Professional Documents
Culture Documents
! Procedure 3lpe Msl Rev.00
! Procedure 3lpe Msl Rev.00
CONSULTANT : M/s Engineers India Pvt. Limited (EIL) EIL Job No.: B416 INSPECTION CATEGORY: B
OD WT QUANTITY
PO SR. NO.
(MM) (MM) (METERS)
1 219.1 7.92 2163
TABLE OF CONTENTS
1.0 INTRODUCTION
2.0 DEFINITIONS
3.0 RESPONSIBILITIES
3.1 Production Manager
3.2 QC Manager
3.3 QC Inspector
4.0 QUALIFICATION OF THE APPLICATION PROCEDURE
5.0 DESCRIPTION OF THE COATING PROCESS
5.1 General
5.2 Incoming Rack
5.3 External Pipe Preheating Station before First Blasting
5.4 Abrasive Blast Cleaning
5.5 Heating Before Epoxy Coating application
5.6 FBE Application Station
5.7 Adhesive Application Station
5.8 Polyethylene Coating Station
5.9 Water Quenching Station
5.10 Inspection Rack after the Water Quenching Station
5.10 Cutback station
5.11 Holiday Inspection Station
5.12 Final activity, Out Going Rack
6.0 3LPE Coating Repair
7.0 PIPE COATING REMOVAL (STRIPPING)
1.0 INTRODUCTION
This procedure describes the process of application of the 3 Layer Polyethylene coating for
line pipes according to the requirement of the Project Specifications provided by the
Customer and as per approved QIP. The bare pipes shall be moved to the Anti-Corrosion
Coating plant where they shall be processed through the cleaning, coating and inspection
working stations. The coating process is performed under covered shed. Externally coated
pipes shall then lifted and transported to the temporary storage area before dispatch to site.
MSL/QIP/CPCL-CBR/PE/23-18, 3Layer Polyethylene Coating of steel Pipes – Quality
Inspection Plan, for all inspection and testing activities to be performed during the coating of steel
pipes with the 3 Layer Polyethylene Coating.
2.0 DEFINITIONS
CUSTOMER/CLIENT : M/s CHENNAI PETROLEUM CORPORATION LIMITED (CPCL)
CONTRACTOR : Maharashtra Seamless Limited
MANUFACTURER : Manufacturer or Supplier of the coating materials for Inspection and testing
Equipment.
3.0 RESPONSIBILITIES
3.1 Production Manager
The Production Manager is responsible for all of the operations performed in the
Coating Plant related to the application of the 3Layer Polyethylene.
3.2 Quality Manager
The QC Manager shall be responsible for all of the quality control inspection and testing during
Surface preparation, coating application and on coated pipe.
3.3 QC Inspector
The QC Inspector shall be responsible for verification that the application of the 3 Layer
Polyethylene coating has been performed in accordance with the approved project documents
and quality of coating meets project approved QIP/specification.
The Procedure Qualification Test shall be performed on 15 pipes and the inspection will be
Conducted as per approved QIP. During PQT coating application parameters shall be established
and recorded to confirm final characteristics of the 3 Layer Polyethylene coating system meet the
agreed Project requirements.
The bare pipes shall bring to the incoming rack using the Fork lift / Hydra from yard.
At this station the pipes shall be visually inspected for presence of surface defects, oil/grease or
similar Contaminant and verify the bare pipe no. with bare packing list.
In case the oil or grease contamination is found, same shall be removed using a suitable solvent or
Chemical (e.g. Xylene, Thinner, Soap water etc.) by swabbing with cloth or similar material.
In case any surface defect is detected on external or internal pipe surface, defected pipe shall be
Segregated and inspected by bare pipe mill team to take further decision.
Any pipe not meeting quality inspection criteria, same shall be segregated and rectify before put in
Coating process.
