Master Document List (MDL) DATE:

Client : ASBRI ENERGY REVISION:


Project-Hub Location: Plant CODE:
Comments/Approval Date Comments/Approval Date
Submission Date
SR. Input Ref.
PPL (Revision 00 ) Revision -1 (Revision 01 ) Revision -2 ( Deemed APPROVED if no response
Document Title Type Originator Deliverable Code ( Vendor ) input receipt date ( Deemed APPROVED if no response ( Deemed APPROVED if no response Status REMARK
NO. SR.NO
(Revision 00 ) reveived within 3 biz. Days of submission
Date
reveived within 3 biz. Days of
Date reveived within 3 biz. Days of submission
date. )
date. ) submission date. )
A Plot of land
A-1 Overall topography (contour map) - Drawing Asbri Energy - Open
A-2 Soil Test Report - Report Asbri Energy - Closed
A-3 Electrical resistivity tomography (ERT) - Report Asbri Energy - Open
A-4 Water test - Report Asbri Energy - Closed
B General input for electrical design
B-1 Architectural Drg :Plan layouts and exterior elevations & Roof Details - Drawing Asbri Energy - Open
B-2 Load list of Equipment - Report Asbri Energy - Open
B-3 Prelimnary Due-diligence - Report Asbri Energy - Open
B-4 Electrical Due - diligence - Report Asbri Energy - Open
B-5 Utility Arrangment Inputs A-1 Drawing Power Protech PPL/DE/23-24/00/Plant-Code Open
B-6 MFG GA Drawing of Equipments - Drawing Asbri Energy - Open
B-7 Load Data Sheet - Report Asbri Energy - Open
c Engineering Deliverables : Electrical design Open
C1-1 Transformer Rating Calculation B-1 Calculatio Power Protech PPL/DE/23-24/01/Plant-Code Open
C1-2 Transformer Specification C1-1 Report Power Protech PPL/DE/23-24/02/Plant-Code Open
C1-3 RMU Panel Rating Calculation C1-1 Calculatio Power Protech PPL/DE/23-24/03/Plant-Code Open
C1-4 RMU Panel Specification C1-3 Report Power Protech PPL/DE/23-24/04/Plant-Code Open
C1-5 LT Panel Rating Calculation C1-1 Calculatio Power Protech PPL/DE/23-24/05/Plant-Code Open
C1-6 LT Panel Speification C1-5 Report Power Protech PPL/DE/23-24/06/Plant-Code Open
C1-7 PSS Technical Specification C1-1 Report Power Protech PPL/DE/23-24/07/Plant-Code Open
C1-8 Aux. Panel Rating Calculation B-2 Calculatio Power Protech PPL/DE/23-24/08/Plant-Code Open
C1-9 Aux. Panel Specification C1-8 Report Power Protech PPL/DE/23-24/09/Plant-Code Open
C1-10 ACDB Panel Rating Calculation C1-16 Calculatio Power Protech PPL/DE/23-24/10/Plant-Code Open
C1-11 ACDB Panel Specification C1-10 Report Power Protech PPL/DE/23-24/11/Plant-Code Open
C1-12 Cable Sizing of HT,LT(Votage Drop, Current carying Capacity, etc) C1-16 Calculatio Power Protech PPL/DE/23-24/12/Plant-Code Open
C1-13 Cable Sizing of Auxilary Supply (Votage Drop, Current carying Capacity, etc) C1-20 Calculatio Power Protech PPL/DE/23-24/13/Plant-Code Open
C1-14 Earthing Calculation C1-16 Calculatio Power Protech PPL/DE/23-24/14/Plant-Code Open
C1-15 Overall Lightning Protection System Calculation C1-20 Drawing Power Protech PPL/DE/23-24/15/Plant-Code Open
C1-16 Single Line Diagram -Overall B-1 Drawing Power Protech PPL/DE/23-24/16/Plant-Code Open
