Sample P6 Schedule

The document outlines the construction schedule for the Riga Airport Terminal Expansion Project, detailing various activities, milestones, and timelines from March 2025 to May 2029. Key activities include the construction of terminal sections, employer deliverables, and engineering tasks, with specific start and finish dates for each phase. The project involves multiple approvals and submissions related to design, permits, and guarantees throughout its duration.

Uploaded by

Manoj G
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
251 views20 pages

Sample P6 Schedule

The document outlines the construction schedule for the Riga Airport Terminal Expansion Project, detailing various activities, milestones, and timelines from March 2025 to May 2029. Key activities include the construction of terminal sections, employer deliverables, and engineering tasks, with specific start and finish dates for each phase. The project involves multiple approvals and submissions related to design, permits, and guarantees throughout its duration.

Uploaded by

Manoj G
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q

Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F

Construction Works For Stage 6 Of Riga Airport Terminal Expansion Project 1178 10-Mar-25 17-May-29

Contractual Milestones 1074 16-Jul-25 17-May-29


RIX.1000 Project Start 0 16-Jul-25
RIX.1010 Project Handover 0 17-May-29
Construction Milestones-Finish Dates 1054 01-Jul-25 06-Apr-29
RIX.2.MS.1001 Specification for technological equipments - Annexure 8 Provided by RIX 0 01-Jul-25
RIX.2.MS.1002 First Section: Demolition of existing access ramps, construction of a temporary building 0 28-Jul-26
RIX.2.MS.1010 Second Section: Construction of external evacuation routes on the North and South sides of the existing terminal 0 11-Aug-26
RIX.2.MS.1020 Third Section: Terminal expansio n 0 23-Jan-29
RIX.2.MS.1030 Fourth Section: Demolition of the temporary building and reconstruction of the non-Schengen arrivals area in Sector D 0 06-Apr-29
RIX.2.MS.1040 Fifth Section: Construction of part of the Terminal Baggage Handling Buil ding 0 17-Nov-28
RIX.2.MS.1050 Sixth Section: Reconstruction of the Schengen arrivals area in sector E of the Terminal and connectio n to BHS 0 24-Jan-29
RIX.2.MS.1060 Seventh Section: Terminal F, 1st floor reconstruction to provide service facilities 0 04-Nov-28
RIX.2.MS.1070 Eighth Section: Construction of an access flyover 0 27-Aug-27
RIX.2.MS.1080 Ninth Section: Areas with utilities, road construction 0 27-Oct-26
RIX.2.MS.1090 Tenth Section: Construction of a multi-storey car parking 0 12-Nov-26
Employer’s deliverables 788 02-May-25 21-Mar-28

RIX.1.CE.1000 Notification of Contract Award 1 02-May-25 02-May-25


RIX.1.CE.1010 Contract Signing 12 02-Jul-25 15-Jul-25
RIX.1.CE.1015 Project Commencement Date 0 16-Jul-25
RIX.1.CE.1020 Approval of Permits for Phase-I (Stage I, II,VIII, IX, X) 20 16-Jul-25 07-Aug-25
RIX.1.CE.1025 Time to Access the Site 1 06-Sep-25 06-Sep-25
RIX.1.CE.1030 Approval of Permits for Terminal Building Part-A (Stage III) 30 08-Sep-25 13-Oct-25
RIX.1.CE.1040 Approval of Permits for Phase-II (Stage III, V) 30 14-Oct-25 04-Dec-25
RIX.1.CE.1050 Approval of Permits for Phase-III (Stage IV, VI, VII) 30 19-Oct-27 24-Nov-27
RIX.1.CE.1060 Notice to Commence for Stage-IV 1 19-Oct-27 20-Oct-27
RIX.1.CE.1070 Notice to Commence for Stage-VI 1 19-Oct-27 20-Oct-27
RIX.1.CE.1080 Notice to Commence for Stage-VII 1 20-Mar-28 21-Mar-28
RIX.1.CE.1090 Payment of Advance payment for Phase-I (Stage I, II,VIII, IX, X) 60 28-May-25 07-Aug-25
RIX.1.CE.1100 Payment of Advance payment for Phase-II (Stage III, V) 60 05-Feb-26 30-Apr-26
RIX.1.CE.1110 Payment of Advance payment for Phase-III (Stage IV, VI, VII) 60 11-Nov-27 26-Jan-28
Preliminary Works 724 10-Mar-25 11-Nov-27

KPIL Company Registration 149 10-Mar-25 05-Sep-25


RIX.3.PL.1005 Registration of branch a foriegh merchant in commercial register 2 10-Mar-25 11-Mar-25
RIX.3.PL.1007 Employment agreement with construction specialist registered with tax authority 40 16-Jul-25 30-Aug-25
RIX.3.PL.1010 Registration in register of construction merchants of republic of latvia 5 01-Sep-25 05-Sep-25
Policy Document Submissions 680 03-May-25 11-Nov-27
RIX.3.PL.1000 Submission of Performance Guarantee Security 28 03-May-25 05-Jun-25
RIX.3.PL.1020 Submission of Advance Payment Guarantee for Phase-I (Stage I, II,VIII, IX, X) 20 03-May-25 27-May-25
RIX.3.PL.1030 Submission of Advance Payment Guarantee for Phase-II (Stage III, V) 20 06-Jun-25 01-Jul-25
RIX.3.PL.1040 Submission of Advance Payment Guarantee for Phase-III (Stage IV, VI, VII) 20 19-Oct-27 11-Nov-27
RIX.3.PL.1050 Submission of CAR insurance 6 01-Sep-25 06-Sep-25
RIX.3.PL.1060 Submission of CTA insurance(Professional Indemnity & Civil lia bility) 6 01-Sep-25 06-Sep-25
RIX.3.PL.1070 Submission of Permit for Terminal Buildin g Part-A (Stage III) 8 16-Jul-25 24-Jul-25
RIX.3.PL.1080 Submission of Permit for Phase-II (Stage III, V) 8 02-Jul-25 10-Jul-25
RIX.3.PL.1090 Submission of Permit for Phase-III (Stage IV, VI, VII) 8 09-Oct-27 19-Oct-27
Preparatory Works 328 12-Mar-25 13-Jun-26

Actual Work Critical Remaining Work Page 1 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Setting up of Temporary Facilities & Staff 328 12-Mar-25 13-Jun-26
RIX.4.PW.1000 Key Personnel Registration (PM, Dy.PM, Plnn & Proj Cntrol Mgr, A/c & Admin Head, EHS Head) 100 12-Mar-25 12-Jul-25
RIX.4.PW.1005 Key Personal Registration for Balance People 20 14-Jul-25 05-Aug-25
RIX.4.PW.1010 Setting-up of Project office 40 06-Sep-25 24-Oct-25
RIX.4.PW.1020 Setting -up of HSE Cabin 40 24-Oct-25 26-Jan-26
RIX.4.PW.1030 Setting -up of QAQC Lab 50 26-Jan-26 14-Apr-26
RIX.4.PW.1040 Setting -up of store 50 14-Apr-26 13-Jun-26
Survey Works 0 06-Sep-25 06-Sep-25
RIX.4.SW.1050 Geotechnical Investigation, Topographical survey ,Dilapidatio n survey and submissio n 0 06-Sep-25
Appontment of Engineering Consultant 1 03-May-25 03-May-25
RIX.1020 Appointment of Engineering Consultant 1 03-May-25 03-May-25
Engineering 62 06-May-25 18-Jul-25

Detailed Design 62 06-May-25 18-Jul-25


Architecture 31 06-May-25 10-Jun-25
RIX.4.PW.DD.1000 MLCP - Detailed Design - Submission 30 06-May-25 09-Jun-25
RIX.4.PW.DD.1005 MLCP - Detailed Design - Approval 1 10-Jun-25 10-Jun-25
RIX.4.PW.DD.1010 Viaduct - Detailed Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1015 Viaduct - Detailed Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1020 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1025 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1030 At grade Work - Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1035 At grade Work - Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1040 Terminal Building Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1045 Terminal Building Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1070 Existing Terminal Buildin g - Refurbishment Work - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1075 Existing Terminal Buildin g - Refurbishment Work - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1080 BHS Building - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1185 BHS Building - Approval 1 07-May-25 07-May-25
Structural 60 08-May-25 18-Jul-25
RIX.4.PW.DD.1085 MLCP - Detailed Design - Submission 30 11-Jun-25 17-Jul-25
RIX.4.PW.DD.1095 MLCP - Detailed Design - Approval 1 18-Jul-25 18-Jul-25
RIX.4.PW.DD.1105 Viaduct - Detailed Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1115 Viaduct - Detailed Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1125 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1135 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1145 At grade Work - Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1155 At grade Work - Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1165 Terminal Building Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1175 Terminal Building Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1225 Existing Terminal Buildin g - Refurbishment Work - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1235 Existing Terminal Buildin g - Refurbishment Work - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1345 BHS Building - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1355 BHS Building - Approval 1 09-May-25 09-May-25
MEP 31 08-May-25 12-Jun-25
RIX.4.PW.DD.1245 MLCP - Detailed Design - Submission 1 11-Jun-25 11-Jun-25
RIX.4.PW.DD.1255 MLCP - Detailed Design - Approval 1 12-Jun-25 12-Jun-25
RIX.4.PW.DD.1265 Viaduct - Detailed Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1275 Viaduct - Detailed Design - Approval 1 09-May-25 09-May-25

Actual Work Critical Remaining Work Page 2 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.PW.DD.1285 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1295 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1305 At grade Work - Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1315 At grade Work - Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1325 Terminal Building Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1335 Terminal Building Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1385 Existing Terminal Buildin g - Refurbishment Work - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1395 Existing Terminal Buildin g - Refurbishment Work - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1405 BHS Building - Submission 1 10-May-25 10-May-25
RIX.4.PW.DD.1415 BHS Building - Approval 1 12-May-25 12-May-25

