DAILY PROGRESS REPORT


May 15, 2024

SECTION NO 1 SECTION NO 2
Cumulative Progress Section no 1&2 as on Today
Activity Nokhar Sustation To Lahore North Sub station Lahore North Sub staion - HVDC Converter Station

Qty %
Total Daily Progress This Day This Month To Date Total Daily Progress This Day This Month To Date Grand Total Weightage Total Progress
Completed Completed

1 2 3 4 5 6 7 8 9 10 11 12=2+7 13=6+11 14=(13/12)*100 15 16=15*13/12


VALIDATION OF ROUTE
(Km)
112.41 112.41 100 2.5% 2.50%
SOIL INVESTIGATION 80 79 100 2.5% 2.50%
TOWER STAKING 132 132 203 203 335 335 100 2.5% 2.50%
TOWER RELEASE 132 132 203 203 335 335 100 2.5% 2.50%
CONVENTIONAL
FOUNDATION 97 97 146 146 243 243 100 36% 36.00%

PILE FOUNDATION 35 35 57 57 92 92.00 100

PILE CAP 35 35 57 57 92 92 100 14% 14.00%

BACKFILLING 97 97 146 146 243 243 100

TOWER ERECTION 132 132 203 203 335 335 100.00

TOWER INSPECTION 132 132 203 203 335 335 100.00


15% 15.00%
TOWER PUNCHING 132 132 203 203 335 335 100.00

TOWER WELDING 132 132 203 203 335 335 100.00


TOWER PAINT 132 132 203 203 335 335 100.00

CONDUCTOR PULLING 44.644 44.295 68.374 68.292 113.018 112.587 99.62


DEAD ENDING / HOOK-UP /
MID SPAN JOINT

CONDUCTOR SAGGING

CONDUCTOR CLIPPING
20% 19.92%
JUMPER INSTALLATION

SHIELDWIRE PULLING
& 44.644 44.115 68.374 68.23 113.018 112.345 99.40
SHIELDWIRE SAGGING
OPGW PULLING &OPGW
SAGGING 44.644 44.566 68.374 68.35 113.018 112.916 99.91

OPGW JOINTING 16 14 24 24 40 38 95.00


TESTING AND
COMMISSIONING 1 0.980 1 0.98 2 1.960 98.00 5% 4.90%

RECTIFICATION OF PUNCH TOWER # 165-203 has been rechecked by GSO Team after
LIST
132 132 203 203 335 335.000 100.00
rectfication by Contractor.

1. ACDs, Barbid wire, Phase & Danger Plates are Installed from T# 1- 1. ACDs, Barbid wire, Phase & Danger Plates are Installed from
132 Except Tower # 01 (grid) & 66, 68 due to ROW. Tower# 1-203 Except Tower # 35,173 Due to ROW.
MISC ITEMS 132
2. Aerial Marking Plates are Instatlled on all specified Located
129 203
2. Aerial Marking Plates are Instatlled on all specified Located
201 335 330 98.51

Towers. Towers.
OVERALL
99.82%
PROGRESS
PUNCH PUNCH TOWER # 165-203 has been rechecked by GSO Team after
LIST LIST rectfication by Contractor.

NOTE: THE LINE IS ENERGIZED ON NO LOAD THROUGH AN INTERM ARRANGEMENT AT UNDER CONSTRUCTION LAHORE NORTH SUB STATION. MEANS BY PASSING THE MENTIONED SUB STATION