C1-17 Single Line Diagram -Auxilary B-5 Drawing Power Protech PPL/DE/23-24/17/Plant-Code Open
C1-18 Key Plan of Gas Plant C1-16 Drawing Power Protech PPL/DE/23-24/18/Plant-Code Open
C1-19 Power flow diagram of Gas Plant C1-18 Drawing Power Protech PPL/DE/23-24/19/Plant-Code Open
C1-20 Gas Plant Electircal Layout (Plan , Elevation & Side View) C1-18 Drawing Power Protech PPL/DE/23-24/20/Plant-Code Open
C1-21 Substation layout (Plan , Elevation & Side View) C1-18 Drawing Power Protech PPL/DE/23-24/21/Plant-Code Open
C1-22 Earthing Layout of Gas Plant with Earth Chart C1-20 Drawing Power Protech PPL/DE/23-24/22/Plant-Code Open
C1-23 Earthing Layout - Substation with Earth Chart C1-21 Drawing Power Protech PPL/DE/23-24/23/Plant-Code Open
C1-24 Earth Pit Sectional Drawing (Cu , GI , CI , Chemicle Etc.) C1-22 Drawing Power Protech PPL/DE/23-24/24/Plant-Code Open
C1-25 Cable routing diagram with sectional drawing & Cable schedule C1-18 Drawing Power Protech PPL/DE/23-24/25/Plant-Code Open
C1-26 Pipe arrangment and Sectional drawing for Power & Control cables C1-18 Drawing Power Protech PPL/DE/23-24/26/Plant-Code Open
C1-27 Power plans include electrical rooms and major electrical equipment locations C1-3 Report Power Protech PPL/DE/23-24/22/Plant-Code Open
C1-28 Nameplate schedules include equipment ID tags, category I nameplates, and arc-flash warning labels C1-3 Report Power Protech
PPL/DE/23-24/27/Plant-Code Open
C1-29 Demolition and removal drawings C1-15 Drawing Power Protech PPL/DE/23-24/28/Plant-Code Open
C1-30 Interconnection/wiring diagrams C1-15 Drawing Power Protech PPL/DE/23-24/29/Plant-Code Open
C1-31 Raceway layout drawings C1-15 Drawing Power Protech PPL/DE/23-24/30/Plant-Code Open
C1-32 Conduit schedule C1-16 Drawing Power Protech PPL/DE/23-24/31/Plant-Code Open
C1-33 LUX Calculation of Entire Plant C1-17 Calculatio Power Protech PPL/DE/23-24/32/Plant-Code Open
C1-34 Lighting layout with Fixtures & LDB , PDB Placement C1-18 Drawing Power Protech PPL/DE/23-24/33/Plant-Code Open
C1-35 Lighting layout with Wiring details and Lighting schedule C1-20 Drawing Power Protech PPL/DE/23-24/34/Plant-Code Open
C1-36 Lightning assessment layout with LA placement & Zone coverage C1-20 Drawing Power Protech PPL/DE/23-24/35/Plant-Code Open
C1-37 Bus duct arrangment (Side View , Elevation , Plan View) if applicable C1-21 Drawing Power Protech PPL/DE/23-24/36/Plant-Code Open
C1-38 Fire & Safety Layout of Gas Plant with Table Utility room fire & Safety is needed (Substation) C1-20 Drawing Power Protech PPL/DE/23-24/37/Plant-Code Open
C1-39 IOT Device : LAN & MODBUS Layout for EMS purpose C1-20 Drawing Power Protech PPL/DE/23-24/38/Plant-Code Open
C1-40 Relay Setting and coordination chart C1-16 Report Power Protech PPL/DE/23-24/39/Plant-Code Open
C1-41 Specification for Electrical Work for Supply, Installation & Commissioning including consumables for, C1-16 Report Power Protech PPL/DE/23-24/40/Plant-Code
- Cables
- Lighting
- Earthing Open
- Lightening
- Safety & Fire fighting
- Bus Duct