Method Statements 92 08-May-25 25-Aug-25

First Section: Demolition of existing access ramps, construction of a temporary building & Chiller H 35 16-Jul-25 25-Aug-25
Demolition of Ramps 10 16-Jul-25 26-Jul-25
RIX.4.ME.1000 Submission 3 16-Jul-25 18-Jul-25
RIX.4.ME.1005 Approval 7 19-Jul-25 26-Jul-25
Construction of Temporary Building & Chiller House - Civil & Structural Steel works 12 19-Jul-25 01-Aug-25
RIX.4.ME.1010 Submission 5 19-Jul-25 24-Jul-25
RIX.4.ME.1015 Approval 7 25-Jul-25 01-Aug-25
Construction of Temporary Building & Chiller House - Facade & Roof Works 12 25-Jul-25 07-Aug-25
RIX.4.ME.1020 Submission 5 25-Jul-25 30-Jul-25
RIX.4.ME.1025 Approval 7 31-Jul-25 07-Aug-25
Construction of Temporary Building & Chiller House - MEP & ELV Works 12 31-Jul-25 13-Aug-25
RIX.4.ME.1030 Submission 5 31-Jul-25 05-Aug-25
RIX.4.ME.1035 Approval 7 06-Aug-25 13-Aug-25
Construction of Temporary Building & Chiller House - Elevators and Escalators 12 06-Aug-25 19-Aug-25
RIX.4.ME.1040 Submission 5 06-Aug-25 11-Aug-25
RIX.4.ME.1045 Approval 7 12-Aug-25 19-Aug-25
Construction of Temporary Building & Chiller House - Finishes 12 12-Aug-25 25-Aug-25
RIX.4.ME.1050 Submission 5 12-Aug-25 16-Aug-25
RIX.4.ME.1055 Approval 7 18-Aug-25 25-Aug-25
Refurbishment of Floor 1 corridor in Existing Terminal Building 12 16-Jul-25 29-Jul-25
RIX.4.ME.1070 Submission 5 16-Jul-25 21-Jul-25
RIX.4.ME.1075 Approval 7 22-Jul-25 29-Jul-25
Miscellaneous Works 12 30-Jul-25 12-Aug-25
RIX.4.ME.1060 Submission 5 30-Jul-25 04-Aug-25
RIX.4.ME.1065 Approval 7 05-Aug-25 12-Aug-25
Second Section: Construction of External Evacuation Routes on the North and South sides 91 08-May-25 23-Aug-25
Construction of Evacuation Routes - Civil & Structural Steel works 26 25-Jul-25 23-Aug-25
RIX.4.ME.1080 Submission 5 25-Jul-25 30-Jul-25
RIX.4.ME.1085 Approval 21 31-Jul-25 23-Aug-25
Construction of Evacuation Routes - Finishes 26 08-May-25 06-Jun-25
RIX.4.ME.1100 Submission 5 08-May-25 13-May-25
RIX.4.ME.1105 Approval 21 14-May-25 06-Jun-25
Third Section: Terminal Expansion 83 08-May-25 14-Aug-25
Construction of Terminal work-Structure, Civil & Structural Steel works 26 16-Jul-25 14-Aug-25
RIX.4.ME.1110 Submission 5 16-Jul-25 21-Jul-25
RIX.4.ME.1115 Approval 21 22-Jul-25 14-Aug-25
Construction of Terminal work-Structure-Roofing 26 08-May-25 06-Jun-25
RIX.4.ME.1120 Submission 5 08-May-25 13-May-25

Actual Work Critical Remaining Work Page 3 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1125 Approval 21 14-May-25 06-Jun-25
Construction of Terminal work-Structure-Facade 26 08-May-25 06-Jun-25
RIX.4.ME.1130 Submission 5 08-May-25 13-May-25
RIX.4.ME.1135 Approval 21 14-May-25 06-Jun-25
Construction of Terminal work-Structure-MEP & ELV 26 10-May-25 09-Jun-25
RIX.4.ME.1140 Submission 5 10-May-25 15-May-25
RIX.4.ME.1145 Approval 21 16-May-25 09-Jun-25
Installation of Airport Systems 26 10-May-25 09-Jun-25
RIX.4.ME.1150 Submission 5 10-May-25 15-May-25
RIX.4.ME.1155 Approval 21 16-May-25 09-Jun-25
BHS and Hold Baggage Security Systems 26 10-May-25 09-Jun-25
RIX.4.ME.1160 Submission 5 10-May-25 15-May-25
RIX.4.ME.1165 Approval 21 16-May-25 09-Jun-25
Finishes Works 26 08-May-25 06-Jun-25
RIX.4.ME.1170 Submission 5 08-May-25 13-May-25
RIX.4.ME.1175 Approval 21 14-May-25 06-Jun-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1180 Submission 5 08-May-25 13-May-25
RIX.4.ME.1185 Approval 21 14-May-25 06-Jun-25
Fourth Section: Demolition of the temporary building and reconstruction of the non-Schengen 26 08-May-25 06-Jun-25
Demolition of Temporary Building 26 08-May-25 06-Jun-25
RIX.4.ME.1190 Submission 5 08-May-25 13-May-25
RIX.4.ME.1195 Approval 21 14-May-25 06-Jun-25
Refurbishment of non-Schengen arrivals in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1200 Submission 5 08-May-25 13-May-25
RIX.4.ME.1205 Approval 21 14-May-25 06-Jun-25
Fifth Section: Construction of part of the Terminal Baggage Handling Building 56 08-May-25 14-Jul-25
Construction of BHS building - Structure, Civil & Structural Steel works 26 08-May-25 06-Jun-25
RIX.4.ME.1210 Submission 5 08-May-25 13-May-25
RIX.4.ME.1215 Approval 21 14-May-25 06-Jun-25
Construction of BHS building-Roofing 26 08-May-25 06-Jun-25
RIX.4.ME.1220 Submission 5 08-May-25 13-May-25
RIX.4.ME.1225 Approval 21 14-May-25 06-Jun-25
Construction of BHS building - Facade 26 08-May-25 06-Jun-25
RIX.4.ME.1230 Submission 5 08-May-25 13-May-25
RIX.4.ME.1235 Approval 21 14-May-25 06-Jun-25
Installation of MEP & ELV 26 13-May-25 11-Jun-25
RIX.4.ME.1240 Submission 5 13-May-25 17-May-25
RIX.4.ME.1245 Approval 21 19-May-25 11-Jun-25
BHS and Hold Baggage Security Systems 26 13-May-25 11-Jun-25
RIX.4.ME.1250 Submission 5 13-May-25 17-May-25
RIX.4.ME.1255 Approval 21 19-May-25 11-Jun-25
Finishes Work 26 12-Jun-25 14-Jul-25
RIX.4.ME.1260 Submission 5 12-Jun-25 17-Jun-25
RIX.4.ME.1265 Approval 21 18-Jun-25 14-Jul-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1270 Submission 5 08-May-25 13-May-25
RIX.4.ME.1275 Approval 21 14-May-25 06-Jun-25
Sixth Section: Reconstruction of the Schengen arrivals area in sector E of the Terminal and BHS 26 08-May-25 06-Jun-25
Refurbishment of Schengen arrivals area in sector E in existing terminal 26 08-May-25 06-Jun-25

Actual Work Critical Remaining Work Page 4 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1280 Submission 5 08-May-25 13-May-25
RIX.4.ME.1285 Approval 21 14-May-25 06-Jun-25
Construction of Connection to New BHS Building 26 08-May-25 06-Jun-25
RIX.4.ME.1290 Submission 5 08-May-25 13-May-25
RIX.4.ME.1295 Approval 21 14-May-25 06-Jun-25
Seventh Section: Terminal F, 1st floor reconstruction to provide service facilities 26 08-May-25 06-Jun-25
Refurbishment of 1st floor reconstruction to provide service facilities in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1300 Submission 5 08-May-25 13-May-25
RIX.4.ME.1305 Approval 21 14-May-25 06-Jun-25
Refurbishment of Departure Baggage Delivery Corridor in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1310 Submission 5 08-May-25 13-May-25
RIX.4.ME.1315 Approval 21 14-May-25 06-Jun-25
Refurbishment of Schengen Passenger Arrival Corridor in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1320 Submission 5 08-May-25 13-May-25
RIX.4.ME.1325 Approval 21 14-May-25 06-Jun-25
Eighth Section: Construction of an access flyover 26 08-May-25 06-Jun-25
Construction of Flyover -Structure Civil & Structural Steel works 26 08-May-25 06-Jun-25
RIX.4.ME.1330 Submission 5 08-May-25 13-May-25
RIX.4.ME.1335 Approval 21 14-May-25 06-Jun-25
Installation of External Canopy 26 08-May-25 06-Jun-25
RIX.4.ME.1340 Submission 5 08-May-25 13-May-25
RIX.4.ME.1345 Approval 21 14-May-25 06-Jun-25
Road Finishing Work 26 08-May-25 06-Jun-25
RIX.4.ME.1350 Submission 5 08-May-25 13-May-25
RIX.4.ME.1355 Approval 21 14-May-25 06-Jun-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1360 Submission 5 08-May-25 13-May-25
RIX.4.ME.1365 Approval 21 14-May-25 06-Jun-25
Ninth Section: Areas with Utilities, Road Construction 26 08-May-25 06-Jun-25
Construction of Road Works 26 08-May-25 06-Jun-25
RIX.4.ME.1370 Submission 5 08-May-25 13-May-25
RIX.4.ME.1375 Approval 21 14-May-25 06-Jun-25
Construction of Utilities Works 26 08-May-25 06-Jun-25
RIX.4.ME.1380 Submission 5 08-May-25 13-May-25
RIX.4.ME.1385 Approval 21 14-May-25 06-Jun-25
Miscelleanous Work 26 08-May-25 06-Jun-25
RIX.4.ME.1390 Submission 5 08-May-25 13-May-25
RIX.4.ME.1395 Approval 21 14-May-25 06-Jun-25
Tenth Section: Construction of a multi-storey car parking 26 11-Jun-25 12-Jul-25
Construction of MLCP - Structure & Civil 26 11-Jun-25 12-Jul-25
RIX.4.ME.1400 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1405 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Structural Steel 26 11-Jun-25 12-Jul-25
RIX.4.ME.1410 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1415 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Roofing 26 11-Jun-25 12-Jul-25
RIX.4.ME.1420 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1425 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Facade 26 11-Jun-25 12-Jul-25
RIX.4.ME.1430 Submission 5 11-Jun-25 16-Jun-25

Actual Work Critical Remaining Work Page 5 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1435 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - MEP & ELV 26 11-Jun-25 12-Jul-25
RIX.4.ME.1440 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1445 Approval 21 17-Jun-25 12-Jul-25
Car Parking Systems 26 11-Jun-25 12-Jul-25
RIX.4.ME.1450 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1455 Approval 21 17-Jun-25 12-Jul-25
Finishes Works 26 11-Jun-25 12-Jul-25
RIX.4.ME.1460 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1465 Approval 21 17-Jun-25 12-Jul-25
Miscellaneous Works 26 11-Jun-25 12-Jul-25
RIX.4.ME.1470 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1475 Approval 21 17-Jun-25 12-Jul-25
Procurement 440 16-Jul-25 09-Apr-27
RIX.2600 Procurement Program reaches 80% of Contract Sum 0 10-Dec-26
Phase 1 Subcontractor Finalization 120 16-Jul-25 12-Jan-26
RIX.4.PW.SUB.1000 MLCP Sub contractor finalization (Piling, Precast, MEP, Solar etc.) 110 16-Jul-25 13-Dec-25
RIX.4.PW.SUB.1010 Viaduct Sub contractor finalization (Piling, Precast, MEP, Solar etc.) 120 16-Jul-25 12-Jan-26
RIX.4.PW.SUB.1015 Demolition Sub contractor finalization 15 16-Jul-25 01-Aug-25
RIX.4.PW.SUB.1020 Temporary Building, Chiller Building, Internal Corridor & Emergency Staircase, Sub contractor finalization 53 16-Jul-25 15-Sep-25
RIX.4.PW.SUB.1030 At Grade works Sub contractor finalization (MEP, Road works, Paving, Signages) 98 16-Jul-25 14-Nov-25
Phase II Subcontractor Finalization 365 16-Jul-25 10-Dec-26
RIX.2530 Terminal Building Sub contractor finalization (Piling) 40 16-Jul-25 30-Aug-25
RIX.2540 Terminal Building Sub contractor finalization (Shell & Core works) 100 01-Sep-25 27-Feb-26
RIX.2550 Terminal Building Sub contractor finalization (MEP, Airport systems, Finishes) 100 30-Oct-25 30-Apr-26
RIX.2560 Terminal Part A Sub contractor finalization - Balance miscellaneous packages 100 30-Apr-26 29-Aug-26
RIX.2570 Terminal Part B Sub contractor finalization - Balance miscellaneous packages 75 29-Aug-26 10-Dec-26
Phase III Subcontractor Finalization 75 10-Dec-26 09-Apr-27
RIX.2580 Existing Airport refurbishment Sub contractor finalization 75 10-Dec-26 09-Apr-27
Construction 1044 11-Jun-25 06-Mar-29

