A ECONOMIZER THERMAX PUNCH LIST AS SHARED TO BE CLEARED TO GET CLEARANCE TO START PLANT SAHU JI + THERMAX TIME TILL 2 P.M AIR LEAK TEST NIL TEAM AFTER 2 P.M, 1 HOUR JOB FEED WATER INLET & OUTLET RTD - WORK UNDER PROGRESS SAMAL JI BEFORE 2 .PM BOX UP OF ECONOMIZER - AFTER COMPLETE CIRCUIT HYDRO TEST IS COMPLETED MITHILESH JI 2 HOURS INSULATION IN PARALLEL - NO LINK WITH PLANT STARTUP TECHNO FABRICATION NO OBSTACLE FOR LIGHTUP B BOILER SOOT BLOWING NO.1 - INSTALLATION VIVEK JI (BOILER OPERATOR) NO OBSTACLE FOR LIGHTUP MUD DRUM MANHOLE - 3 NO'S BOXUP DJ CRAFTSMAN, SUPERVISION BY KANARATH (BOILER DCS) BEFORE 2 .PM FURNACE MANHOLE - 1 NO'S BOXUP KANARATH (BOILER DCS) BEFORE 2 .PM APH MANHOLE - 2 NO'S BOXUP VIVEK JI (BOILER OPERATOR) BEFORE 2 .PM WINDBOX & BURNER MANHOLE - 2 NO'S BOXUP VIVEK JI (BOILER OPERATOR) BEFORE 2 .PM BFG 911 VALVE - INSTALLATION (SUBJECT TO RECEIPT IN PLANT BY 2 P.M) DJ CRAFTSMAN, SUPERVISION BY PRAVEEN JI 3 HOURS AFTER RECEIPT. DEARATOR NOZZLE FIXING (SUBJECT TO RECEIPT IN PLANT BY 2 P.M) DILIP JI (FITTER) 2 HOURS AFTER RECEIPT. MAIN OIL GUN NOZZLE CLEANING CHANDRAMOHAN (FITTER) 1 HOUR JOB AFTER 2 P.M BY CASUAL (2) - SUPERVISION BY GUPTA JI TUBE CLEANING - BANK ZONE AFTER 3 P.M. / 3 HOURS JOB WORK. / BY 6 P.M FINAL INSPECTION ANIL JI + SAHU JI REFRACTORY INSTALLATION - ALL SIDES DJ CRAFTSMAN. SUPERVISION BY GUPTA JI NO OBSTACLE FOR LIGHTUP CASING PLATE INSTALLATION - BACK SIDE DJ CRAFTSMAN. SUPERVISION BY GUPTA JI NO OBSTACLE FOR LIGHTUP BY CASUAL (2) - SUPERVISION BY GUPTA JI MIST ELIMINATOR - SHREEWIRE - CLEANING 3-4 HOURS JOB WORK. BEFORE 3 P.M FINAL INSPECTION ANIL JI + SAHU JI AIR LEAK TEST NIL TEAM AFTER 2 P.M, 1 HOUR JOB INSULATION CLADDING - NO LINK WITH PLANT STARTUP TECHNO FABRICATION NO OBSTACLE FOR LIGHTUP C TURBINE GEAR BOX - BOXUP HINDUSTHAN ENGG BY 2 P.M LOW SPEED COUPLING ALIGNMENT HINDUSTHAN ENGG BY 3 P.M COUPLING FITTUP HINDUSTHAN ENGG BY 10 P.M FLANGE CONNECTION TO ESV HINDUSTHAN ENGG BY 2 P.M OIL COOLER BOXUP NIL TEAM BY 2 P.M FILTER REPLACEMENT HINDUSTHAN ENGG 1 HOUR AFTER BARRING GEAR TRIP OIL CIRCUIT TO BE TESTED HINDUSTHAN ENGG + TRIVENI ENGG BY 7 P.M STILMULATION TEST - TURBINE HINDUSTHAN ENGG + TRIVENI ENGG BY 7 P.M D ALTERNATOR BEARING CLEARANCE TO BE CHECKED HINDUSTHAN ENGG DONE COOLER HYDRO TEST HINDUSTHAN ENGG BY 2 P.M COMPLETE TESTING PIONEER ELECTRICALS BY 2 - 3 P.M ALIGNMENT OF ROTOR HINDUSTHAN ENGG 3 P.M - 6 P.M STATOR + ROTOR + EXCITOR - AIR GAP TO BE CHECKED HINDUSTHAN ENGG BY 7 P.M COMPLETE BALANCE WORK HINDUSTHAN ENGG BY 10 P.M E CONDENSOR CLOSING OF DOOR - ROAD SIDE SIDHARTH (DM PLANT INCHARGE) BY 1 P.M LEAK TEST OF CONDENSOR DOOR SIDHARTH (DM PLANT INCHARGE) BY 3 P.M F OVERALL / MISC HYDRO TEST - COMPLETE CIRCUIT NIL TEAM AFTER LEAK TEST OF ECONOMIZER, 2 HOURS ALL EQUIPMENT TRIAL RUN NIL TEAM BEFORE 5 P.M STILMULATION TEST - BOILER UL SYSTEM & CONTROLS AFTER HYDRO TESTING BOILER LIGHT UP NIL TEAM BY 7 P.M