Professional Documents
Culture Documents
WO Hole Cleaning Guidelines
WO Hole Cleaning Guidelines
1/22
Hole Cleaning Guidelines Page 2 of 22
2/22
Hole Cleaning Guidelines Page 3 of 22
The key to effective clean out of a well is to ensure the methodology used is effective at cleaning out
any solids to optimise well production without jeopardising the well productivity by damaging the
formation.
There are very few studies done on hole cleaning in Workover, compared to Drilling and Coil Tubing.
In Drilling the focus on hole cleaning is generally to optimise ROP whereas in coil tubing it is generally
to promote the application of the technology. This guideline leverages drilling and CTU studies.
This guideline reviews hole cleaning where adequate circulation is possible including:
A brief review of hole cleaning of new wells to appreciate the drilling paradigm
A brief review of coiled tubing hole cleaning to appreciate the coiled tubing paradigm
Guidelines for Direct Circulation
Guidelines for Reverse Circulation
A summary page at the end gathers all of the recommendations on one page.
It does not include hole cleaning where the hole cleaning via circulation is not possible due to
excessive losses and one of the following techniques should be applied:
Bailing e.g. with the CEPS (Shakira) Pump
Jet Pump lifting with:
o Concentric Coil Tubing
o Jointed pipe
Although the impact of losses on well cleanout are considered within the guideline it does not cover
Fluid Loss Management Procedures which are addressed in Fluid Loss Management Procedures Ref
PR-DLC-FL.
3/22
Hole Cleaning Guidelines Page 4 of 22
Knowledge about the type of solids is important as this has a major impact on how easy it might be
to remove them from a well. In particular the vertical setting velocity of particles in a fluid can be
described as follows:
0.667
Settling Velocity = 175*Pd*(Pw-Mw) ft/min
0.333 0.333
(Mw )*(Cp )
Where:
Pd Particle Diameter (in)
Pw Particle density (ppg)
Mw Mud Density (ppg)
Cp Plastic Viscosity (cp)
This equation clearly shows how the speed with which particles will fall in a stationary fluid is:
Proportional to the:
o Solid Size
o Solid Buoyant Weight
Inversely Proportional to the:
o Fluid Density
o Fluid Viscosity
This means that larger and more dense solids will fall through the fluid more rapidly than smaller,
lighter particles and they will not fall as fast through more dense and/or more viscous fluids. Table 1
shows some typical particles we might find in wells.
4/22
Hole Cleaning Guidelines Page 5 of 22
Table 1: Settling Velocities and Minimum Annular Velocities Recommended for Vertical Wells
As can be seen in Table 1 the settling velocity in the vertical plane can vary by up to two orders of
magnitude from a few to hundreds of feet per minute dependent on particle density, size and fluid
rheology. The rule of thumb in a vertical well is that the Fluid Velocity should be at least double the
settling velocity to lift solids out of the well. For a given particle type the one factor that can have the
most affect on the settling velocity in a vertical well is an increased fluid viscosity. That is why viscous
pills are very effective at cleaning out solids from the vertical sections of wells, but aren’t as effective
in more deviated well sections.
The liquid velocity is driven by the hole or annular size so the larger the hole the smaller the velocity.
In particular when trying to calculate the annular velocity the equation to use is as follows:
Where:
Q = Flow Rate gpm
Do = ID of Hole or Outer Pipe in
Di = OD of Pipe in
i.e. for 5bpm/210gpm being circulated inside 9 5/8” 47ppf 8.681” ID casing and 3.5” Pipe the annular
velocity is 81.5fpm.
5/22
Hole Cleaning Guidelines Page 6 of 22
For a well of Deviation Ø from the vertical the liquid flow in the vertical plane can be determined by:
Therefore subject to the well deviation solids will travel straight up, or travel only a few joints before
falling to the low side of the well. Of course in horizontal wells the particles just roll along with
saltation flow as happens with waves at the beach or wind in the desert.
This avalanche section has to be respected and will be found both in deviated and horizontal wells.
As shown above in Fig 1 the S Shaped type wells are more difficult to clean out than the J Shaped
wells. This is because it is easy to clean out the lower less deviated section of the well, but then when
the pumps are shut off sand can collect and avalanche in the more deviated section of the well and
even stick downhole tool strings.