Work Permit 528 11-Jun-25 21-Jun-27


RIX.4.PW.WP.1000 Work Permit for Ramp Demolition and Temporary Building/Chiller Construction 10 16-Jul-25 26-Jul-25
RIX.4.PW.WP.1010 Work Permit for Internal Corridor 13 16-Jul-25 30-Jul-25
RIX.4.PW.WP.1020 At grade Work North - Work Permit 10 16-Jul-25 26-Jul-25
RIX.4.PW.WP.1030 At grade Work South - Work Permit 10 09-Jun-27 21-Jun-27
RIX.4.PW.WP.1040 Terminal Building Part A- Work Permit 13 16-Jul-25 30-Jul-25
RIX.4.PW.WP.1045 Terminal Building Part B & BHS- Unaffected 10 17-Jul-26 29-Jul-26
RIX.4.PW.WP.1060 MLCP - Work Permit 13 11-Jun-25 27-Jun-25
Phase-1 296 02-Aug-25 23-Sep-26
Stage-1 202 02-Aug-25 03-Jun-26
Demolition Works 49 02-Aug-25 29-Sep-25
Demolition of Existing Ramp 49 02-Aug-25 29-Sep-25
RIX.8.CP1.1020 Demolition of Existing Ramp 49 02-Aug-25 29-Sep-25
Construction of Temporary Building 165 15-Sep-25 03-Jun-26
Civil, Structural Steel & Roofing works 125 15-Sep-25 15-Apr-26
RIX.8.CP1.1030 Foundation Works 40 15-Sep-25 31-Oct-25
RIX.8.CP1.1040 Superstructure Works 40 21-Oct-25 16-Jan-26
RIX.8.CP1.1050 Structural Steel Works 40 19-Dec-25 14-Mar-26
RIX.8.CP1.1055 Erection of Roof 35 03-Mar-26 15-Apr-26

Actual Work Critical Remaining Work Page 6 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
MEP Works 45 14-Mar-26 11-May-26
RIX.8.CP1.1080 PHE (Storm Water, Rain Water Pipe, UG Services Dismantling) 15 14-Mar-26 01-Apr-26
RIX.8.CP1.1090 ELV (Fire/PA, CCTV, ACS, Network, UG Services Dismantling) 20 23-Mar-26 17-Apr-26
RIX.8.CP1.1370 HVAC (Split AC) 20 26-Mar-26 21-Apr-26
RIX.8.CP1.1730 Electrical (Panel, Cable Tray, Cabli ng, Earthing, LPS, Light Fixture, Point Power Wiring) 45 14-Mar-26 11-May-26
RIX.8.CP1.1760 Firefighting (Hydrant System, Extinguisher) 15 01-Apr-26 21-Apr-26
Elevators and Escalators 30 14-Mar-26 21-Apr-26
RIX.8.CP1.1100 Elevator Installation 30 14-Mar-26 21-Apr-26
RIX.8.CP1.1110 Escalator Installation 30 14-Mar-26 21-Apr-26
Facade Works 35 26-Mar-26 11-May-26
RIX.8.CP1.1070 Facade Erection 35 26-Mar-26 11-May-26
Finishes 30 21-Apr-26 28-May-26
RIX.8.CP1.1120 Finishing Work 30 21-Apr-26 28-May-26
Miscellaneous Works 20 11-May-26 03-Jun-26
RIX.8.CP1.1130 Miscellaneous Works 20 11-May-26 03-Jun-26
Refurbishment of Floor 1 corridor in existing terminal building 100 13-Sep-25 13-Mar-26
RIX.8.CP1.1140 Refurbishment of Floor 1 corridor 100 13-Sep-25 13-Mar-26
Emergency Staircase North & South 100 16-Sep-25 16-Mar-26
RIX.2590 Erection of Emergency Staircases 100 16-Sep-25 16-Mar-26
Chiller Building 145 30-Sep-25 25-May-26
Civil, Structural Steel & Roofing works 75 30-Sep-25 25-Feb-26
RIX.8.CP1.1150 Civil, Structural Steel & Roofing works 75 30-Sep-25 25-Feb-26
MEP Works 55 26-Feb-26 07-May-26
RIX.8.CP1.1170 PHE (Rain Water Pip e, Condensate Drain) 15 26-Feb-26 17-Mar-26
RIX.8.CP1.1180 ELV (Fire/PA, CCTV, ACS, Network, BMS) 30 07-Mar-26 14-Apr-26
RIX.8.CP1.1770 HVAC (Chiller, Piping, Insulation, Pumps, AHU, Air Distribution System) 45 11-Mar-26 07-May-26
RIX.8.CP1.1780 Electrical (Panel, Cable Tray, Cabli ng, Earthing, LPS, Light Fixture, Point Power Wiring) 45 26-Feb-26 23-Apr-26
RIX.8.CP1.1790 Firefighting (Extinguisher) 7 17-Mar-26 25-Mar-26
Facade Works 35 17-Mar-26 29-Apr-26
RIX.8.CP1.1160 Facade Works 35 17-Mar-26 29-Apr-26
Finishes 35 04-Apr-26 19-May-26
RIX.8.CP1.1200 Building Finishes Work 35 04-Apr-26 19-May-26
Miscellaneous works 20 29-Apr-26 25-May-26
RIX.8.CP1.1210 Miscellaneous Works 20 29-Apr-26 25-May-26
Stage-2 81 16-Mar-26 25-Jun-26
Construction of External Evacuation Routes 81 16-Mar-26 25-Jun-26
North Side of Existing Terminal 53 16-Mar-26 21-May-26
Civil Structural Steel & MEP works 43 16-Mar-26 09-May-26
RIX.8.CP1.1220 Civil Works - North Evacuation Route 28 16-Mar-26 20-Apr-26
RIX.8.CP1.1230 MEP works (Lighting, Wiring, ACS) 15 20-Apr-26 09-May-26
Finishes 25 20-Apr-26 21-May-26
RIX.8.CP1.1250 Finishes Work 25 20-Apr-26 21-May-26
South Side of Existing Terminal 53 20-Apr-26 25-Jun-26
Civil Structural Steel & MEP works 43 20-Apr-26 11-Jun-26
RIX.8.CP1.1260 Civil Works - South Evacuation Route 28 20-Apr-26 25-May-26
RIX.8.CP1.1270 MEP works (Lighting, Wiring, ACS) 15 25-May-26 11-Jun-26
Finishes 25 25-May-26 25-Jun-26
RIX.8.CP1.1290 Finishes Works 25 25-May-26 25-Jun-26
Stage-8 262 06-Sep-25 18-Sep-26
Construction of the Viaduct 262 06-Sep-25 18-Sep-26
North Part - Viaduct 262 06-Sep-25 18-Sep-26

Actual Work Critical Remaining Work Page 7 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Foundation Works 65 06-Sep-25 13-Dec-25
RIX.8.CP1.1300 Piling & Demolition Work 40 06-Sep-25 23-Oct-25
RIX.8.CP1.1310 Pile Cap 40 07-Oct-25 13-Dec-25
Superstructure Works 157 15-Dec-25 03-Aug-26
RIX.8.CP1.1320 Pier Construction 60 15-Dec-25 07-Apr-26
RIX.8.CP1.1330 Pier Top Constructio n 50 28-Feb-26 30-Apr-26
RIX.8.CP1.1335 Beam & Slab works, Retaining Wall works 30 18-Apr-26 26-May-26
RIX.8.CP1.1340 Viaduct Construction 65 08-May-26 25-Jul-26
RIX.8.CP1.1350 Miscellaneous works 10 22-Jul-26 03-Aug-26
Electrical & Plumbing Works 175 15-Dec-25 24-Aug-26
RIX.8.CP1.1830 Existing Services Dismantling Works 30 15-Dec-25 27-Feb-26
RIX.8.CP1.1840 Installation of Drainage Pipes 20 08-Jul-26 31-Jul-26
RIX.8.CP1.1850 HDPE Containment, Power Cabling, Fibre Optic Cabling, Network Cabling 20 08-Jul-26 31-Jul-26
RIX.8.CP1.1860 Installation of Feeder Piller, Street Light Poles, JB 15 20-Jul-26 06-Aug-26
RIX.8.CP1.1870 Installation of Light Fixures, Cameras, Speakers 15 06-Aug-26 24-Aug-26
RIX.8.CP1.1880 Installation of Escalator 30 26-May-26 02-Jul-26
Finishing Works 22 24-Aug-26 18-Sep-26
RIX.8.CP1.1360 Viaduct Road Pavement & Finishes works 15 24-Aug-26 10-Sep-26
RIX.8.CP1.1380 Miscellaneous works 7 10-Sep-26 18-Sep-26
Stage-9 199 30-Oct-25 28-Aug-26
Areas with External Engineering Utility Networks 199 30-Oct-25 28-Aug-26
Construction of External Services 199 30-Oct-25 28-Aug-26
RIX.8.CP1.1750 Dismantling/Removal of Existing Services 25 30-Oct-25 29-Dec-25
RIX.8.CP1.1890 Temporary Diversion of Utilities 25 03-Dec-25 04-Feb-26
RIX.8.CP1.1895 Re-Installation of Perimeter Intrusion detection system 25 13-Jan-26 06-Mar-26
RIX.8.CP1.1900 Commissioning of Temporary diverted Utilities 25 17-Feb-26 24-Mar-26
RIX.8.CP1.1910 Installation of Fire Pipes 40 12-Mar-26 30-Apr-26
RIX.8.CP1.1920 Installation of Sewer Drain & Storm Water Drain , Installa tion of Duct Pipe/HT Cables 40 07-Apr-26 26-May-26
RIX.8.CP1.1930 Installation of Hot Water Pipes, Cold Water Supply Pipes, Irrigation pipes, Duct Pipe/LT Cables, Cable Pit 40 30-Apr-26 18-Jun-26
RIX.8.CP1.1940 Installation of HDPE Duct Pipe & Laying of FO Cable, Cu Cable, CAT 6 Cable 40 26-May-26 14-Jul-26
RIX.8.CP1.1950 Installation of Hydrant, Hose reel Cabinet 10 03-Jun-26 15-Jun-26
RIX.8.CP1.1960 Installation of Street light Poles, Feeder Piller, DB, Outdoor Racks, Cameras, Display Panel 40 11-Jun-26 30-Jul-26
RIX.8.CP1.1970 Installation of Boom Barrier, UVSS, Parking Management Machines 25 30-Jul-26 28-Aug-26
Road Construction 188 15-Nov-25 25-Aug-26
RIX.8.CP1.DIV Road and Passanger Diversion 2 29-Apr-26 02-May-26
North Side - Road 188 15-Nov-25 25-Aug-26
Main Road 91 15-Nov-25 29-Apr-26
RIX.8.CP1.1440 Excavation 21 15-Nov-25 09-Jan-26
RIX.8.CP1.1450 Subgrade Preparation 21 10-Dec-25 02-Feb-26
RIX.8.CP1.1460 Frost-resistant layer 21 08-Jan-26 25-Feb-26
RIX.8.CP1.1470 Mineral material sack 0/56 N-II 21 31-Jan-26 11-Mar-26
RIX.8.CP1.1480 Mineral material sack 0/45 N-I 21 24-Feb-26 23-Mar-26
RIX.8.CP1.1490 Asphalt concrete AC32base 70/100 S-II 21 10-Mar-26 04-Apr-26
RIX.8.CP1.1500 Asphalt concrete AC22bin 70/100 S-II 21 21-Mar-26 17-Apr-26
RIX.8.CP1.1510 Asphalt concrete AC16surf 50/70 S-I (Top Layer) 21 02-Apr-26 29-Apr-26
Paver Road below Viaduct (Centre portion) 96 09-Jan-26 01-Jun-26
RIX.8.CP1.1520 Excavation 25 09-Jan-26 05-Mar-26
RIX.8.CP1.1530 Subgrade Preparation 25 13-Feb-26 23-Mar-26
RIX.8.CP1.1540 Frost resistant layer 25 11-Mar-26 11-Apr-26

