Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Construction Works For Stage 6 Of Riga Airport Terminal Expansion Project 1178 10-Mar-25 17-May-29
Contractual Milestones 1074 16-Jul-25 17-May-29
RIX.1000 Project Start 0 16-Jul-25
RIX.1010 Project Handover 0 17-May-29
Construction Milestones-Finish Dates 1054 01-Jul-25 06-Apr-29
RIX.2.MS.1001 Specification for technological equipments - Annexure 8 Provided by RIX 0 01-Jul-25
RIX.2.MS.1002 First Section: Demolition of existing access ramps, construction of a temporary building 0 28-Jul-26
RIX.2.MS.1010 Second Section: Construction of external evacuation routes on the North and South sides of the existing terminal 0 11-Aug-26
RIX.2.MS.1020 Third Section: Terminal expansio n 0 23-Jan-29
RIX.2.MS.1030 Fourth Section: Demolition of the temporary building and reconstruction of the non-Schengen arrivals area in Sector D 0 06-Apr-29
RIX.2.MS.1040 Fifth Section: Construction of part of the Terminal Baggage Handling Buil ding 0 17-Nov-28
RIX.2.MS.1050 Sixth Section: Reconstruction of the Schengen arrivals area in sector E of the Terminal and connectio n to BHS 0 24-Jan-29
RIX.2.MS.1060 Seventh Section: Terminal F, 1st floor reconstruction to provide service facilities 0 04-Nov-28
RIX.2.MS.1070 Eighth Section: Construction of an access flyover 0 27-Aug-27
RIX.2.MS.1080 Ninth Section: Areas with utilities, road construction 0 27-Oct-26
RIX.2.MS.1090 Tenth Section: Construction of a multi-storey car parking 0 12-Nov-26
Employer’s deliverables 788 02-May-25 21-Mar-28
RIX.1.CE.1000 Notification of Contract Award 1 02-May-25 02-May-25
RIX.1.CE.1010 Contract Signing 12 02-Jul-25 15-Jul-25
RIX.1.CE.1015 Project Commencement Date 0 16-Jul-25
RIX.1.CE.1020 Approval of Permits for Phase-I (Stage I, II,VIII, IX, X) 20 16-Jul-25 07-Aug-25
RIX.1.CE.1025 Time to Access the Site 1 06-Sep-25 06-Sep-25
RIX.1.CE.1030 Approval of Permits for Terminal Building Part-A (Stage III) 30 08-Sep-25 13-Oct-25
RIX.1.CE.1040 Approval of Permits for Phase-II (Stage III, V) 30 14-Oct-25 04-Dec-25
RIX.1.CE.1050 Approval of Permits for Phase-III (Stage IV, VI, VII) 30 19-Oct-27 24-Nov-27
RIX.1.CE.1060 Notice to Commence for Stage-IV 1 19-Oct-27 20-Oct-27
RIX.1.CE.1070 Notice to Commence for Stage-VI 1 19-Oct-27 20-Oct-27
RIX.1.CE.1080 Notice to Commence for Stage-VII 1 20-Mar-28 21-Mar-28
RIX.1.CE.1090 Payment of Advance payment for Phase-I (Stage I, II,VIII, IX, X) 60 28-May-25 07-Aug-25
RIX.1.CE.1100 Payment of Advance payment for Phase-II (Stage III, V) 60 05-Feb-26 30-Apr-26
RIX.1.CE.1110 Payment of Advance payment for Phase-III (Stage IV, VI, VII) 60 11-Nov-27 26-Jan-28
Preliminary Works 724 10-Mar-25 11-Nov-27
KPIL Company Registration 149 10-Mar-25 05-Sep-25
RIX.3.PL.1005 Registration of branch a foriegh merchant in commercial register 2 10-Mar-25 11-Mar-25
RIX.3.PL.1007 Employment agreement with construction specialist registered with tax authority 40 16-Jul-25 30-Aug-25
RIX.3.PL.1010 Registration in register of construction merchants of republic of latvia 5 01-Sep-25 05-Sep-25
Policy Document Submissions 680 03-May-25 11-Nov-27
RIX.3.PL.1000 Submission of Performance Guarantee Security 28 03-May-25 05-Jun-25
RIX.3.PL.1020 Submission of Advance Payment Guarantee for Phase-I (Stage I, II,VIII, IX, X) 20 03-May-25 27-May-25
RIX.3.PL.1030 Submission of Advance Payment Guarantee for Phase-II (Stage III, V) 20 06-Jun-25 01-Jul-25
RIX.3.PL.1040 Submission of Advance Payment Guarantee for Phase-III (Stage IV, VI, VII) 20 19-Oct-27 11-Nov-27
RIX.3.PL.1050 Submission of CAR insurance 6 01-Sep-25 06-Sep-25
RIX.3.PL.1060 Submission of CTA insurance(Professional Indemnity & Civil lia bility) 6 01-Sep-25 06-Sep-25
RIX.3.PL.1070 Submission of Permit for Terminal Buildin g Part-A (Stage III) 8 16-Jul-25 24-Jul-25
RIX.3.PL.1080 Submission of Permit for Phase-II (Stage III, V) 8 02-Jul-25 10-Jul-25
