Krishna Buildestates Pvt Ltd.

Sub:- Balance Work At Godrej Nurture Site With Amendment


Date:30.03.2024
Amendment
S. No. Description Unit A1a A2a C1a NTA Total Qty. Rate Amount Amendment Rate Remarks
Amount

1 Excavation 7.8 7.8 180 1404

2 Back Filling 2000 2000 110 220000

3 PCC Work Cum. 75 75 5200 390000

4 RCC Cum. 89.4 502 591.4 12850 7599490 500 295700

5 RCC Facia & Band Cum. 2 11.5 49.63 3 66.13 12850 849770.5 500 33065

6 Fly Ash Brick Work Cum. 41.04 184.00 225.04 5800 1305232

7 AAC Block Work 9" Cum. 25.0 46.0 231.0 302.0 5100 1540200 500 151000

8 AAC Block Work 4.5" Sqm. 402 20 422 775 327050 500 21100

9 VACCUM DEWATERING Cum. 6.00 23.00 75.00 376.8 480.8 6800 3269440

10 VACCUM DEWATERING Sqm. 60.00 230.00 750.00 1884.00 2924.00 180 526320

11 IPS floor Sqm. 100.00 100.00 100.00 150.00 450.00 564 253800

RMP WALL PLASTER -


12 INTERNAL PLASTER Sqm. 4612.00 4612.00 6611.00 1645.20 17480.20 460 8040892

13 Gypsum Plaster Work Sqm. 1037 9922 10959.00 345 3780855 45 49315.5

14 CEILING PLASTER Sqm. 1278 240 1518.00 185 280830

20 MM CEMENT PLASTER IN TWO


15 LAYER -EXTERNAL PLASTER (RMP) Sqm. 9090.72 9940.72 14106 33137.44 890 29492325.605

16 WHITE WASHING Sqm. 585 585 845 3900 5915.00 50 295750


17 Balcony Railing KG 2730 2730.00 95 259350

17 STRUCTURAL STEEL KG 1360 1530 1680 300 4870.00 95 462650

18 Slab Conduiting Work Rmt 800 800.00 50 40000

18 Wall Conduiting Work Rmt 2840 2840.00 55 156200

19 3 x 3 inch 408 408.00 116 47328

20 4x 3 inch 320 320.00 121 38720

21 5x 3 inch 88 88.00 141 12408

22 8x 3 inch 208 208.00 225 46800


Total Balance Work At Godrej Nurture 59236815.105 550180.5 59786995.605
Site