Actual Work Critical Remaining Work Page 8 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP1.1550 Mineral mat. sack 0/45 21 28-Mar-26 24-Apr-26
RIX.8.CP1.1555 Levelling layer 21 17-Apr-26 14-May-26
RIX.8.CP1.1560 concrete paving stone (Top layer) 21 07-May-26 01-Jun-26
At grade Pedestrian Road 111 05-Mar-26 20-Jul-26
RIX.8.CP1.1570 Excavation 21 05-Mar-26 30-Mar-26
RIX.8.CP1.1575 Subgrade Preparation 21 23-Mar-26 18-Apr-26
RIX.8.CP1.1580 Frost resistant layer 21 11-Apr-26 08-May-26
RIX.8.CP1.1585 Mineral material sack 0/56 21 29-Apr-26 26-May-26
RIX.8.CP1.1590 Mineral material sack 0/45 21 19-May-26 12-Jun-26
RIX.8.CP1.1595 Levelling layer 21 05-Jun-26 02-Jul-26
RIX.8.CP1.1599 Concrete paving stone (Top layer) 21 25-Jun-26 20-Jul-26
Road Finishes Work along with Footpath Works 31 20-Jul-26 25-Aug-26
RIX.8.CP1.2000 Road finishes work 31 20-Jul-26 25-Aug-26
Utilities Work 31 12-Mar-26 20-Apr-26
RIX.8.CP1.2010 Installation of Lighting, Fire fighting and Plumbing pipes 31 12-Mar-26 20-Apr-26
Stage-10 266 06-Sep-25 23-Sep-26
Construction of Multi Level Car Parking 266 06-Sep-25 23-Sep-26
Civil & Structure 206 06-Sep-25 15-Jul-26
Foundation Works 65 06-Sep-25 13-Dec-25
RIX.8.CP1.2250 Piling Work 30 06-Sep-25 11-Oct-25
RIX.8.CP1.2260 Excavation 10 07-Oct-25 17-Oct-25
RIX.8.CP1.2270 Pile Cap 30 13-Oct-25 02-Dec-25
RIX.8.CP1.2280 Backfilling 10 21-Nov-25 13-Dec-25
Floor 1 52 15-Dec-25 26-Mar-26
RIX.8.CP1.2290 Grade Slab 7 15-Dec-25 05-Jan-26
RIX.8.CP1.2300 Structural steel Columns & beam,staircases 21 06-Jan-26 23-Feb-26
RIX.8.CP1.2310 Laying Decksheet 14 22-Jan-26 23-Feb-26
RIX.8.CP1.2320 Laying of Reinforcement 21 07-Feb-26 14-Mar-26
RIX.8.CP1.2330 Laying of Concrete Floor 1 Slab 10 14-Mar-26 26-Mar-26
Floor 2 45 26-Mar-26 21-May-26
RIX.8.CP1.2340 Structural steel Columns & beam,staircases 21 26-Mar-26 21-Apr-26
RIX.8.CP1.2350 Laying Decksheet 14 04-Apr-26 22-Apr-26
RIX.8.CP1.2360 Laying of Reinforcement 21 14-Apr-26 09-May-26
RIX.8.CP1.2370 Laying of Concrete Floor 2 Slab 10 09-May-26 21-May-26
Floor 3 45 21-May-26 15-Jul-26
RIX.8.CP1.2380 Structural steel Columns & beam,staircases 21 21-May-26 15-Jun-26
RIX.8.CP1.2390 Laying Decksheet 14 29-May-26 15-Jun-26
RIX.8.CP1.2400 Laying of Reinforcement 21 06-Jun-26 03-Jul-26
RIX.8.CP1.2410 Laying of Concrete Floor 3 Slab 10 03-Jul-26 15-Jul-26
Facade & Roof Works 50 15-Jul-26 11-Sep-26
RIX.8.CP1.1600 Roof Works 45 15-Jul-26 05-Sep-26
RIX.8.CP1.1610 Facade Works 30 07-Aug-26 11-Sep-26
Installation of MEP & ELV 31 15-Jul-26 20-Aug-26
RIX.8.CP1.1620 PHE 21 27-Jul-26 20-Aug-26
RIX.8.CP1.1630 ELV 21 21-Jul-26 14-Aug-26
RIX.8.CP1.1800 HVAC 20 23-Jul-26 15-Aug-26
RIX.8.CP1.1810 Electrical 30 15-Jul-26 19-Aug-26
RIX.8.CP1.1820 Firefighting 20 27-Jul-26 19-Aug-26
Finishes Works 25 19-Aug-26 17-Sep-26
RIX.8.CP1.1640 Finishes Works 25 19-Aug-26 17-Sep-26

Actual Work Critical Remaining Work Page 9 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Miscellaneous Works 5 17-Sep-26 23-Sep-26
RIX.8.CP1.1650 Miscellaneous Works 5 17-Sep-26 23-Sep-26
Phase-2 846 15-Aug-25 14-Sep-28
RIX.8.CP2.TO Terminal Opening 0 10-May-28
Stage-3 - Construction of New Terminal 834 15-Aug-25 31-Aug-28
Construction of New Terminal Part - A 396 15-Aug-25 17-Mar-27
Structure Works 396 15-Aug-25 17-Mar-27
Foundation Works 155 15-Aug-25 20-Apr-26
RIX.8.CP2.2090 Piling Work 30 15-Aug-25 18-Sep-25
RIX.8.CP2.2100 Excavation 45 19-Sep-25 22-Nov-25
RIX.8.CP2.2110 Pile Cap 50 24-Nov-25 13-Mar-26
RIX.8.CP2.2120 Backfilling 20 13-Mar-26 08-Apr-26
RIX.8.CP2.2340 Substructure Waterproofing 10 08-Apr-26 20-Apr-26
Floor 1 112 20-Apr-26 02-Sep-26
RIX.8.CP2.2130 Grade Slab 45 20-Apr-26 13-Jun-26
RIX.8.CP2.2140 Structural steel, Columns, beam & Staircases 45 13-Jun-26 07-Aug-26
RIX.8.CP2.2150 Laying Decksheet 10 07-Aug-26 19-Aug-26
RIX.8.CP2.2160 Laying of Reinforcement 10 19-Aug-26 31-Aug-26
RIX.8.CP2.2165 Laying of Concrete Floor 1 Slab 2 31-Aug-26 02-Sep-26
Floor 2 31 02-Sep-26 09-Oct-26
RIX.8.CP2.2170 Structural steel, Columns, beam & Staircases 20 02-Sep-26 26-Sep-26
RIX.8.CP2.2180 Laying Decksheet 5 26-Sep-26 02-Oct-26
RIX.8.CP2.2190 Laying of Reinforcement 5 02-Oct-26 08-Oct-26
RIX.8.CP2.2200 Laying of Concrete Floor 2 Slab 1 08-Oct-26 09-Oct-26
Floor 3 67 09-Oct-26 30-Jan-27
RIX.8.CP2.2210 Structural steel, Columns, beam & Staircases 45 09-Oct-26 17-Dec-26
RIX.8.CP2.2220 Laying Decksheet 10 17-Dec-26 09-Jan-27
RIX.8.CP2.2230 Laying of Reinforcement 10 09-Jan-27 27-Jan-27
RIX.8.CP2.2240 Laying of Concrete Floor 3 Slab 2 27-Jan-27 30-Jan-27
Floor 4 31 30-Jan-27 17-Mar-27
RIX.8.CP2.2250 Structural steel, Columns, beam & Staircases 20 30-Jan-27 04-Mar-27
RIX.8.CP2.2260 Laying Decksheet 5 04-Mar-27 10-Mar-27
RIX.8.CP2.2270 Laying of Reinforcement 5 10-Mar-27 16-Mar-27
RIX.8.CP2.2280 Laying of Concrete Floor 4 Slab 1 16-Mar-27 17-Mar-27
Construction of New Terminal Part - B Unaffected 377 29-Jul-26 06-Dec-27
Structure Works 377 29-Jul-26 06-Dec-27
Foundation Works 136 29-Jul-26 13-Feb-27
RIX.8.CP2.1000 Piling Work 30 29-Jul-26 02-Sep-26
RIX.8.CP2.1010 Excavation 31 02-Sep-26 09-Oct-26
RIX.8.CP2.1020 Pile Cap 45 09-Oct-26 17-Dec-26
RIX.8.CP2.1030 Backfilling 20 17-Dec-26 27-Jan-27
RIX.8.CP2.2350 Substructure Waterproofing 10 27-Jan-27 13-Feb-27
Floor 1 112 13-Feb-27 06-Jul-27
RIX.8.CP2.1040 Grade Slab 45 13-Feb-27 14-Apr-27
RIX.8.CP2.1050 Structural steel, Columns, beam & Staircases 45 14-Apr-27 08-Jun-27
RIX.8.CP2.1060 Laying Decksheet 10 08-Jun-27 19-Jun-27
RIX.8.CP2.1070 Laying of Reinforcement 10 19-Jun-27 03-Jul-27
RIX.8.CP2.1075 Laying of Concrete Floor 1 Slab 2 03-Jul-27 06-Jul-27
Floor 2 31 06-Jul-27 11-Aug-27
RIX.8.CP2.1080 Structural steel, Columns, beam & Staircases 20 06-Jul-27 29-Jul-27