C1-42 Cable Schedule of Entire Plant - Electrical Report Power Protech PPL/DE/23-24/41/Plant-Code
Cable Schedule of Entire Plant - Control System C1-16 Open
C1-43 Work Contract for Electrical Installation C1-16 Report Power Protech PPL/DE/23-24/42/Plant-Code Open
C1-44 Master Bills of Material for Electrical Infra C1-16 BOM Power Protech PPL/DE/23-24/43/Plant-Code Open
C1-45 List of Approved Makes for Deliverables of Supply C1-16 Report Power Protech PPL/DE/23-24/44/Plant-Code Open
D-40 Design of AMF Panel & Control Scheme arrangement C1-18 Report Power Protech PPL/DE/23-24/45/Plant-Code Open
D-41 Design of DG Sizing With Installation Plan C1-18 Report Power Protech PPL/DE/23-24/46/Plant-Code Open
D-42 Design of Power Factor consumption of Entire Plant and Calculation C1-18 Report Power Protech PPL/DE/23-24/47/Plant-Code Open
D-43 Design of APFCR Panel for Entire Plant C1-20 Report Power Protech PPL/DE/23-24/48/Plant-Code Open
D OEM input : For Detailed Engineering Open
D-01 Equipment/Load Datasheet B-7 Datasheet Vendor - Open
D-02 Equipment/Load Installation Manual B-7 Report Vendor - Open
D-03 Equipment/Load Test Report B-7 Report Vendor Open
D-05 Transformer-GA LAYOUT - Detailed drawing C1-2 Drawing Vendor - Open
D-06 Transformer-GTP - As built C1-2 GTP Vendor - Open
D-07 Transformer-Recommended Foundation Drawing D-05 Drawing Vendor - Open
D-08 Transformer-Routine Test Report - Report Vendor - Open
D-09 Transformer-Type Tesr Report - Report Vendor - Open
D-10 RMU-GA LAYOUT - Detailed drawing C1-4 Drawing Vendor - Open
D-11 RMU-GTP -As built C1-4 GTP Vendor - Open
D-12 RMU-Recommended Foundation Drawing D-10 Drawing Vendor - Open
D-13 RMU-Routine Test Report - Report Vendor - Open
D-14 RMU-Type Tesr Report - Report Vendor - Open
D-15 LT Panel-GA LAYOUT - Detailed drawing C1-6 Drawing Vendor - Open
D-16 LT Panel-GTP -As built C1-6 GTP Vendor - Open
D-17 LT Panel-Recommended Foundation Drawing D-15 Drawing Vendor - Open
D-18 LT Panel-Routine Test Report - Report Vendor - Open
D-19 LT Panel-Type Tesr Report - Report Vendor - Open
D-20 PSS -GA LAYOUT - Detailed drawing C1-7 Drawing Vendor - Open
D-21 PSS-GTP - As built C1-7 GTP Vendor - Open
D-22 PSSl-Recommended Foundation Drawing D-20 Drawing Vendor - Open
D-23 PSS-Routine Test Report D-21 Report Vendor - Open
D-24 PSS-Type Tesr Report D-21 Report Vendor - Open
D-25 ACDB Panel -GA LAYOUT - Detailed drawing C1-10 Drawing Vendor - Open
D-26 ACDB Panel-GTP C1-11 GTP Vendor - Open
D-27 ACDB Panel-Recommended Foundation Drawing D-25 Drawing Vendor - Open
D-28 ACDB Panel-Routine Test Report D-26 Report Vendor - Open
D-29 ACDB Panel-Type Tesr Report - Report Vendor - Open
D-30 Aux. Panel-GA LAYOUT C1-9 Drawing Vendor - Open
D-31 Aux. Panel-GTP C1-9 GTP Vendor - Open
D-32 Aux. LT Panel-Recommended Foundation Drawing D-30 Drawing Vendor - Open
D-33 Aux. LT Panel-Routine Test Report D-31 Report Vendor - Open
D-34 Power Cable-GTP C1-12 GTP Vendor - Open
D-35 Power Cable-Routine Test report C1-12 Report Vendor - Open
