You are on page 1of 14

Republic of the Philippines

Polytechnic University of the Philippines


Open University System
Sta. Mesa, Manila

CLASS ASSIGNMENT NO. 4

MSCM604 Construction Quality Risk Management

Dr. Manuel Muhi

ENGR. NATHANNIEL P. GONZALES

Master of Science in Construction Management

July 30, 2023


Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Case Study 1

Using the concept of risk management, prepare a simple risk management plan of your current project or work.

You may present your quantitative assessment (using expected monetary value or decision tree risk analysis) and qualitative assessment

(you may use the risk matrix like probability-impact or probability consequence matrix). (Make some justifiable assumptions).

1. What are the Risk appetite of your company/project?

2. What are the risk mitigation plan that you will recommend?

3. What are the risk response plan and monitoring plan that you will implement to address the problem/s?
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Answer:

The risk appetites of the company are those events that are rated with a risk prioritization/factor (RF) of two (2) or less. This means that no

additional controls are necessary and monitoring is still required to ensure current control is maintained to prevent risk from manifesting.
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

The following are some risk events of our company with the corresponding response plan and mitigation plan:

Process Risk Event L S RF Response Plan Mitigation Plan

Infrastructure Asset Inappropriate maintenance 1. Provide assistance to the Maintenance 1. Train maintenance
Maintenance activities applied to identified Point Persons (MPP) in identifying the personnel and crews
defects on the national roads appropriate maintenance activities on proper
and bridge leading to their corresponding to the identified road maintenance and
recurrences, resulting to: and bridge maintenance needs, and repair methodology.
a. Potential hazard to provision of corresponding fund in the 2. Coordinate with the
pedestrian and 2 3 6 AMWP. ESU to include in the
motorists 2. Monitor the performance of each procurement plan
b. Slowdown of traffic 3 3 9 Maintenance Point Person and the basic highway
flow evaluate the impact of the above maintenance
c. Increased 3 3 9 measures based on the condition of equipment and
maintenance cost their respective roads assigned. tools.
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila
Failure to validate the nature 2 2 4 1. Maintain regularly an updated 1. Establish a database
of work and urgency of the inventory of all OPB and FCS of all completed
proposed projects prioritized 2. Conduct annual validation of OPB and projects funded
under the Other Public FCS proposed for repair and under the OPB and
Buildings (OPB) and Flood maintenance including previously FCS Maintenance
Control Structures (FCS) funded and completed projects. Program for use in
Maintenance Program, leading the succeeding
to modification or realignment evaluation for
resulting to delayed project prioritization of
implementation. projects.

Frequent displacement of 3 2 6 1. Conduct daily roving on road sections 1. Coordinate with the
road warning signage by where signage were placed for road local government
individual road users which safety. units within the
may lead to vehicular road 2. Monitor regularly the maintenance of congressional
accidents. road signage. Observe a clear and district for an
visible view of road signage to prevent assistance to
and minimize future road accidents. monitor different
signage within their
jurisdiction.
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Process Risk Event L S RF Response Plan Mitigation Plan

Inspectorate and Failure to recommend 1 1 1 1. Closely monitor the progress on the 1. Plan the schedule of
Monitoring appropriate measures to implementation of Development/ assessment on the
address identified Action Plan to address identified compliance to policy
maintenance deficiencies/ problem areas. guidelines on the
improvement needs due to 2. Evaluate the effectiveness of the maintenance of
non-completion of assessment instituted measures and their impact national roads and
process leading to non- to the DEOs level of compliance to bridges to ensure
improvement or decline in the maintenance standards as well as to completion of the
implementing offices' level of the maintenance service delivery activity and the
compliance to maintenance target level. collection of data
standards needed for the
performance
evaluation/analysis
and identification of
problem areas.

Failure to provide on time a 2 2 4 1. Improve the current Emergency 1. Automate the


complete consolidated Operation Center (EOC) specifically for reporting system
situational report to NDRRMC the purpose of Disaster Preparedness, utilizing web or
and other NGA's for possible Response and Recovery, complete with mobile application in
response operations, due to all the required communication and coordination with
communication and reporting monitoring tools and equipment. the IMS.
issues resulting to delayed 2. Monitor the efficiency of the reporting
dissemination of information system upon completion of the web/
and incomplete data on mobile application.
passable/unpassable roads.
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila
Failure to provide immediate 1 3 3 1. Ask assistance from Local Government 1. Regularly, inspect
response to the National Units with an available appropriate the maintenance
Roads and Bridges situation tools and equipment to restore the tools and equipment
during Calamities/Disasters flow of the traffic. for possible defects
due to unavailability of tools 2. Rent necessary tools and equipment and damages and
and equipment resulting to for the restoration of the traffic flow. recommend for
the disruption of the maintenance repair,
continuous flow of traffic. if necessary
Non-conformance to the 2 3 6 1. Monitor regularly the completion of the 1. Request for the
Removal of Obstructions removal of the obstructions within the assistance of Local
within the Right-of-Way (D.O. Right-of-Way. Government Unit to
73 s.2014) due to refusal and transact for the
noncooperation of owners. cooperation of the
removal of
obstructions and the
issuance of notices.
Maintenance technical 1 2 2 1. Monitor the personnel from wearing 1. All employees must
personnel might be harmed proper protective wearables such as be fully vaccinated
by the Covid-19 virus during face mask, and face shield. and follow the
inspection and monitoring of 2. Isolate personnel who were exposed prescribed Standard
daily maintenance activities to the covid-19 virus. Protocols for COVID-
and may not be able to go to 19.
work. This will hamper the
usual workflow in the office
and the services to the public.
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Case Study 2

If you are the project manager of the company, using the figure below, how can you relate the opportunity of the

company’s investment from a possible loss of the invested resources (manpower, materials, equipment, etc.) to a

substantial gain. Discuss the important relationship between risk and uncertainty and what are the possible actions you

will do in pursuit of an opportunity.


Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Answer:

A project manager should properly study the organization’s risk appetite and the acceptable deviation from the organization's risk appetite (risk

tolerance). Thru this, a project manager can effectively assess whether the invested resources could provide substantial gain or a loss of

resources. From the given figure, a project manager can analyze that invested resources should not exceed the risk appetite point B because

increasing the resources will just result to the same considerable gain and increasing hazard exposure of risks may result to an increasing loss of

resources.

Risk is the situation under which the decision outcomes and their probabilities of occurrences are known to the decision-maker, and uncertainty is

the situation under which such information is not available to the decision-maker. Risk and uncertainty are related in that both preclude knowledge

of future states and both may be described by probabilities. It is important, however, to distinguish whether a lack of predictability arises from

insufficient knowledge (uncertainty) or from a well-understood probabilistic process (risk). Risk can be described by the likelihood and severity

of a negative event and thus, can be prevented through appropriate mitigation plans. Uncertainties are events that cannot be predicted and thus,

only be controlled and minimized by appropriate response plans.


Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Opportunity is also an uncertain event that could have a positive effect leading to benefits or rewards. It is a positive event that could be determined

by the benefit and occurrence of this event happening. In the pursuit of an opportunity, a project manager should determine the likelihood of the

event happening and also the range of benefits to consider in order to determine what opportunity should be prioritized for an action plan in order

for it to grow more which promotes welfare for the project.


Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Case Study 3

a. Explain the important points of qualitative risk analysis and what are the risk characteristics that are evaluated during

a qualitative risk analysis?

b. What is the contingency reserve of the project if the following risk information will be considered:

Identified Risk Probability Consequence


Delayed Delivery of Materials 0.16 -125,000.00
Lack of Manpower 0.57 36,800.00
Materials Quality 0.89 -89,000.00
Inflation 0.92 157,000.00
Trained Personnel 0.67 -123,000.00
Permits 0.25 101,000.00
Fabrication 0.35 -100,000.00
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

Answer:

a. Qualitative risk analysis tends to be more subjective. It focuses on identifying risks to measure both the likelihood of a specific risk event

occurring during the project life cycle and the impact it will have on the overall schedule should it hit. It prioritizes risks according to probability

and impact, identifies the main areas of risk exposure and improves the understanding of project risks. Organizations can improve the project’s

performance by focusing on high-priority risks. Perform Qualitative Risk Analysis also assesses other factors as well such as the time frame

for response and the organization’s risk tolerance associated with the project constraints of cost, schedule, scope, and quality. Such assessments

reflect the attitude of the project team and other stakeholders to risk.

Risk Likelihood or Probability - the possibility of a potential risk occurring, interpreted using qualitative values such as low, medium, or

high. This is in comparison with quantitative assessments, which use data and numbers.

Risk Severity or Impact - the extent of the damage to the institution, its people, and its goals and objectives resulting from a risk event

occurring. It is the expected harm or adverse effect that may occur due to exposure to the Risk. In other words, it measures how bad things

could get if a particular Risk materializes.


Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila
Risk Tolerance - the degree, volume or amount of risk that an organization can withstand. It indicates how sensitive organizations,

stakeholders, and people are towards risks.

Risk Appetite - the level of uncertainty an organization or stakeholder is willing to take on with the anticipation of reward at the end. The risk

appetite of an organization indicates how much it is willing to take risks to grow itself.

Risk Categories - made up of risk causes that fall into common groups. These groups can include risks such as technical risks, internal risks,

external risks, group risks, organizational risks, and or, environmental risks.

b.

Identified Risk Probability Consequence Expected Monetary


Value
Delayed Delivery of Materials 0.16 -125,000.00 -20,000.00
Lack of Manpower 0.57 36,800.00 20,976.00
Materials Quality 0.89 -89,000.00 -79,210.00
Inflation 0.92 157,000.00 144,440.00
Trained Personnel 0.67 -123,000.00 -82,410.00
Permits 0.25 101,000.00 25,250.00
Fabrication 0.35 -100,000.00 -35,000.00
Total -25,954.00
Republic of the Philippines
Polytechnic University of the Philippines
Open University System
Sta. Mesa, Manila

In the scenario, a cost of 25,954.00 needs to be added in the budget to cover all identified risks. This is because not all possible risks are guaranteed;

some may happen and some may not. All risks will add their EMV to the pool. The risks that do occur will use money from the pool, but the risks

that do not occur will help cover the cost of those that did

You might also like