You are on page 1of 1

MAIN OFFICE: Block 2, Lot 20, Alijis road, Alijis National Highway, Bacolod City 6100

Project: PASUDECO TOWER 1 March 15, 2023


Location: Capitol Town, San Fernando, Pampanga
Package: SANITARY/PLUMBING WORKS

ATTENTION : ENGR. LEO A. TANAMAL


PIC – PASUDECO TOWER 1
THRU : ENGR. JOSEPH MARIE L. MAGHIRANG
ME – PASUDECO TOWER 1
SUBJECT : REQUEST FOR PLUMBING & SANITARY PUMPS
Dear Sir,
This is to submit to your good office the material and equipment request for Sanitary- Plumbing works base on Material supplied by
the owner (OFM).

BOOSTER PUMP SCHEDULE


QTY (AS PER TOTAL CAPACITY APPROX. HEAD MOTOR POWER REMARKS
PUMP NUMBER FCD / UNIT RPM
CONTRACT)
GPM (CMH) FT (M) HP (KW) V Ph Hz

170 GPM (39.7 m3/HR) PACKAGED DUPLEX CONSTANT PRESSURE (CPS) BOOSTER PUMP 50%
220 FT. 2-10 HP EA. CAPACITY EACH W/ BLADDER TANK CAP. OF 220 GALLONS COMPLETE W/ VFD
BP 1a, 1b 1 SET OR 2-85 GPM EA. (2- 3500 400 3 60 Hz
(67.0m) (2-7.46 KW) CONTROLLER-PRE PIPED, PRE-WIRED MOUNTED IN COMMON BASE-READY
19.8 m3/HR) FOR PIPING HOOK-UP ALTERNATE ANDE OR SIMULTANEOUS OPERATION

PACKAGED DUPLEX CONSTANT PRESSURE (CPS) BOOSTER PUMP 50% 50%


30 GPM (6.8 m3/HR) 2-1.5 HP
161.7 FT CAPACITY EACH W/ BLADDER TANK CAP. OF 34 GALLONS COMPLETE W/ VFD
BP 2a, 2b 1 SET OR 2-15 GPM EA. (2- EA. (2-1.11 3500 400 3 61 Hz
(49.29m) CONTROLLER-PRE PIPED, PRE-WIRED MOUNTED IN COMMON BASE-READY
3.40 m3/HR) KW) FOR PIPING HOOK-UP ALTERNATE ANDE OR SIMULTANEOUS OPERATION

Sincerely yours,

Arch. Warlito Dato-on – Project Manager