissioning and Start-Up activities (Lump Sum)
The unit price is applicable in a single solution for the whole project.
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 45 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 46 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

LEGEND

Starting level of the Ground, as indicated in the Annexes and on the drawings Issued for
Construction (IFC), can be defined in the following ways:

PTS Prepared Top Soil


NGE Natural Ground Elevation
FGL Final Grade Level
HPP High Point Paving
BOE Bottom Of Excavation
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 47 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 1

EXCAVATION AND BACKFILLING FOR SINGLE FOUNDATION

LIMITED SECTION EXCAVATION - m3 - (A02AB)


The excavation volume "VLE" of each individual foundation is to be calculated as follow regardless the
actual volume of the excavation executed:

A=axb

VLE = A x h

LIMITED SECTION BACKFILLING - m3 - (A05AE)


The level of backfilling in absence of pavement shall be the starting level of excavation. In presence
of pavement the top of backfilling shall be the bottom of subbase of paving.

The volume of Limited section Backfilling (VLB) is to be calculated as follow, according to pertinent
codes, regardless the actual volume of the backfilling executed:

VLB = a x b x h – (c0 + VC)


MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 48 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

Example of Limited section excavation and backfilling for open ditches, concrete trench and duct bank

D
Excavation for figures A, B, C, and D, shall be calculated as follows:

a x h x Length

Backfilling

• for figures A and D consider only


• for figures B and C backfilling is = 0 (zero)
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 49 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 2
FOUNDATION REQUIRING SOIL IMPROVEMENT

LIMITED SECTION EXCAVATION m3 (A02AB)


The excavation volume "VLE" of each individual foundation is to be calculated as follow, regardless the
actual volume of the excavation executed:

A=axb
VLE = A x h

Where:
A: surface (a x b) area of the improvement as indicated on drawing issued for construction.
h: excavation depth between PTS/NGL and bottom of excavation elevation shown in the drawings issued
for construction.
hs: sub-base thickness as per design requirement, project specification or drawings issued for
construction.

LIMITED SECTION BACKFILLING m3 (A05AE)


The level of backfilling in absence of pavement shall be the starting level of excavation. In presence of of
pavement the top of backfilling shall be the bottom of subbase of paving.
The volume of Limited section Backfilling (VLB) is to be calculated as follow, according to pertinent codes,
regardless the actual volume of the backfilling executed:

VLB = a x b x h – (a x b x hs + VC+c0)
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 50 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 3
EXCAVATION OF UNDERGROUND PIPING SYSTEM (m3)

Q1, Q1a, Q1b = Elevation of ground (NGE/PTS)


BOE1, BOE2, BOE3 = Elevation of bottom excavation, according to the drawings issued for construction

DN = Nominal pipe Diameter


h, h1, h2 = Excavation depth
F = Distance between pipes, according to the construction drawings
K = Distance between pipes and the sides of excavation.

DN ≤ 35 cm K = 35 cm
DN ≥ 35 cm to ≤ 60 cm K = 40 cm
DN ≥ 60 cm to ≤ 150 cm K = 45 cm
DN ≥ 150 cm K = 60 cm
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 51 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 4

FOUNDATION CONCRETE (A08AB)


EXAMPLE OF TYPOLOGY OF CONCRETE
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 52 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

SCHEMATIC EXAMPLE OF OPEN DITCH,


CONCRETE TRENCH AND BASIN
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 53 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 5
CONCRETE REINFORCEMENT REBARS