5.3 External Pipe Preheating Station Before Blasting
At this station external surface of pipes shall be heated by diesel fire oven until the external pipe
Surface temperature is within range specified in approved QIP/Project specification and pipe surface
Temperature at least 3°C above atmosphere dew point temperature. The steel surface temperature
shall be verified using a digital contact thermometer. Following atmospheric condition shall be checked
by using thermo-hygrometer and recorded before blast cleaning:
1. Ambient temperature
2. Relative humidity.
3. Atmospheric Dew point temperature
The internal surface of the pipes shall be closed on both sides of the pipe with the end plugs, to prevent
the ingress of the abrasive into the internal surface of the pipe. Remove end plug at inspection rack
after blast cleaning.
The external pipe surface shall be blast clean using two dry abrasive blast cleaning units attached with
dust collector to achieve surface cleanliness and profile as per approved QIP requirement. For blasting
purpose metallic shot / grit shall be used.
Blasted pipe surface shall be inspected as per QIP requirement for cleanliness, profile, salt level, dust
level and elapsed time after blast cleaning.
Doc No.: MSL/PROC/CPCL-CBR/PE/23-18 4|Page
Rev 00, DATE: 14.03.2023
D.P.JINDAL GROUP OF INDUSTRIES
MAHARASHTRA SEAMLESS LIMITED,
PIPE NAGAR, COATING PLANT
a. Cleanliness shall be checked confirming to Sa2½ as per pictorial representation of ISO 8501-1,
b. Surface profile is not dished and rounded when viewed with 30X magnification.
c. Surface roughness profile shall be checked using Digital Roughness Gauge SJ210 or equivalent.
d. Dust level check by using dust level assessment transparent comply to ISO 8502-3 and peeling-off
to assess the degree of Dust.
e. Salt level checking by salt meter (SCM400/130 or Equivalent) as per approved QIP requirements.
If Salt level exceeding the acceptable limits as per approved QIP then pipes shall be either re-
blasted or washed by De - ionized Water.
All pipes shall be visually examined for presence of any shot/grit/loose material left inside the pipe
during blast cleaning. Any foreign material or shots/grit present in the pipe shall be completely removed
by high-pressure air equipped with suction arrangement in the dust collector on the other end of pipe.
After blast cleaning, surface of all pipes shall be checked for defects such as slivers, laminations, welds
spatters, gouges, or any other defects considered injurious to the coating integrity shall be segregate
and inspected by bare pipe mill team to take further decision. Before coating, the pipe surface shall be
cleaned from all dust and foreign matter using clean dry compressed air. The compressed air shall be
free of any trace of oil.
Any pipe not meeting quality requirement, same shall be mark NTC (not to coat), and remove from
Coating line for rectification/re-blast cleaning.
3LPE coated pipes shall be cooled down to approximately ≤ 80ºC using water, before kick out from
Coating line to thickness inspection rack. The quenching time must be established and recorded during
PQT to ensure FBE layer is enough cured to achieve DSC result (Delta Tg / % Cure) specified in
Approved QIP and maintain during production.
The 3LPE coated pipe temperature shall be continuously monitored by non-contact type pyrometer and
Verified by the portable IR thermometer / contact type digital thermometers.
From this station the pipe shall be conveyed to the coating inspection rack.
At this station following final activity will be conducted and ensure 3LPE coated pipe meeting quality
Requirement:
1. Pipe bevel grinding by flap disk to remove any coating residue at both pipe ends.
2. Cutback inspection, ensure QIP requirement.
3. Check Residual magnetism as per approved QIP requirement.
Marking for pipe OD will be conducted as per approved QIP.
Any 3LPE coating damage observed, same shall be repaired as per approved repair procedure.
Gel time shall be determined by placing coating material in a hot plate stabilized at temperature of
205°C ± 3°C or as per manufacturer’s recommendation. Use a spatula to coat out a Uniform thickness.
Start the timing device as soon as the coating material is applied to the hot plate Surface. Stir/Scribe the
coating with a spatula and stop the watch when the coating becomes as Un-steerable /comes over epoxy
layer and no longer contact with metal plate. The elapsed time is the Gel time. Test performs three times
and takes the average value for result.
Acceptance criteria depending on the FBE powder manufacture recommendation.