D-36 Control Cable -GTP C1-13 GTP Vendor - Open
D-37 Control Cable -Routine Test report C1-14 Report Vendor - Open
D-38 Earthing Material -GTP C1-14 GTP Vendor - Open
D-39 Earthing Material -Routine Test report C1-15 Report Vendor - Open
D-40 Design of AMF Panel & Control Scheme arrangment C1-16 Report Vendor Open
D-41 Design of DG Sizing With Installation Plan C1-17 Report Vendor Open
E Engineering Deliverables : Civil & Structural Open
E-10 BOM for Switchyard Foundation - BOM Power Protech PPL/DE/23-24/47/Plant-Code Open
E-14 Meter Room & RMU detailed drawing - Drawing Power Protech PPL/DE/23-24/51/Plant-Code Open
E-15 Cable Trench Layout (Switchyard , Electrical Room , LT panel) D-06 Drawing Power Protech PPL/DE/23-24/52/Plant-Code Open
E-16 Transformer -Foundation Drawing D-07 Drawing Power Protech PPL/DE/23-24/53/Plant-Code Open
E-17 RMU - Foundation drawing D-12 Drawing Power Protech PPL/DE/23-24/54/Plant-Code Open
E-18 LT Panel- Foundation drawing D-17 Drawing Power Protech PPL/DE/23-24/55/Plant-Code Open
E-19 PSS Foundation drawing D-22 Drawing Power Protech PPL/DE/23-24/56/Plant-Code Open
E-20 Fire Wall for Transformer- Detailed Drawings - Drawing Power Protech PPL/DE/23-24/57/Plant-Code Open
E-21 Bus Duct Support member Foundation - Drawing Power Protech PPL/DE/23-24/58/Plant-Code Open
E-22 Motor and Other Equipment Foundation/ Stand Drawing D-02 Drawing Power Protech PPL/DE/23-24/59/Plant-Code Open
E-25 Work Contract for Civil & Structural work - Report Power Protech PPL/DE/23-24/62/Plant-Code Open
E-26 Raceway & Cable Tray Structural drawing with Members and Support with Part BOM Report Power Protech PPL/DE/23-24/63/Plant-Code Open
F Security & Safety Open
F-1 CCTV camera Layout Drawing Power Protech PPL/DE/23-24/63/Plant-Code Open
F-2 Camera Installation and Zone Coverage layout with Placement of DVR C1-18 Drawing Power Protech PPL/DE/23-24/64/Plant-Code Open
F-3 Internet - LAN distribution layout with Router arrangment C1-20 Drawing Power Protech PPL/DE/23-24/65/Plant-Code Open
G Testing Activity – Electrical – Additional Activity to be done apart from MDL. Open
G-1 Providing Testing Reports of Electrical Panels in SAT Format C1-22 BOM Power Protech PPL/DE/23-24/47/Plant-Code Open
G-2 Providing Testing Reports of HV Switchgear in SAT Format - Drawing Power Protech PPL/DE/23-24/51/Plant-Code Open
G-3 Providing Testing Reports of Transformers in SAT Format C1-24 Drawing Power Protech PPL/DE/23-24/52/Plant-Code Open
G-4 Providing Testing Reports of Cables HT in SAT Format D-25 Drawing Power Protech PPL/DE/23-24/53/Plant-Code Open
G-5 Providing Testing Reports of Cables LT in SAT Format D-30 Drawing Power Protech PPL/DE/23-24/54/Plant-Code Open
G-6 Providing Testing Reports of Lighting Fixtures in SAT Format D-35 Drawing Power Protech PPL/DE/23-24/55/Plant-Code Open
G-7 Providing Testing Reports of Earthing in SAT Format E Drawing Power Protech PPL/DE/23-24/56/Plant-Code Open
G-8 Providing Testing Reports of DG in SAT Format - Drawing Power Protech PPL/DE/23-24/57/Plant-Code Open