Weight of 1m of rebar in kg for diameter from 5 to 40mm and section area in cm2

Number of rebar's and relevant section area in cm2


Diameter of Ø

Weight kg of
1m

1 2 3 4 5 6 7 8 9 10 11 12 13 14
mm

5 0.154 0.20 0.39 0.59 0.78 0.98 1.18 1.37 1.57 1.76 1.96 2.16 2.35 2.55 2.74
6 0.222 0.28 0.57 0.85 1.13 1.14 1.70 1.98 2.26 2.55 2.83 3.11 3.40 3.68 3.96
7 0.302 0.38 0.77 1.16 1.54 1.93 2.31 2.70 3.08 3.47 3.85 4.24 4.62 5.01 5.39
8 0.395 0.50 1.01 1.51 2.01 2.52 3.02 3.52 4.02 4.53 5.03 5.53 6.04 6.54 7.04
9 0.499 0.64 1.27 1.91 2.54 3.18 3.82 4.45 5.09 5.72 6.36 7.00 7.63 8.27 8.90
10 0.617 0.79 1.57 2.36 3.14 3.93 4.71 5.50 6.28 7.06 7.85 8.64 9.42 10.2 11.9
11 0.746 0.95 1.90 2.85 3.80 4.75 5.70 6.65 7.60 8.55 9.50 10.4 11.4 12.3 13.3
12 0.888 1.13 2.26 3.39 4.52 5.65 6.78 7.91 9.04 10.1 11.3 12.4 13.5 14.6 15.8
13 1.042 1.33 2.66 3.99 5.32 6.65 7.98 9.31 10.6 11.9 13.3 14.6 15.9 17.2 18.6
14 1.208 1.54 3.08 4.62 6.16 7.70 9.24 10.7 12.3 13.8 15.4 16.9 18.4 20.0 21.5
15 1.387 1.77 3.54 5.31 7.08 8.85 10.6 12.3 14.1 15.9 17.7 19.4 21.2 23.0 24.7
16 1.578 2.01 4.02 6.03 8.04 10.0 12.0 14.0 16.0 18.0 20.1 22.1 24.2 26.1 28.1
17 1.782 2.27 4.54 6.81 9.08 11.35 13.6 15.8 18.1 20.4 22.7 24.9 27.2 29.5 31.7
18 1.998 2.54 5.08 7.62 10.1 12.7 15.2 17.7 20.3 22.8 25.4 27.9 30.4 33.0 35.5
19 2.226 2.84 5.68 8.52 11.3 14.2 17.0 19.8 22.7 25.5 28.4 31.2 34.0 36.9 39.7
20 2.466 3.14 6.28 9.42 12.5 15.7 18.8 21.9 25.1 28.2 31.4 34.5 37.6 40.8 43.9
21 2.719 3.46 6.92 10.3 13.8 17.3 20.7 24.2 27.6 31.1 34.6 38.0 41.5 44.9 48.4
22 2.984 3.80 7.60 11.4 15.2 19.0 22.8 26.6 30.4 34.2 38.0 41.8 45.6 49.4 53.2
23 3.261 4.15 8.30 12.4 16.6 20.7 24.9 29.9 33.2 37.3 44.5 45.6 49.8 53.9 58.1
24 3.551 4.52 9.04 13.5 18.0 22.6 27.1 31.6 36.1 40.6 45.2 49.7 54.2 58.7 63.2
25 3.853 4.91 9.82 14.7 19.6 24.5 29.4 34.3 39.2 44.1 49.1 54.0 58.9 63.8 68.7
26 4.168 5.31 10.6 15.9 21.2 26.5 31.8 37.1 42.4 47.7 53.1 58.4 63.7 69.0 74.3
27 4.495 5.73 11.4 17.1 22.9 28.6 34.3 40.1 45.8 51.5 57.3 63.0 68.7 74.4 80.2
28 4.834 6.16 12.3 18.4 24.6 30.8 36.9 43.1 49.2 55.4 61.6 67.7 73.9 80.0 86.2
29 5.185 6.61 13.2 19.8 26.4 33.0 39.6 46.2 52.8 59.4 66.1 72.7 79.3 85.9 92.5
30 5.549 7.07 14.1 21.2 28.2 35.3 42.4 49.4 56.5 63.6 70.7 77.7 84.8 91.9 98.9
32 6.113 8.04 16.0 24.1 32.1 40.2 48.2 56.2 64.3 72.3 80.4 89.0 97.6 105 115
34 7.127 9.08 18.1 27.2 36.3 45.4 54.4 63.5 72.6 81.7 90.8 99.8 108 118 127
36 7.990 10.1 20.3 30.5 40.7 50.9 61.0 71.2 81.4 91.5 101 111 121 131 141
38 8.903 11.3 22.6 34.0 45.3 56.4 68.0 79.3 90.7 102 113 124 135 146 158
40 9.865 12.5 25.1 37.7 50.2 62.8 75.4 87.9 100 113 125 137 150 162 175
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 54 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

CONCRETE REINFORCEMENT WIRE WELDED MESH

EXAMPLE OF BAR BENDING SCHEDULE - B.B.S.

These tables are usually included in reinforced concrete drawings issued for construction
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 55 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 56 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 6
FENCE

A
PTS

S=AxB
MOD-A4DP-E is.4

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent
NR Identification Code
SPECIAL PREAMBLES AND MEASUREMENT
METHODS FOR CONSTRUCTION WORKS
PHOTOVOLTAIC PLANT N046-EM-WR-A00001

P.M.G.D. CHILE CHILE ENGINEERING-Civil & Structural Sheet 57 / 57 Issue 05


Company Identification Code
COMPANY LOGO COMPANY NAME (/ PROJECT)
XXXXXXXXXXXX

ANNEX 7
UNDERGROUND PIPING

Firma electrónica avanzada


ARTURO ESTEBAN
GALVEZ MARIN
MOD-A4DP-E is.4

2023.04.24 08:16:12 -0400

This document is Tecnimont’s property, and cannot be used by others for any purpose, without prior written consent