6/22
Hole Cleaning Guidelines Page 7 of 22
7/22
Hole Cleaning Guidelines Page 8 of 22
Today’s best practises as recommended by K&M Schlumberger Hole Cleaning experts are:
The larger the hole and the smaller the pipe the more difficult it is to clean out solids from the hole
particularly since the pipe is more eccentred. However higher rotation can compensate for this
because it helps to centre the pipe as well as lift the cuttings via viscous drag up into the zones of
higher velocity (Refer to Figure 3).
Fig 3: Pipe & solids are eccentred so the main fluid flow avoids the solids until the pipe is rotated
“dragging” solids via viscous coupling Into the main flow.
8/22
Hole Cleaning Guidelines Page 9 of 22
Fig 4: Drillers use large water ways on their downhole tools to help pulling out of the hole – this is
not the case with CCCPs for ESP Cables where sand &/or scale can be dragged up & get them stuck
Barite Sag
Barite (BaSO4) has a density of 4.2sg and can easily fall out of the mud due to its high
density. Remember that when milling scale which is generally BaSO4 the highest possible
velocities are required to clean out the well.
Keep Pipe Moving
If unable to rotate then reciprocate – drillers do this to prevent getting stuck with differential
sticking, cement etc. On a Pulling Unit it is best to reciprocate over +/-30ft equivalent to the
length of one joint as this allows the coupling to move over the entire length of a joint and
disturb any solids on the low side. On a jacking unit we are limited by the jack stroke, but if
possible move an entire joint. (Also refer to Fig 5 where the velocity required for cleaning
with stationery coil is double that for coil which is being moved.) Therefore for cleanouts
without rotation pipe reciprocation/pipe movement is required to facilitate the cleanout.
9/22
Hole Cleaning Guidelines Page 10 of 22
In coil tubing the industry can be split ito two very distinct geographic groups North America and the
rest of the world. Most developments have occurrred in North America and in particular Alaska
where Arco, and then it’s successor, BP pioneered CTU applications on land wells. Here reverse
circulating as well as direct circulating has been used extensively.
Fig 5: Compares liquid flow rates/velocities required for various CTU cleanout modes
10/22
Hole Cleaning Guidelines Page 11 of 22
11/22
Hole Cleaning Guidelines Page 12 of 22
12/22
Hole Cleaning Guidelines Page 13 of 22
Fig 8: A pictorial comparison of laminar flow Fig 9: Contrast between turbulent & laminar flow
above with turbulent flow below – turbulent flow accelerates erosion
The random flow created with turbulent flow disturbs the solids and lifts them up from the side of
the hole into the main flow so the hole can be cleaned without rotation as is the case with Coil
Tubing.
Table 4 below shows how the critical velocity, above which there is turbulent flow, is very much
influenced by the fluid viscosity and yield point. In particular a flow rate some 50x larger is required
with mud compared to water. Therefore there is a distinct advantage of using water and or brines for
hole cleaning that drilling cannot leverage because of the mud rheology.
Table 4: Comparison of Flow Rates Needed to Achieve Turbulent Flow with Different Rheology
However rotation still helps hole cleaning even with turbulent flow as can be seen by the study
illustrated in Fig 10. This demonstrates that even without significant viscous drag rotation is a useful
tool since to facilitate hole cleaning it helps centralise the pipe.
13/22
Hole Cleaning Guidelines Page 14 of 22
Fig 10: 2015 IRJet Study with 1-2cp water with an Outer Pipe ID (Do) of 3.0” and Inner Pipe OD (Di)
of 2.0” clearly demonstrates that even with turbulence pipe rotation of 10 rpm (Orange) has a
significant impact on hole cleaning and the percentage of sand particles (WRP %) recovered within
the test period compared to no rotation (Blue).
Fig 11: Demonstrates that without rotation a flow rate of at least 200fpm is required, but
in this experiment the pipe was centered with only 0.5” standoff. With eccentered pipe &
lower viscosities a higher flow rate is recommended.
