You are on page 1of 1

CPP SHUTDOWN FINAL LIST

Sl No Area Job List Person Assigned Time


A ECONOMIZER THERMAX PUNCH LIST AS SHARED TO BE CLEARED TO GET CLEARANCE TO START PLANT SAHU JI + THERMAX TIME TILL 2 P.M
AIR LEAK TEST NIL TEAM AFTER 2 P.M, 1 HOUR JOB
FEED WATER INLET & OUTLET RTD - WORK UNDER PROGRESS SAMAL JI BEFORE 2 .PM
BOX UP OF ECONOMIZER - AFTER COMPLETE CIRCUIT HYDRO TEST IS COMPLETED MITHILESH JI 2 HOURS
INSULATION IN PARALLEL - NO LINK WITH PLANT STARTUP TECHNO FABRICATION NO OBSTACLE FOR LIGHTUP
B BOILER SOOT BLOWING NO.1 - INSTALLATION VIVEK JI (BOILER OPERATOR) NO OBSTACLE FOR LIGHTUP
MUD DRUM MANHOLE - 3 NO'S BOXUP DJ CRAFTSMAN, SUPERVISION BY KANARATH (BOILER DCS) BEFORE 2 .PM
FURNACE MANHOLE - 1 NO'S BOXUP KANARATH (BOILER DCS) BEFORE 2 .PM
APH MANHOLE - 2 NO'S BOXUP VIVEK JI (BOILER OPERATOR) BEFORE 2 .PM
WINDBOX & BURNER MANHOLE - 2 NO'S BOXUP VIVEK JI (BOILER OPERATOR) BEFORE 2 .PM
BFG 911 VALVE - INSTALLATION (SUBJECT TO RECEIPT IN PLANT BY 2 P.M) DJ CRAFTSMAN, SUPERVISION BY PRAVEEN JI 3 HOURS AFTER RECEIPT.
DEARATOR NOZZLE FIXING (SUBJECT TO RECEIPT IN PLANT BY 2 P.M) DILIP JI (FITTER) 2 HOURS AFTER RECEIPT.
MAIN OIL GUN NOZZLE CLEANING CHANDRAMOHAN (FITTER) 1 HOUR JOB AFTER 2 P.M
BY CASUAL (2) - SUPERVISION BY GUPTA JI
TUBE CLEANING - BANK ZONE AFTER 3 P.M. / 3 HOURS JOB WORK. / BY 6 P.M
FINAL INSPECTION ANIL JI + SAHU JI
REFRACTORY INSTALLATION - ALL SIDES DJ CRAFTSMAN. SUPERVISION BY GUPTA JI NO OBSTACLE FOR LIGHTUP
CASING PLATE INSTALLATION - BACK SIDE DJ CRAFTSMAN. SUPERVISION BY GUPTA JI NO OBSTACLE FOR LIGHTUP
BY CASUAL (2) - SUPERVISION BY GUPTA JI
MIST ELIMINATOR - SHREEWIRE - CLEANING 3-4 HOURS JOB WORK. BEFORE 3 P.M
FINAL INSPECTION ANIL JI + SAHU JI
AIR LEAK TEST NIL TEAM AFTER 2 P.M, 1 HOUR JOB
INSULATION CLADDING - NO LINK WITH PLANT STARTUP TECHNO FABRICATION NO OBSTACLE FOR LIGHTUP
C TURBINE GEAR BOX - BOXUP HINDUSTHAN ENGG BY 2 P.M
LOW SPEED COUPLING ALIGNMENT HINDUSTHAN ENGG BY 3 P.M
COUPLING FITTUP HINDUSTHAN ENGG BY 10 P.M
FLANGE CONNECTION TO ESV HINDUSTHAN ENGG BY 2 P.M
OIL COOLER BOXUP NIL TEAM BY 2 P.M
FILTER REPLACEMENT HINDUSTHAN ENGG 1 HOUR AFTER BARRING GEAR
TRIP OIL CIRCUIT TO BE TESTED HINDUSTHAN ENGG + TRIVENI ENGG BY 7 P.M
STILMULATION TEST - TURBINE HINDUSTHAN ENGG + TRIVENI ENGG BY 7 P.M
D ALTERNATOR BEARING CLEARANCE TO BE CHECKED HINDUSTHAN ENGG DONE
COOLER HYDRO TEST HINDUSTHAN ENGG BY 2 P.M
COMPLETE TESTING PIONEER ELECTRICALS BY 2 - 3 P.M
ALIGNMENT OF ROTOR HINDUSTHAN ENGG 3 P.M - 6 P.M
STATOR + ROTOR + EXCITOR - AIR GAP TO BE CHECKED HINDUSTHAN ENGG BY 7 P.M
COMPLETE BALANCE WORK HINDUSTHAN ENGG BY 10 P.M
E CONDENSOR CLOSING OF DOOR - ROAD SIDE SIDHARTH (DM PLANT INCHARGE) BY 1 P.M
LEAK TEST OF CONDENSOR DOOR SIDHARTH (DM PLANT INCHARGE) BY 3 P.M
F OVERALL / MISC HYDRO TEST - COMPLETE CIRCUIT NIL TEAM AFTER LEAK TEST OF ECONOMIZER, 2 HOURS
ALL EQUIPMENT TRIAL RUN NIL TEAM BEFORE 5 P.M
STILMULATION TEST - BOILER UL SYSTEM & CONTROLS AFTER HYDRO TESTING
BOILER LIGHT UP NIL TEAM BY 7 P.M

You might also like