2) Thermal analysis (Virgin Epoxy Powder):-
Test equipment: DSC equipment connected to a data analyzer and printer, laboratory balance with
scales accurate to the nearest 0.1 mg, DSC Pans & laboratory tools.
Test procedure:
Heating cycle as per standard condition and raw material manufacturer recommendation
DSC pans shall have a volume such to contain the sample to be tested. Weight 10 mg ± 3 mg of the
Epoxy powder coating. Record the weight of the sample with an accuracy of 0.1 mg. After having
Placed the sample on the bottom of the pan, with a suitable and perfectly clean cylindrical rod, push
Gently the sample close to the bottom of the pan in order to increase as much as possible the contact
Surface of the sample with the pan. After this operation, Pierce the top of the pan cover with a
Clean needle. Close the pan with its pan cover by the specific device. An inert gas (N2) shall be used
To purge the cell. The scan program shall be prepared depending on the instrument used DSC
Machine with fast cooling device.
Heating cycle as per standard condition and raw material manufacturer recommendation.
Acceptance criteria depending on the FBE powder manufacture recommendation.
3) Moisture Content:-
Procedure A (Mass loss methods)
The test shall be performed in the laboratory.
Test equipments: Hot Air Oven, Balance (Accurate to 0.001gm), Desiccators.
Sample container.
Test procedure:
Weigh the sample container. Transfer approx. 10 g of epoxy powder into the sample container. Weigh
the sample container and epoxy powder. Place the sample container with the epoxy powder into the
oven for a minimum of 2 hours at 105 ± 3°C. Remove the container from the oven and place it in the
desiccators to cool. Weigh the sample container when it has cooled to 20 ± 3°C and then return it to the
Desiccators repeat at intervals of 1 Hrs ± 10 min until two consecutive mass determinations.
Where,
M = Percentage of Moisture
B = Initial mass of sample container and epoxy powder, g
C = Final mass of sample container and epoxy powder, g
A = Mass of sample container, g
Procedure B (automatic procedure)
The moisture content of the epoxy powder shall be determined using a machine that automatically
Determines moisture content by mass loss.
Acceptance criteria depending on the FBE powder manufacture recommendation.
4) Cure time
Test equipment: DSC equipment connected to a data analyzer and printer, laboratory balance with
scales accurate to the nearest 0.1 mg, DSC Pans & laboratory tools.
Test procedure:
Heating cycle as per standard condition and raw material manufacturer recommendation
DSC pans shall have a volume such to contain the sample to be tested. Weight 10 mg ± 3 mg of the
Cured FBE sample which are prepared by Hot plate temp. @ 232±3°C, after 120 seconds or as per
Raw Material manufacturer recommendation. After having placed the sample on the bottom of the
Pan, with a suitable and perfectly clean cylindrical rod, push gently the sample close to the bottom of
The Pan in order to increase as much as possible the contact Surface of the sample with the pan.
After This Operation, Pierce the top of the pan cover with a clean needle. Close the pan with its pan
Cover by the specific device. The scan program shall be prepared depending on the instrument used
DSC Machine with fast cooling device. An inert gas (N2) shall be used to purge the cell.
Heating cycle as per standard condition and raw material manufacturer recommendation.
Test Procedure:
For the adhesive and topcoat HDPE material, the melt index shall be determined at a temperature of
190°C±3°C with a load of 2.16 kgs, Preheat the apparatus to test temperature for at least 15 minutes.
Remove the piston and place it on the insulated surface. Charge the cylinder within 1 minute with a
weighed portion of the sample, 4 to 6 grams. Place the weighed piston into position. Start timing for a
6 to 8 minute pre-heat period. As the lower scribe mark reaches the top of the cylinder (or index), reset
the stopwatch and cut off the extruded material simultaneously. Cut off the extruded material 3 times
after each interval of 20 seconds (Adhesive) & 40 seconds (HDPE). Discharge the remainder of the
specimen and push the die out through the top of the cylinder. Swab out the cylinder with cloth
patches while hot, like a gun barrel. It is not necessary to clean the die so long when similar materials
are being tested. When the Extruded material has cooled to the room temperature weigh it to the
nearest mg and record the melt Flow rate in g/10minutes.