14/22
Hole Cleaning Guidelines Page 15 of 22
15/22
Hole Cleaning Guidelines Page 16 of 22
Fig 12: TCTM-A09 Drilling out cement in this S Shaped well caused problems
16/22
Hole Cleaning Guidelines Page 17 of 22
LGN-06 Colombia
Work String
Min Annular
Component
Velocity/Flow
10x 4 ¾” x 7” Liner 140fpm/1.8bpm
2 7/8” x 7” Liner 140fpm/3.5bpm
2 7/8” x 9 5/8” Csg 140fpm/8.7bpm
3.5” x 9 5/8” 120fpm/6.95bpm
Cleanout Parameters:
Parameter Actually Used
Fluid Water + Vis Pills
Rotation 70rpm
Flow Rate 3.4bpm
Min Velocity 54fpm
17/22
Hole Cleaning Guidelines Page 18 of 22
Dynamic Losses (blpd) = Pressure Losses Due to Liquid Flow * Injectivity Index
Before a workover the losses should be calculated for both Direct & Reverse Circulation scenarios to
determine the best cleanout method. Normally for the same flowrate the pressure loss inside pipe is
greater than the pressure loss in the annulus. However when cleaning out wells the flow rate is a
18/22
Hole Cleaning Guidelines Page 19 of 22
consequence of the liquid velocity required to lift the solids and generally when reverse circulating
the net flow rate required up the pipe is lower than the net flow rate required up the larger annulus.
Well Characteristics
PI = 1blpd
II Max = 3blpd
Casing Size = 9 5/8” 43.5ppf ID 8.755”
Work String Type = 3.5” DP
Work String OD /ID = 3.5”/2.764”
Reservoir Measured Depth = 2000mMDRT
Reservoir True Vertical Depth = 1500mTVDRT
Reservoir Pressure = 1278psi
Reservoir EMW = 0.6sg
Workover Fluid to be Used = FTSW (Filtered Treated Seawater)
Workover Fluid Density = 1.03sg
Workover Fluid Viscosity = 0.5cp @ Formation Temperature
Overbalance = 916psi
Max Static Losses = 1.91bpm
Max Well Deviation = 40°
Rotation Possible = Yes – 70rpm
Minimum Annular Velocity = 140fpm
Annular Equivalent Flow Rate = 368gpm/8.76bpm
Minimum Pipe Velocity = 150fpm
Pipe Equivalent Flow Rate = 47gpm/1.11bpm
19/22
Hole Cleaning Guidelines Page 20 of 22
So if only a cleanout is required then reverse circulation should be considered if the pumping
capacity is limited.
Casing/Drillpipe 7”/3.5”
Well Max Deviation 30.3°
Minimum Annular Velocity >120fpm
Proppant 12-18 Mesh (1200µ)
Cleanout Liquid Filtered Treated Seawater/1.03sg
Pump Flow Rate 7.7bpm
Total Losses 3.0bpm
Net Flow Rate after Losses 4.7bpm
Annular Velocity 171fpm (>120fpm minimum required.)
Viscous Pills HEC
20/22
Hole Cleaning Guidelines Page 21 of 22
Well Data
Casing/Drillpipe 7”/3.5”
Well Max Deviation 49.2° - Avalanche Country
Minimum Annular Velocity >160fpm
Proppant 12-18 Mesh (1200µ)
Cleanout Liquid NaCl Brine/1.15sg
Direct Circulation
Pump Flow Rate 4.0bpm (At 6bpm had 2.5bpm losses)
Total Losses 1.0bpm
Net Flow Rate after Losses 3.0bpm
Annular Velocity 109fpm (<160fpm minimum required.)
Viscous Pills HEC
Rotation 70rpm
Reverse Circulation
DP Pressure Loss 45psi
Surface Pressure Losses 25psi Estimated
Min Required Flow Rate 1.26bpm
Max Back Pressure 70psi
Total Losses +/-6.25bpm Estimated
Total Flow Rate Required 7.51bpm
It is always essential to have sufficient cleanout fluid readily available or a contingent means to
recover the fill i.e. CEPs/Shakira Pump etc. (In this well the CEPs pump was tried but the proppant fell
out of the tool because the tool used flappers to retain the proppant and not plungers as have since
been recommended by CEPs.)
21/22
Hole Cleaning Guidelines Page 22 of 22
22/22