Actual Work Critical Remaining Work Page 10 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1090 Laying Decksheet 5 29-Jul-27 04-Aug-27
RIX.8.CP2.1100 Laying of Reinforcement 5 04-Aug-27 10-Aug-27
RIX.8.CP2.1110 Laying of Concrete Floor 2 Slab 1 10-Aug-27 11-Aug-27
Floor 3 67 11-Aug-27 29-Oct-27
RIX.8.CP2.1120 Structural steel, Columns, beam & Staircases 45 11-Aug-27 04-Oct-27
RIX.8.CP2.1130 Laying Decksheet 10 04-Oct-27 15-Oct-27
RIX.8.CP2.1140 Laying of Reinforcement 10 15-Oct-27 27-Oct-27
RIX.8.CP2.1150 Laying of Concrete Floor 3 Slab 2 27-Oct-27 29-Oct-27
Floor 4 31 29-Oct-27 06-Dec-27
RIX.8.CP2.1160 Structural steel, Columns, beam & Staircases 20 29-Oct-27 23-Nov-27
RIX.8.CP2.1170 Laying Decksheet 5 23-Nov-27 29-Nov-27
RIX.8.CP2.1180 Laying of Reinforcement 5 29-Nov-27 04-Dec-27
RIX.8.CP2.1190 Laying of Concrete Floor 4 Slab 1 04-Dec-27 06-Dec-27
Permanent Utility Diversion through the Precast Tunnel 100 29-Jul-26 07-Dec-26
RIX.8.CP1.1420 Utility Diversion - UG Precast Tunnel, Storm Water Drain, Sewer, Water Supply, Hydrant & Hot Water System 100 29-Jul-26 07-Dec-26
Construction of New Terminal Part - B Affected 377 07-Dec-26 05-Apr-28
Structure Works 377 07-Dec-26 05-Apr-28
Foundation Works 136 07-Dec-26 19-Jun-27
RIX.8.CP2.3020 Piling Work 30 07-Dec-26 03-Feb-27
RIX.8.CP2.3030 Excavation 31 03-Feb-27 19-Mar-27
RIX.8.CP2.3040 Pile Cap 45 19-Mar-27 15-May-27
RIX.8.CP2.3050 Backfilling 20 15-May-27 08-Jun-27
RIX.8.CP2.3220 Substructure Waterproofing 10 08-Jun-27 19-Jun-27
Floor 1 112 19-Jun-27 01-Nov-27
RIX.8.CP2.3060 Grade Slab 45 19-Jun-27 13-Aug-27
RIX.8.CP2.3070 Structural steel, Columns, beam & Staircases 45 13-Aug-27 06-Oct-27
RIX.8.CP2.3080 Laying Decksheet 10 06-Oct-27 18-Oct-27
RIX.8.CP2.3090 Laying of Reinforcement 10 18-Oct-27 29-Oct-27
RIX.8.CP2.3230 Laying of Concrete Floor 1 Slab 2 29-Oct-27 01-Nov-27
Floor 2 31 01-Nov-27 08-Dec-27
RIX.8.CP2.3100 Structural steel, Columns, beam & Staircases 20 01-Nov-27 25-Nov-27
RIX.8.CP2.3110 Laying Decksheet 5 25-Nov-27 01-Dec-27
RIX.8.CP2.3120 Laying of Reinforcement 5 01-Dec-27 07-Dec-27
RIX.8.CP2.3130 Laying of Concrete Floor 2 Slab 1 07-Dec-27 08-Dec-27
Floor 3 67 08-Dec-27 29-Feb-28
RIX.8.CP2.3140 Structural steel, Columns, beam & Staircases 45 08-Dec-27 03-Feb-28
RIX.8.CP2.3150 Laying Decksheet 10 03-Feb-28 15-Feb-28
RIX.8.CP2.3160 Laying of Reinforcement 10 15-Feb-28 26-Feb-28
RIX.8.CP2.3170 Laying of Concrete Floor 3 Slab 2 26-Feb-28 29-Feb-28
Floor 4 31 29-Feb-28 05-Apr-28
RIX.8.CP2.3180 Structural steel, Columns, beam & Staircases 20 29-Feb-28 23-Mar-28
RIX.8.CP2.3190 Laying Decksheet 5 23-Mar-28 29-Mar-28
RIX.8.CP2.3200 Laying of Reinforcement 5 29-Mar-28 04-Apr-28
RIX.8.CP2.3210 Laying of Concrete Floor 4 Slab 1 04-Apr-28 05-Apr-28
Structural Steel Roof Erection 133 29-Feb-28 10-Aug-28
Roof Truss Erection Works 60 29-Feb-28 13-May-28
RIX.8.CP2.1220 Roof Truss Erection Works 60 29-Feb-28 13-May-28
Periphery Columns 73 13-May-28 10-Aug-28
RIX.8.CP2.2500 Base Plate Installation for Slanting Columns 13 13-May-28 29-May-28
RIX.8.CP2.2510 Erection of Slanting Columns 20 29-May-28 21-Jun-28

Actual Work Critical Remaining Work Page 11 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.2520 Peripheral Cantilever Roof Installation 20 21-Jun-28 18-Jul-28
RIX.8.CP2.2530 Connection to Main Roof 20 18-Jul-28 10-Aug-28
Roofing 60 29-Feb-28 13-May-28
Roof Sheeting Work 60 29-Feb-28 13-May-28
RIX.8.CP2.1230 Roof Sheeting Work 60 29-Feb-28 13-May-28
Roof Cladding Works 45 29-Feb-28 24-Apr-28
RIX.8.CP2.1240 Roof Cladding Works 45 29-Feb-28 24-Apr-28
Facade & Skylight Works 60 29-May-28 10-Aug-28
Framing 60 29-May-28 10-Aug-28
RIX.8.CP2.1200 Framing Work 60 29-May-28 10-Aug-28
Glazing Work 60 29-May-28 10-Aug-28
RIX.8.CP2.1210 Glazing Work 60 29-May-28 10-Aug-28
RIX.8.CP2.1215 Installation of Sky Lighting 45 29-May-28 24-Jul-28
MEP & Electronic Communication Systems 512 02-Sep-26 27-Jun-28
Electrical Work 428 09-Oct-26 21-Apr-28
RIX.8.CP2.1250 First fix works (Conduit fixing, Wiring, Earthing, Concealed Items) 90 09-Oct-26 08-Mar-27
RIX.8.CP2.1260 Second Fix Works (Cable Tray, Cabling, Above False Ceiling Fixtures) 120 21-Oct-26 26-Apr-27
RIX.8.CP2.1270 Substation 2050 works (TR, HT/LT Panels, RMU, Bus Duct, HT/LT Cables) 60 01-Nov-27 15-Jan-28
RIX.8.CP2.1280 Special Systems (Lighting Automation, UPS) 60 09-Feb-28 21-Apr-28
RIX.8.CP2.1285 Final Fix Works (Installation of light Fixtures, Switches & Other Exposed Items) 60 09-Feb-28 21-Apr-28
Plumbing Works 141 02-Sep-26 02-Apr-27
RIX.8.CP2.1290 Cold & Hot Water Piping Work 120 02-Sep-26 06-Mar-27
RIX.8.CP2.1300 Sewerage Pipe Works 90 21-Oct-26 19-Mar-27
RIX.8.CP2.1310 Siphonic Roof Drainage / Condensate Drain Piping Works 90 02-Nov-26 02-Apr-27
RIX.8.CP2.1320 Installation of Sanitary fixtures 45 16-Jan-27 24-Mar-27
RIX.8.CP2.1330 Pumps & Panels 60 06-Nov-26 26-Feb-27
HVAC Works 100 02-Sep-26 03-Feb-27
RIX.8.CP2.1340 Chilled water pipeline 60 02-Sep-26 19-Nov-26
RIX.8.CP2.1350 Ducting Works 75 14-Sep-26 07-Jan-27
RIX.8.CP2.1360 Insulation Works 75 26-Sep-26 25-Jan-27
RIX.8.CP2.1370 Installation of AHUs,VAV ,fans etc 60 08-Oct-26 16-Jan-27
RIX.8.CP2.1380 Chillers & chilled water pumps 60 20-Oct-26 03-Feb-27
ELV (FAS, PA, ACS, CCTV, IIDS, SAS, Monitor, PRM, PFMS, ASSD, Master Clock, BMS, ECS Active Passive) 471 21-Oct-26 27-Jun-28
RIX.8.CP2.1390 Conduit, Concealed Items 60 21-Oct-26 04-Feb-27
RIX.8.CP2.1400 Cable Tray, Race Ways, Network, Communication Cables 90 26-Apr-27 13-Aug-27
RIX.8.CP2.1410 Rack, Panels, Switches, Deductors, Sensors, Modules, Speakers, Controller, Reader, IO Face Plate, Master clock 45 11-Apr-28 07-Jun-28
RIX.8.CP2.1411 Software, Server, Monitor Installation 15 07-Jun-28 27-Jun-28
Fire Fighting Works 448 21-Oct-26 29-May-28
RIX.8.CP2.1440 Piping Works (Sprinkler and Hydrant) 120 21-Oct-26 26-Apr-27
RIX.8.CP2.1445 Pumproom Works (Technical Room) 45 06-Nov-26 30-Jan-27
RIX.8.CP2.1450 Clean Agent System Works 90 09-Feb-28 29-May-28
RIX.8.CP2.1460 Installation of Sprinklers, Landing Valve, Fire Hose Reels and Hose Cabinets 60 09-Feb-28 21-Apr-28
Elevator 60 19-Jun-28 31-Aug-28
RIX.8.CP2.3010 Installation of Elevators 60 19-Jun-28 31-Aug-28
Escalator 60 19-Jun-28 31-Aug-28
RIX.8.CP2.3000 Installation of Escalators 30 19-Jun-28 27-Jul-28
RIX.8.CP2.3260 Installation of Escalators in Existing Terminal Building 30 27-Jul-28 31-Aug-28
Finishes Works 337 06-Jul-27 17-Aug-28
Floor 1 160 06-Jul-27 15-Jan-28
RIX.8.CP2.1610 Plastering Works 20 06-Jul-27 29-Jul-27