Acceptance criteria as per Approved QIP & material manufacture recommendation
2) Vicat Softening Point - HDPE & Adhesive
Test equipment: Vicat softening assembly.
Test Procedure:
The test shall be performed in the laboratory. This method consists of temperature at which a flat
Ended needle penetrates 1mm under a specified load (10N) and uniform rise rate of temperature.
For testing purpose approximately 10mm X 10mm sample shall be cut from sheet prepared from
Granules of materials (HDPE/ADHESIVE). Sample shall be place under needle and apply a 10N
Load and set indent meter on “zero”. Start the heater @ 50±5°C/hrs. Record the temperature of the
Bath when the needle has penetrated 1± 0.01 mm into the test specimen.
Test Procedure:
Heating cycle as per standard condition and raw material manufacturer recommendation.
DSC pans shall have a volume such to contain the sample to be tested. Weight 5 mg to10 mg of the
HDPE sample. After weighing the sample with DSC pan and pin, locked the DSC pan with press
assembly. After then put sample in DSC machine and start it. When the temperature of sample reached
at 220°C, then An inert gas (N2) shall be used to purge the cell after then Oxygen (O2) will be start
automatically. After completion of test machine show the result on Graph for print.
Acceptance criteria as per Approved QIP & material manufacture recommendation.
15 pipes to be coated, out of these 1 partly coated with epoxy and partly with both epoxy & adhesive
Layer + 5 pipes 3LPE coated shall be selected for testing.
Testing
One partially coated and 5 No’s 3LPE coated test pipes shall be selected out of 15 coated pipes by
Owner Representative / TPI for coating procedure approval tests and shall be subjected to procedure
Qualification testing as described here in after.
Inscribe a V-cut with two 20 mm lines intersecting at approximately 5 mm from their ends at 30° to 45°.
Insert the blade of the knife at the point of the V-cut, 45° to the surface, then with an upward flicking action
Attempt To dislodge the coating within the V. If little or no coating is removed, repeat this action within the
V at Least four Times to confirm the integrity of the coating. Examine the appearance of the disbonded
Surface and compare the rating / Test Acceptance criteria as per Approved QIP.
3LPE coated pipe, prepared in lab hydraulic press. Sample shall be subjected for Tensile strength test as
per ISO 21809-1 & ISO 527.
3.7) Air Entrapment Test
Equipments: Utility knife & 30 X magnification (handheld).
Procedure:
Strips from the bond strength tests may be used to help determine the Air entrapment of the finished
Coating. The strips shall be viewed from the side and the interface of the coating. The examination
shall be down with the help 30X-magnification hand held microscope. The polyethylene and Adhesive
layer shall have no more than 10 % of the observed area & thickness taken up with air entrapment as
per Approved QIP.
Procedure:
Test shall be carried out on 3LPE Coated pipe samples. The Cathodic disbondment test shall be carried
out for 24 hrs(Testing during PQT & Regular Production) & 28 days in accordance with the ISO 21809-1
Standard. Prepare the 3LPE coated pipe Sample of size approximately 100 mm × 100 mm. after cutting
the sample, the sample by using transparent vessel assemble with sealant and make electrolyte solution of
3% NaCl. After drying the sealant put the sample in sand bath and maintaining test temperature with filling
Electrolyte solution and connected electrodes to Cathodic disbondment tester apparatus and start the test.
Monitoring the parameter of test at least once in a day.
During test following parameter shall be maintained:-
A) Testing during PQT Only – Once whole project)
Test temperature
Test Potential (sample Temp.) Test duration Electrolyte solution
- 1.5 (Min.) 23°C ± 3°C 28 Days 3% NaCl
- 1.5 (Min.) 80°C ± 3°C 28 Days 3% NaCl
B) Testing during PQT & Regular Production - Once per day)
- 3.5 (Min.) 65°C± 3°C 24 Hours 3% NaCl
Acceptance Criteria as per Approved QIP.