Work Programme

The document outlines a project schedule for the construction of NH-30, detailing various tasks, their durations, start and finish dates, and dependencies. Key tasks include design and drawing submissions, construction of culverts, road works, and installation of traffic control devices, with the overall project spanning from April 2025 to April 2026. The schedule includes milestones and specific activities related to road safety and pedestrian facilities.

Uploaded by

Prince Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
297 views1 page

Work Programme

The document outlines a project schedule for the construction of NH-30, detailing various tasks, their durations, start and finish dates, and dependencies. Key tasks include design and drawing submissions, construction of culverts, road works, and installation of traffic control devices, with the overall project spanning from April 2025 to April 2026. The schedule includes milestones and specific activities related to road safety and pedestrian facilities.

Uploaded by

Prince Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

ID Task Name Duration Start Finish Predecessors 01 March 01 May 01 July 01 September 01 November 01 January 01 March 01 May

03-02 03-03 31-03 28-04 26-05 23-06 21-07 18-08 15-09 13-10 10-11 08-12 05-01 02-02 02-03 30-03 27-04
1 Construction of NH-30 from km 162+000 to 365 d 02-04-25 02-04-26
179+500
2 Issue of LOA
3 Receipt of Appointment Date 0d 02-04-25 02-04-25 02-04
4 Preliminaries Activities 33 d 02-04-25 05-05-25
5 Handover ROW by NHAI 0d 02-04-25 02-04-25 02-04
6 Utility Shifting Works 30 d 05-04-25 05-05-25
7 Design & Drawing 90 d 09-04-25 08-07-25
8 Submission of Design Director Cv 0d 09-04-25 09-04-25 09-04
9 Submission of Proof Check Consultant 0d 09-04-25 09-04-25 8SS 09-04
Biodata for Approval
10 Submission of Safety Consultant Biodata for 0d 09-04-25 09-04-25 8SS 09-04
Approval
11 Submission of Drawing of Widen Culverts 7d 24-05-25 31-05-25 13
12 Submission of Pavement Design report 1d 15-05-25 16-05-25
13 Submission of Plan Profile of Main Carriageway 8d 16-05-25 24-05-25 12
14 Submission of Drawing of New Culverts 5d 24-05-25 29-05-25 13
15 Submission of Minor Bridge Drawing along 35 d 24-05-25 28-06-25 13
with Geotech report
16 Submission of Road Furniture Drawing 10 d 28-06-25 08-07-25 15
along with all Misc.items like bus
bays,New Jersey carsh barrier and
17 Execution 365 d 02-04-25 02-04-26
18 Construction of Culverts 180 d 29-05-25 25-11-25
19 Widening of Box Culverts 60 d 29-05-25 28-07-25 14
20 Widening of Pipe Culverts RCC Culverts 60 d 28-07-25 26-09-25 19
21 Construction of New Box Culverts 60 d 26-09-25 25-11-25 20
22 Construction of Road Side Drainage 122 d 02-04-25 02-08-25
23 RCC drain 70 d 24-05-25 02-08-25 13
24 Construction of Lined drain with Geocell 30 d 02-04-25 02-05-25
25 Construction of Road works 225 d 02-05-25 13-12-25
26 Widening of existing work upto GSB level 40 d 02-05-25 11-06-25 24
27 Milling of Bt layer 20 d 11-06-25 01-07-25 26
28 Laying of WMM Layer (Reinforced 80 d 01-07-25 19-09-25 27
with geogrid)
29 Laying of DBM 40 d 19-09-25 29-10-25 28
30 Laying of BC 45 d 29-10-25 13-12-25 29
31 Construction of Minor Bridges 188 d 28-06-25 02-01-26
32 Construction of upto Foundation 50 d 28-06-25 17-08-25 15
33 Construction of Sub structure 50 d 17-08-25 06-10-25 32
34 Construction of Super structure 70 d 06-10-25 15-12-25 33
including bearing
35 Laying of wearing coat on MNB 8d 15-12-25 23-12-25 34
36 Misc Works 10 d 23-12-25 02-01-26 35
37 Traffic Control Devices and Road Safety 360 d 02-04-25 28-03-26
38 Installation of Traffic Signs 20 d 02-01-26 22-01-26 39
39 Pavement Marking 20 d 13-12-25 02-01-26 30
40 Safety Barrier 30 d 02-04-25 02-05-25
41 Instalation of Thrie Beam single faced 25 d 23-12-25 17-01-26 35
MBCB
42 Instalation of Concrete Single faced 30 d 17-01-26 16-02-26 41
barriers
43 Construction of Concrete double 40 d 16-02-26 28-03-26 42
faced barriers (NJB)
44 Installation of antiglare sheet 10 d 02-01-26 12-01-26 36
45 Road Side Furniture 50 d 02-01-26 21-02-26
46 Installation of Kilometer and Hectometer 10 d 02-01-26 12-01-26 36
Stones
47 Installation of Overhead Gantry 20 d 12-01-26 01-02-26 46
48 Installation of Road Delineators 10 d 01-02-26 11-02-26 47
49 Installation of Road Studs 10 d 11-02-26 21-02-26 48
50 Pedestrian Facilities 53 d 31-01-26 25-03-26
51 Instalation of Bus Shelter 15 d 21-02-26 08-03-26 49
52 Instalation of PGR 10 d 08-03-26 18-03-26 51
53 Highway Lighting 38 d 31-01-26 10-03-26 36
54 Land Scaping and Tree Plantation 23 d 02-03-26 25-03-26
55 Site Demobilazation 1d 01-04-26 02-04-26 54SS
Task Summary External Milestone Inactive Summary Manual Summary Rollup Finish-only
Project: Km 1Km 62.000 (Lalgopa
Split Project Summary Inactive Task Manual Task Manual Summary Deadline
Date: 10-05-25
Milestone External Tasks Inactive Milestone Duration-only Start-only Progress

Page 1