Actual Work Critical Remaining Work Page 12 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1620 Flooring Works 20 29-Jul-27 21-Aug-27
RIX.8.CP2.1630 Partition Works 20 21-Aug-27 14-Sep-27
RIX.8.CP2.1640 Wall Finishes Works 20 14-Sep-27 08-Oct-27
RIX.8.CP2.1650 Ceiling works 20 08-Oct-27 01-Nov-27
RIX.8.CP2.1660 Signages Works 20 01-Nov-27 25-Nov-27
RIX.8.CP2.1670 Rest room finishes 20 25-Nov-27 18-Dec-27
RIX.8.CP2.1680 Furniture & Fixtures 20 18-Dec-27 15-Jan-28
Floor 2 160 11-Aug-27 21-Feb-28
RIX.8.CP2.1690 Plastering Works 20 11-Aug-27 03-Sep-27
RIX.8.CP2.1700 Flooring Works 20 03-Sep-27 28-Sep-27
RIX.8.CP2.1710 Partition Works 20 28-Sep-27 21-Oct-27
RIX.8.CP2.1720 Wall Finishes Works 20 21-Oct-27 13-Nov-27
RIX.8.CP2.1730 Ceiling works 20 13-Nov-27 08-Dec-27
RIX.8.CP2.1740 Signages Works 20 08-Dec-27 05-Jan-28
RIX.8.CP2.1750 Rest room finishes 20 05-Jan-28 28-Jan-28
RIX.8.CP2.1760 Furniture & Fixtures 20 28-Jan-28 21-Feb-28
Floor 3 160 29-Oct-27 13-May-28
RIX.8.CP2.1770 Plastering Works 20 29-Oct-27 23-Nov-27
RIX.8.CP2.1780 Flooring Works 20 23-Nov-27 16-Dec-27
RIX.8.CP2.1790 Partition Works 20 16-Dec-27 13-Jan-28
RIX.8.CP2.1800 Wall Finishes Works 20 13-Jan-28 05-Feb-28
RIX.8.CP2.1810 Ceiling works 20 05-Feb-28 29-Feb-28
RIX.8.CP2.1820 Signages Works 20 29-Feb-28 23-Mar-28
RIX.8.CP2.1830 Rest room finishes 20 23-Mar-28 18-Apr-28
RIX.8.CP2.1840 Furniture & Fixtures 20 18-Apr-28 13-May-28
Floor 4 208 06-Dec-27 17-Aug-28
RIX.8.CP2.1850 Plastering Works 21 06-Dec-27 04-Jan-28
RIX.8.CP2.1860 Flooring Works 21 04-Jan-28 28-Jan-28
RIX.8.CP2.1870 Partition Works 21 28-Jan-28 22-Feb-28
RIX.8.CP2.1880 Wall Finishes Works 21 22-Feb-28 17-Mar-28
RIX.8.CP2.1890 Ceiling works 21 17-Mar-28 11-Apr-28
RIX.8.CP2.1900 Signages Works 21 24-Jul-28 17-Aug-28
Reconstruction of Existing Terminal 240 29-Jul-27 16-May-28
Reconstruction of Custom Room 105 29-Jul-27 01-Dec-27
RIX.8.CP2.1910 Reconstruction of Custom Room 105 29-Jul-27 01-Dec-27
Reconstruction of L&F Room 90 01-Dec-27 20-Mar-28
RIX.8.CP2.1920 Reconstruction of L&F Room 90 01-Dec-27 20-Mar-28
Installation of Elevator and Escalators 45 20-Mar-28 16-May-28
RIX.8.CP2.1930 Installation of Elevators 45 20-Mar-28 16-May-28
RIX.8.CP2.1940 Installation of Escalators 45 20-Mar-28 16-May-28
MEP Works 40 20-Mar-28 10-May-28
RIX.8.CP2.1945 MEP Works 40 20-Mar-28 10-May-28
Stage-5 BHS Building 609 29-Jul-26 14-Sep-28
Construction of New BHS Building 609 29-Jul-26 14-Sep-28
Structure 269 29-Jul-26 30-Jul-27
Foundation Works 135 29-Jul-26 11-Feb-27
RIX.8.CP2.1950 Piling Work 30 29-Jul-26 02-Sep-26
RIX.8.CP2.1955 Excavation 30 02-Sep-26 08-Oct-26
RIX.8.CP2.1957 Construction of BHS - Tunnel 23 08-Oct-26 06-Nov-26
RIX.8.CP2.1960 Pile Cap 45 08-Oct-26 15-Dec-26

Actual Work Critical Remaining Work Page 13 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1965 Backfilling 30 15-Dec-26 11-Feb-27
Floor 1 82 11-Feb-27 28-May-27
RIX.8.CP2.1970 Grade Slab Work 30 11-Feb-27 24-Mar-27
RIX.8.CP2.1980 Structural steel, Columns, beam & Staircases 30 24-Mar-27 30-Apr-27
RIX.8.CP2.1990 Laying of deck sheet 10 30-Apr-27 14-May-27
RIX.8.CP2.2000 Laying of Reinforcement 10 14-May-27 26-May-27
RIX.8.CP2.2010 Laying of Concrete Floor 1 Slab 2 26-May-27 28-May-27
Floor 2 52 28-May-27 30-Jul-27
RIX.8.CP2.2360 Structural steel, Columns, beam & Staircases 30 28-May-27 05-Jul-27
RIX.8.CP2.2370 Laying of deck sheet 10 05-Jul-27 16-Jul-27
RIX.8.CP2.2380 Laying of Reinforcement 10 16-Jul-27 28-Jul-27
RIX.8.CP2.2390 Laying of Concrete Floor 2 Slab 2 28-Jul-27 30-Jul-27
Roofing 60 30-Jul-27 09-Oct-27
RIX.8.CP2.2030 Erection of Roofing Work 60 30-Jul-27 09-Oct-27
Installation of MEP & ELV 252 06-Nov-26 18-Oct-27
RIX.8.CP2.1281 DG - DRUPS Standby Power System (Incl HSD Yard, Exhaust Strut, Piping, Insulation, Bus Duct, Panel, Fuel Piping, 120
Tank)06-Nov-26 12-May-27
RIX.8.CP2.2040 PHE 30 30-Jul-27 03-Sep-27
RIX.8.CP2.2050 ELV 45 11-Aug-27 04-Oct-27
RIX.8.CP2.2060 HVAC 40 23-Aug-27 09-Oct-27
RIX.8.CP2.2290 Electrical 40 31-Aug-27 18-Oct-27
RIX.8.CP2.2300 Firefighting 30 07-Sep-27 13-Oct-27
Installation of BHS 392 28-May-27 14-Sep-28
Sequence 1 120 28-May-27 19-Oct-27
RIX.8.CP2.2061 Dismantling of Existing Structures 10 28-May-27 09-Jun-27
RIX.8.CP2.2071 Mechanical erection 20 05-Jul-27 28-Jul-27
RIX.8.CP2.2081 Equipment Installstion 20 28-Jul-27 20-Aug-27
RIX.8.CP2.2091 Electrical Cabling Work 20 20-Aug-27 13-Sep-27
RIX.8.CP2.2101 Unitory/Overall Test 25 13-Sep-27 13-Oct-27
RIX.8.CP2.2111 Preliminary Reception Test 5 13-Oct-27 19-Oct-27
Sequence 2 185 05-Jul-27 12-Feb-28
RIX.8.CP2.3280 Mechanical erection 90 05-Jul-27 19-Oct-27
RIX.8.CP2.3300 Electrical Cabling Work 90 22-Jul-27 05-Nov-27
RIX.8.CP2.3305 Screening Machine Installation 7 28-Oct-27 05-Nov-27
RIX.8.CP2.3310 Unitory/Overall Test 75 05-Nov-27 07-Feb-28
RIX.8.CP2.3320 Preliminary Reception Test 5 07-Feb-28 12-Feb-28
Sequence 3 26 12-Feb-28 14-Mar-28
RIX.2310 Dismantling 7 12-Feb-28 21-Feb-28
RIX.2320 Mechanical erection 7 21-Feb-28 29-Feb-28
RIX.2330 Unitory/Overall Test 7 29-Feb-28 08-Mar-28
RIX.2340 Preliminary Reception Test 5 08-Mar-28 14-Mar-28
Sequence 4 44 14-Mar-28 09-May-28
RIX.2350 Dismantling 7 14-Mar-28 22-Mar-28
RIX.2360 Mechanical Erection 15 22-Mar-28 08-Apr-28
RIX.2370 Electrical Cabling Work 15 22-Mar-28 08-Apr-28
RIX.2380 Screening Machine Installation 7 08-Apr-28 19-Apr-28
RIX.2390 Unitory Overall Test 10 19-Apr-28 02-May-28
RIX.2400 Preliminary Reception Test 5 02-May-28 09-May-28
Sequence 5 33 09-May-28 16-Jun-28
RIX.2410 Dismantling 7 09-May-28 17-May-28

Actual Work Critical Remaining Work Page 14 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.2420 Mechanical Erection 7 17-May-28 25-May-28
RIX.2430 Electrical Cabling Work 7 25-May-28 02-Jun-28
RIX.2440 Unitory Overall Test 7 02-Jun-28 10-Jun-28
RIX.2450 Preliminary Reception Test 5 10-Jun-28 16-Jun-28
Sequence 6 44 16-Jun-28 10-Aug-28
RIX.2460 Dismantling 7 16-Jun-28 27-Jun-28
RIX.2470 Mechanical Erection 15 27-Jun-28 15-Jul-28
RIX.2480 Electrical Cabling Work 15 27-Jun-28 15-Jul-28
RIX.2490 Screening Machine Installation 7 15-Jul-28 24-Jul-28
RIX.2500 Unitory Overall Test 10 24-Jul-28 04-Aug-28
RIX.2510 Preliminary Reception Test 5 04-Aug-28 10-Aug-28
System Performance & Integration 30 10-Aug-28 14-Sep-28
RIX.2520 System Performance & Integration 30 10-Aug-28 14-Sep-28
Facade 45 09-Oct-27 02-Dec-27
RIX.8.CP2.2020 Erection of Facade 45 09-Oct-27 02-Dec-27
Finishes Works 31 01-Nov-27 08-Dec-27
RIX.8.CP2.2070 Finishes Works 31 01-Nov-27 08-Dec-27
Miscellaneous Work 15 01-Dec-27 18-Dec-27
RIX.8.CP2.2080 Miscellaneous Works 15 01-Dec-27 18-Dec-27
South Part - Viaduct 456 24-Oct-25 10-Aug-27
Foundation Works 65 24-Oct-25 12-Mar-26
RIX.8.CP1.1660 Piling Work 40 24-Oct-25 23-Jan-26
RIX.8.CP1.1670 Pile Cap 40 15-Dec-25 12-Mar-26
Superstructure Works 310 12-Mar-26 05-May-27
RIX.8.CP1.1680 Pier Construction 75 12-Mar-26 12-Jun-26
RIX.8.CP1.1690 Pier Top Constructio n 60 12-Jun-26 24-Aug-26
RIX.8.CP1.1695 Beam & Slab works, Retaining Wall works 30 24-Aug-26 29-Sep-26
RIX.8.CP1.1700 Viaduct Construction 75 29-Sep-26 28-Jan-27
RIX.8.CP1.1705 Vertical connection Building and Foot bridge - Structure works 30 28-Jan-27 15-Mar-27
RIX.8.CP1.1710 External Canopy Works 30 15-Mar-27 21-Apr-27
RIX.8.CP1.1715 Miscellaneous works 10 21-Apr-27 05-May-27
Electrical & Plumbing Works 90 15-Mar-27 05-Jul-27
RIX.8.CP1.2420 Existing Services Dismantling Works 30 15-Mar-27 21-Apr-27
RIX.8.CP1.2430 Installation of Drainage Pipes 30 21-Apr-27 28-May-27
RIX.8.CP1.2440 HDPE Containment, Power Cabling, Fibre Optic Cabling, Network Cabling 30 21-Apr-27 28-May-27
RIX.8.CP1.2450 Installation of Feeder Piller, Street Light Poles, JB 15 28-May-27 15-Jun-27
RIX.8.CP1.2460 Installation of Light Fixures, Cameras, Speakers 15 15-Jun-27 05-Jul-27
Finishing Works 31 05-Jul-27 10-Aug-27
RIX.8.CP1.1720 Viaduct Road Pavement & Finishes works 21 05-Jul-27 29-Jul-27
RIX.8.CP1.1740 Miscellaneous works 10 29-Jul-27 10-Aug-27
South Side - Road 329 21-Jun-27 26-Jul-28
Main Road 189 21-Jun-27 05-Feb-28
RIX.8.CP1.2040 Excavation 25 21-Jun-27 22-Jul-27
RIX.8.CP1.2050 Subgrade Preparation 25 22-Jul-27 20-Aug-27
RIX.8.CP1.2060 Frost-resistant layer 25 20-Aug-27 18-Sep-27
RIX.8.CP1.2070 Mineral material sack 0/56 N-II 21 18-Sep-27 14-Oct-27
RIX.8.CP1.2080 Mineral material sack 0/45 N-I 21 14-Oct-27 08-Nov-27
RIX.8.CP1.2090 Asphalt concrete AC32base 70/100 S-II 21 08-Nov-27 03-Dec-27
RIX.8.CP1.2100 Asphalt concrete AC22bin 70/100 S-II 21 03-Dec-27 30-Dec-27
RIX.8.CP1.2110 Asphalt concrete AC16surf 50/70 S-I (Top Layer) 30 30-Dec-27 05-Feb-28

Actual Work Critical Remaining Work Page 15 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Paver Road below Viaduct (Centre portion) 138 18-Sep-27 04-Mar-28
RIX.8.CP1.2120 Excavation 25 18-Sep-27 19-Oct-27
RIX.8.CP1.2130 Subgrade Preparation 25 19-Oct-27 17-Nov-27
RIX.8.CP1.2140 Frost resistant layer 25 17-Nov-27 17-Dec-27
RIX.8.CP1.2150 Mineral mat. sack 0/45 21 17-Dec-27 15-Jan-28
RIX.8.CP1.2160 Levelling layer 21 15-Jan-28 09-Feb-28
RIX.8.CP1.2170 concrete paving stone (Top layer) 21 09-Feb-28 04-Mar-28
At grade Pedestrian Road 159 17-Nov-27 31-May-28
RIX.8.CP1.2180 Excavation 25 17-Nov-27 17-Dec-27
RIX.8.CP1.2190 Subgrade Preparation 25 17-Dec-27 20-Jan-28
RIX.8.CP1.2200 Frost resistant layer 25 20-Jan-28 18-Feb-28
RIX.8.CP1.2210 Mineral material sack 0/56 21 18-Feb-28 14-Mar-28
RIX.8.CP1.2220 Mineral material sack 0/45 21 14-Mar-28 07-Apr-28
RIX.8.CP1.2230 Levelling layer 21 07-Apr-28 06-May-28
RIX.8.CP1.2240 Concrete paving stone (Top layer) 21 06-May-28 31-May-28
Road Finishes Work along with Footpath Works 45 31-May-28 26-Jul-28
RIX.8.CP1.2020 Road finishes work 45 31-May-28 26-Jul-28
Utilities Work 31 01-Sep-27 08-Oct-27
RIX.8.CP1.2030 Installation of Lighting, Fire fighting and Plumbing pipes 31 01-Sep-27 08-Oct-27
Phase-3 250 10-May-28 06-Mar-29
Stage-4 165 21-Aug-28 06-Mar-29
RIX.8.CP3.1000 Refurbishment of Area D South - Dismantling of Existing non-Shengen Arrival Corridor 15 21-Aug-28 07-Sep-28
RIX.8.CP3.1010 Refurbishment of Area D South - Refurbishment of Existing non-Shengen Arrival Corridor 60 07-Sep-28 16-Nov-28
RIX.8.CP3.1020 Refurbishment of Area D South - BHS Area 60 16-Nov-28 30-Jan-29
RIX.8.CP3.1180 Integration with Existing Facilities 30 30-Jan-29 06-Mar-29
Stage-6 190 10-May-28 22-Dec-28
RIX.8.CP3.1030 Refurbishment of Area E Central - Temporary Shengen Arrival Corridor, 1st Portion of New Passport Control 15 10-May-28 27-May-28
RIX.8.CP3.1040 Refurbishment of Area E Central - New Shengen Arrival Corridor 15 28-Jun-28 17-Jul-28
RIX.8.CP3.1190 Integration with Existing Facilities 30 17-Jul-28 21-Aug-28
Refurbishment of Area E Central - Connection with Existing BHS 105 21-Aug-28 22-Dec-28
RIX.8.CP3.1050 Step-1 : Installation of all componants of New BHS 10 21-Aug-28 01-Sep-28
RIX.8.CP3.1070 Step-2: Install a temporary transit pier connected to the EDS3 10 01-Sep-28 13-Sep-28
RIX.8.CP3.1080 Step-3: Shifting EDS1 from existing no-Schengen transits to the new position 10 13-Sep-28 25-Sep-28
RIX.8.CP3.1090 Step-4: T & C of EDS-1 5 25-Sep-28 30-Sep-28
RIX.8.CP3.1100 Step-5: Connection of The first Check-in island and one of the new no-Sch transit lines to EDS1 10 30-Sep-28 12-Oct-28
RIX.8.CP3.1110 Step-6: Connection of The second Check-in island and the other new no-Sch transit line to EDS1 10 12-Oct-28 24-Oct-28
RIX.8.CP3.1120 Step-7: Move the EDS2 from existing to the new position 10 24-Oct-28 04-Nov-28
RIX.8.CP3.1130 Step-8: T & C of EDS-2 5 04-Nov-28 10-Nov-28
RIX.8.CP3.1140 Step-9: Connection of Three Check-in islands and no-Sch transit lines to EDS1 and EDS2 10 10-Nov-28 23-Nov-28
RIX.8.CP3.1150 Step-10: Connection of all the check-in islands and no-Sch transit lines to EDS1 and EDS2 10 23-Nov-28 05-Dec-28
RIX.8.CP3.1160 Step-11: Move the EDS3 from existing to the new position 10 05-Dec-28 16-Dec-28
RIX.8.CP3.1170 Step-12: T & C of EDS-3 5 16-Dec-28 22-Dec-28
Stage-7 110 27-May-28 06-Oct-28
RIX.8.CP3.1060 Refurbishment of Area F North - 2nd Portion of Passport Control 80 27-May-28 01-Sep-28
RIX.8.CP3.1200 Integration with Existing Facilities 30 01-Sep-28 06-Oct-28
Testing & Commissioning 838 03-Jun-26 23-Apr-29

Phase - 1 118 03-Jun-26 22-Oct-26


Stage 1 56 03-Jun-26 10-Aug-26
Standalone Testing 15 03-Jun-26 20-Jun-26

Actual Work Critical Remaining Work Page 16 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1105 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 03-Jun-26 15-Jun-26
RIX.1115 PHE/FPS (Hydro Test) 7 03-Jun-26 11-Jun-26
RIX.1125 HVAC (Pipe Hydro Test, Air Leakage Test, Chemical Flushing) 15 03-Jun-26 20-Jun-26
RIX.1145 ELV (Cont/Inspection Test) 7 03-Jun-26 11-Jun-26
RIX.1155 Elevator & Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 7 03-Jun-26 11-Jun-26
Power & Water Availability 2 29-Jun-26 01-Jul-26
RIX.1107 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 29-Jun-26 30-Jun-26
RIX.1109 Water Availability (Tapping from near by existing header) 1 30-Jun-26 01-Jul-26
Precommissioning 20 30-Jun-26 23-Jul-26
RIX.1110 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 20 30-Jun-26 23-Jul-26
RIX.1130 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 2 01-Jul-26 03-Jul-26
RIX.1160 HVAC (Powering of Eqpts, No Load test, Eqpt Test, Wild Air Cooling) 15 30-Jun-26 17-Jul-26
RIX.1190 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 15 30-Jun-26 17-Jul-26
RIX.1220 Elevator & Escalator (Panel Charging, Slow Speed, Visual Inspection) 7 30-Jun-26 08-Jul-26
Commissioning 32 03-Jul-26 10-Aug-26
RIX.1120 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing) 15 23-Jul-26 10-Aug-26
RIX.1250 PHE/Fire Protection (Integration with existing system, Physical Check) 3 03-Jul-26 08-Jul-26
RIX.1280 HVAC (Water & Air Balancing, Independent System Commissioning) 15 17-Jul-26 04-Aug-26
RIX.1310 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 15 17-Jul-26 04-Aug-26
RIX.1340 Elevator & Escalator (Full Load Test, Normal Speed Operatio n) 7 08-Jul-26 16-Jul-26
Stage 2 38 11-Jun-26 28-Jul-26
Standalone Testing 10 11-Jun-26 25-Jun-26
RIX.1450 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 11-Jun-26 25-Jun-26
RIX.1480 ELV (Cont/Inspection Test) 7 11-Jun-26 19-Jun-26
Power & Water Availability 1 07-Jul-26 08-Jul-26
RIX.1440 Permanent Power 1 07-Jul-26 08-Jul-26
Precommissioning 10 08-Jul-26 20-Jul-26
RIX.1420 Electrical (DB Meggering, Power Stability Check) 10 08-Jul-26 20-Jul-26
RIX.1530 ELV (Network-uplink, Controller Powerup, Field Devices Check) 7 08-Jul-26 16-Jul-26
Commissioning 10 16-Jul-26 28-Jul-26
RIX.1430 Electrical (DB Meggering, Power Stability Check) 7 20-Jul-26 28-Jul-26
RIX.1570 ELV (Network-uplink, Controller Powerup, Field Devices Check) 7 16-Jul-26 24-Jul-26
Stage 8 46 02-Jul-26 25-Aug-26
Standalone Testing 10 02-Jul-26 14-Jul-26
RIX.1780 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 02-Jul-26 14-Jul-26
RIX.1810 ELV (Cont/Inspection Test) 10 02-Jul-26 14-Jul-26
RIX.1820 Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 7 02-Jul-26 10-Jul-26
Power & Water Availability 1 31-Jul-26 01-Aug-26
RIX.1770 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 31-Jul-26 01-Aug-26
Precommissioning 10 01-Aug-26 13-Aug-26
RIX.1760 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 10 01-Aug-26 13-Aug-26
RIX.1860 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 10 01-Aug-26 13-Aug-26
RIX.1870 Escalator (Panel Charging, Slow Speed, Visual Inspection) 7 01-Aug-26 10-Aug-26
Commissioning 13 10-Aug-26 25-Aug-26
RIX.1880 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 10 13-Aug-26 25-Aug-26
RIX.1910 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 10 13-Aug-26 25-Aug-26
RIX.1920 Escalator (Full Load Test, Normal Speed Operation) 7 10-Aug-26 18-Aug-26
Stage 9 39 25-Aug-26 10-Oct-26
Standalone Testing 10 25-Aug-26 05-Sep-26
RIX.1950 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 25-Aug-26 05-Sep-26

Actual Work Critical Remaining Work Page 17 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1960 PHE/FPS (Hydro Test) 10 25-Aug-26 05-Sep-26
RIX.1970 HVAC (Pipe Hydro Test, Chemical Flushing) 10 25-Aug-26 05-Sep-26
RIX.1980 ELV (Cont/Inspection Test) 10 25-Aug-26 05-Sep-26
Power & Water Availability 2 14-Sep-26 16-Sep-26
RIX.1940 Permanent Power (Taping from Existing Power Substation 204A) 1 14-Sep-26 15-Sep-26
RIX.2000 Water Availability (Tapping from near by existing header) 1 15-Sep-26 16-Sep-26
Precommissioning 11 15-Sep-26 29-Sep-26
RIX.1930 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 10 15-Sep-26 28-Sep-26
RIX.2010 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 10 16-Sep-26 29-Sep-26
RIX.2030 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 10 15-Sep-26 28-Sep-26
Commissioning 11 28-Sep-26 10-Oct-26
RIX.2050 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 10 28-Sep-26 09-Oct-26
RIX.2060 PHE/Fire Protection (Integration with existing system, Physical Check) 10 29-Sep-26 10-Oct-26
RIX.2080 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 10 28-Sep-26 09-Oct-26
Stage 10 46 28-Aug-26 22-Oct-26
RIX.1375 Standalone Testing 3 28-Aug-26 01-Sep-26
RIX.1377 Temporary/Permanent Power & Water Availability 1 01-Sep-26 03-Sep-26
RIX.1380 Precommissioning 12 23-Sep-26 08-Oct-26
RIX.1390 Commissioning 12 08-Oct-26 22-Oct-26
Phase - 2 314 18-Dec-27 05-Jan-29
Stage 3 199 10-May-28 05-Jan-29
Standalone Testing 108 10-May-28 16-Sep-28
RIX.1610 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 30 10-May-28 14-Jun-28
RIX.1620 PHE/FPS (Hydro Test) 7 29-May-28 06-Jun-28
RIX.1630 HVAC (Pipe Hydro Test, Air Leakage Test, Chemical Flushing) 15 10-May-28 27-May-28
RIX.1640 ELV (Cont/Inspection Test) 60 27-Jun-28 06-Sep-28
RIX.1650 Elevator & Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 14 31-Aug-28 16-Sep-28
Power & Water Availability 2 04-Jul-28 06-Jul-28
RIX.1600 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 04-Jul-28 05-Jul-28
RIX.1660 Water Availability (Tapping from near by existing header) 1 05-Jul-28 06-Jul-28
Precommissioning 98 05-Jul-28 28-Oct-28
RIX.1580 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 45 05-Jul-28 28-Aug-28
RIX.1670 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 15 06-Jul-28 25-Jul-28
RIX.1680 HVAC (Powering of Eqpts, No Load test, Eqpt Test, Wild Air Cooling) 30 05-Jul-28 10-Aug-28
RIX.1690 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 45 06-Sep-28 28-Oct-28
RIX.1700 Elevator & Escalator (Panel Charging, Slow Speed, Visual Inspection) 14 16-Sep-28 03-Oct-28
Commissioning 137 25-Jul-28 05-Jan-29
RIX.1710 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 55 28-Aug-28 31-Oct-28
RIX.1720 PHE/Fire Protection (Integration with existing system, Physical Check) 30 25-Jul-28 29-Aug-28
RIX.1730 HVAC (Water & Air Balancing, Independent System Commissioning) 54 10-Aug-28 12-Oct-28
RIX.1740 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 55 28-Oct-28 05-Jan-29
RIX.1750 Elevator & Escalator (Full Load Test, Normal Speed Operatio n) 14 03-Oct-28 19-Oct-28
Stage 5 261 18-Dec-27 31-Oct-28
RIX.1225 Standalone Testing 3 18-Dec-27 22-Dec-27
RIX.1227 Temporary/Permanent Power & Water Availability 1 22-Dec-27 27-Dec-27
RIX.1230 Precommissioning 20 14-Sep-28 07-Oct-28
RIX.1240 Commissioning 20 07-Oct-28 31-Oct-28
Phase - 3 135 06-Oct-28 17-Mar-29
Stage 4 10 06-Mar-29 17-Mar-29

Actual Work Critical Remaining Work Page 18 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1195 Testing & Commissoining 10 06-Mar-29 17-Mar-29
Stage 6 10 22-Dec-28 06-Jan-29
RIX.1255 Testing & Commissoining 10 22-Dec-28 06-Jan-29
Stage 7 10 06-Oct-28 18-Oct-28
RIX.1285 Testing & Commissoining 10 06-Oct-28 18-Oct-28
Final Integration 90 05-Jan-29 23-Apr-29
RIX.2090 HVAC System Integrated with BMS 90 05-Jan-29 23-Apr-29
RIX.2100 HVAC-CPM Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2110 Energy/BTU meter integration wth BMS if any 90 05-Jan-29 23-Apr-29
RIX.2120 VFD Panel Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2130 Pumps Integration with the CPM & BMS 90 05-Jan-29 23-Apr-29
RIX.2140 AHU/Fans & Other HVAC Equipments with BMS 90 05-Jan-29 23-Apr-29
RIX.2150 Fire Alarm System Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2160 Elevator & Escalator integration with Fire Alarm 90 05-Jan-29 23-Apr-29
RIX.2170 Elevator & Escalator integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2180 Fire Damper integration with BMS & Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2190 PA System integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2200 Clean Agent system integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2210 ASSD Integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2220 Lighting Management System integration with the Fire & BMS 90 05-Jan-29 23-Apr-29
RIX.2230 CCTV integration with the BHS 90 05-Jan-29 23-Apr-29
RIX.2240 BHS integration with PA, Fire Alarm 90 05-Jan-29 23-Apr-29
RIX.2250 Access Control System Integration with Fire Alarm, Elevator, Doors, Intrusion Detection 90 05-Jan-29 23-Apr-29
RIX.2260 BHS Integrated with FIDS 90 05-Jan-29 23-Apr-29
RIX.2270 ICT/ECS system integration with Existing Server/Switch 90 05-Jan-29 23-Apr-29
RIX.2280 PFMS Integration with Existing Server 90 05-Jan-29 23-Apr-29
RIX.2290 BHS Integration with AODB, DCS & CDM 90 05-Jan-29 23-Apr-29
RIX.2300 Overall System Performance of Integration 90 05-Jan-29 23-Apr-29
Reporting 1035 02-Aug-25 17-Apr-29
RIX.5.RP.1000 Submission of Monthly Progress Report - 1 1 02-Aug-25 02-Aug-25
RIX.5.RP.1010 Submission of Monthly Progress Report - 2 1 06-Sep-25 08-Sep-25
RIX.5.RP.1020 Submission of Monthly Progress Report - 3 1 13-Oct-25 13-Oct-25
RIX.5.RP.1030 Submission of Monthly Progress Report - 4 1 08-Dec-25 09-Dec-25
RIX.5.RP.1040 Submission of Monthly Progress Report - 5 1 20-Feb-26 21-Feb-26
RIX.5.RP.1050 Submission of Monthly Progress Report - 6 1 01-Apr-26 02-Apr-26
RIX.5.RP.1060 Submission of Monthly Progress Report - 7 1 13-May-26 14-May-26
RIX.5.RP.1070 Submission of Monthly Progress Report - 8 1 15-Jun-26 15-Jun-26
RIX.5.RP.1080 Submission of Monthly Progress Report - 9 1 22-Jul-26 23-Jul-26
RIX.5.RP.1090 Submission of Monthly Progress Report - 10 1 27-Aug-26 28-Aug-26
RIX.5.RP.1100 Submission of Monthly Progress Report - 11 1 03-Oct-26 03-Oct-26
RIX.5.RP.1110 Submission of Monthly Progress Report - 12 1 10-Nov-26 11-Nov-26
RIX.5.RP.1120 Submission of Monthly Progress Report - 13 1 11-Jan-27 12-Jan-27
RIX.5.RP.1130 Submission of Monthly Progress Report - 14 1 04-Mar-27 04-Mar-27
RIX.5.RP.1140 Submission of Monthly Progress Report - 15 1 09-Apr-27 10-Apr-27
RIX.5.RP.1150 Submission of Monthly Progress Report - 16 1 19-May-27 20-May-27
RIX.5.RP.1160 Submission of Monthly Progress Report - 17 1 25-Jun-27 25-Jun-27
RIX.5.RP.1170 Submission of Monthly Progress Report - 18 1 30-Jul-27 31-Jul-27
RIX.5.RP.1180 Submission of Monthly Progress Report - 19 1 06-Sep-27 07-Sep-27

Actual Work Critical Remaining Work Page 19 of 20 10-Feb-25


Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.5.RP.1190 Submission of Monthly Progress Report - 20 1 09-Oct-27 09-Oct-27
RIX.5.RP.1200 Submission of Monthly Progress Report - 21 1 13-Nov-27 15-Nov-27
RIX.5.RP.1210 Submission of Monthly Progress Report - 22 1 21-Dec-27 22-Dec-27
RIX.5.RP.1220 Submission of Monthly Progress Report - 23 1 31-Jan-28 31-Jan-28
RIX.5.RP.1230 Submission of Monthly Progress Report - 24 1 04-Mar-28 06-Mar-28
RIX.5.RP.1240 Submission of Monthly Progress Report - 25 1 11-Apr-28 12-Apr-28
RIX.5.RP.1250 Submission of Monthly Progress Report - 26 1 22-May-28 22-May-28
RIX.5.RP.1260 Submission of Monthly Progress Report - 27 1 28-Jun-28 29-Jun-28
RIX.5.RP.1270 Submission of Monthly Progress Report - 28 1 04-Aug-28 05-Aug-28
RIX.5.RP.1280 Submission of Monthly Progress Report - 29 1 08-Sep-28 08-Sep-28
RIX.5.RP.1290 Submission of Monthly Progress Report - 30 1 13-Oct-28 14-Oct-28
RIX.5.RP.1300 Submission of Monthly Progress Report - 31 1 21-Nov-28 22-Nov-28
RIX.5.RP.1310 Submission of Monthly Progress Report - 32 1 27-Dec-28 27-Dec-28
RIX.5.RP.1320 Submission of Monthly Progress Report - 33 1 01-Feb-29 02-Feb-29
RIX.5.RP.1330 Submission of Monthly Progress Report - 34 1 09-Mar-29 10-Mar-29
RIX.5.RP.1340 Submission of Monthly Progress Report - 35 1 17-Apr-29 17-Apr-29
Handing Over / Employers Taking Over 822 16-Jul-26 17-May-29
RIX.10.HO.1000 Handing Over - Stage 1 10 16-Jul-26 28-Jul-26
RIX.10.HO.1010 Handing Over - Stage 2 15 24-Jul-26 11-Aug-26
RIX.10.HO.1020 Handing Over - Stage 3 15 05-Jan-29 23-Jan-29
RIX.10.HO.1030 Handing Over - Stage 4 15 17-Mar-29 06-Apr-29
RIX.10.HO.1040 Handing Over - Stage 5 15 31-Oct-28 17-Nov-28
RIX.10.HO.1050 Handing Over - Stage 6 15 06-Jan-29 24-Jan-29
RIX.10.HO.1060 Handing Over - Stage 7 15 18-Oct-28 04-Nov-28
RIX.10.HO.1070 Handing Over - Stage 8 15 10-Aug-27 27-Aug-27
RIX.10.HO.1080 Handing Over - Stage 9 15 09-Oct-26 27-Oct-26
RIX.10.HO.1090 Handing Over - Stage 10 15 22-Oct-26 12-Nov-26
RIX.10.HO.1100 Final Handover 19 23-Apr-29 17-May-29
Start of Warranty Period 779 28-Jul-26 06-Apr-29
RIX.11.WP.1000 Start of Warrenty Period - Stage 1 0 28-Jul-26
RIX.11.WP.1010 Start of Warrenty Period - Stage 2 0 11-Aug-26
RIX.11.WP.1020 Start of Warrenty Period - Stage 3 0 23-Jan-29
RIX.11.WP.1030 Start of Warrenty Period - Stage 4 0 06-Apr-29
RIX.11.WP.1040 Start of Warrenty Period - Stage 5 0 17-Nov-28
RIX.11.WP.1050 Start of Warrenty Period - Stage 6 0 24-Jan-29
RIX.11.WP.1060 Start of Warrenty Period - Stage 7 0 04-Nov-28
RIX.11.WP.1070 Start of Warrenty Period - Stage 8 0 27-Aug-27
RIX.11.WP.1080 Start of Warrenty Period - Stage 9 0 27-Oct-26
RIX.11.WP.1090 Start of Warrenty Period - Stage 10 0 12-Nov-26
Demobilization 0 17-May-29 17-May-29
RIX.12.DM.1000 Site Demobilization 0 17-May-29

Actual Work Critical Remaining Work Page 20 of 20 10-Feb-25