RIX.3.PL.1090 Submission of Permit for Phase-III (Stage IV, VI, VII) 8 09-Oct-27 19-Oct-27
Preparatory Works 328 12-Mar-25 13-Jun-26
Actual Work Critical Remaining Work Page 1 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Setting up of Temporary Facilities & Staff 328 12-Mar-25 13-Jun-26
RIX.4.PW.1000 Key Personnel Registration (PM, Dy.PM, Plnn & Proj Cntrol Mgr, A/c & Admin Head, EHS Head) 100 12-Mar-25 12-Jul-25
RIX.4.PW.1005 Key Personal Registration for Balance People 20 14-Jul-25 05-Aug-25
RIX.4.PW.1010 Setting-up of Project office 40 06-Sep-25 24-Oct-25
RIX.4.PW.1020 Setting -up of HSE Cabin 40 24-Oct-25 26-Jan-26
RIX.4.PW.1030 Setting -up of QAQC Lab 50 26-Jan-26 14-Apr-26
RIX.4.PW.1040 Setting -up of store 50 14-Apr-26 13-Jun-26
Survey Works 0 06-Sep-25 06-Sep-25
RIX.4.SW.1050 Geotechnical Investigation, Topographical survey ,Dilapidatio n survey and submissio n 0 06-Sep-25
Appontment of Engineering Consultant 1 03-May-25 03-May-25
RIX.1020 Appointment of Engineering Consultant 1 03-May-25 03-May-25
Engineering 62 06-May-25 18-Jul-25
Detailed Design 62 06-May-25 18-Jul-25
Architecture 31 06-May-25 10-Jun-25
RIX.4.PW.DD.1000 MLCP - Detailed Design - Submission 30 06-May-25 09-Jun-25
RIX.4.PW.DD.1005 MLCP - Detailed Design - Approval 1 10-Jun-25 10-Jun-25
RIX.4.PW.DD.1010 Viaduct - Detailed Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1015 Viaduct - Detailed Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1020 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1025 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1030 At grade Work - Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1035 At grade Work - Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1040 Terminal Building Design - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1045 Terminal Building Design - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1070 Existing Terminal Buildin g - Refurbishment Work - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1075 Existing Terminal Buildin g - Refurbishment Work - Approval 1 07-May-25 07-May-25
RIX.4.PW.DD.1080 BHS Building - Submission 1 06-May-25 06-May-25
RIX.4.PW.DD.1185 BHS Building - Approval 1 07-May-25 07-May-25
Structural 60 08-May-25 18-Jul-25
RIX.4.PW.DD.1085 MLCP - Detailed Design - Submission 30 11-Jun-25 17-Jul-25
RIX.4.PW.DD.1095 MLCP - Detailed Design - Approval 1 18-Jul-25 18-Jul-25
RIX.4.PW.DD.1105 Viaduct - Detailed Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1115 Viaduct - Detailed Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1125 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1135 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1145 At grade Work - Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1155 At grade Work - Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1165 Terminal Building Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1175 Terminal Building Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1225 Existing Terminal Buildin g - Refurbishment Work - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1235 Existing Terminal Buildin g - Refurbishment Work - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1345 BHS Building - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1355 BHS Building - Approval 1 09-May-25 09-May-25
MEP 31 08-May-25 12-Jun-25
RIX.4.PW.DD.1245 MLCP - Detailed Design - Submission 1 11-Jun-25 11-Jun-25
RIX.4.PW.DD.1255 MLCP - Detailed Design - Approval 1 12-Jun-25 12-Jun-25
RIX.4.PW.DD.1265 Viaduct - Detailed Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1275 Viaduct - Detailed Design - Approval 1 09-May-25 09-May-25
Actual Work Critical Remaining Work Page 2 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.PW.DD.1285 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1295 Detailed Drawing for Temporary Build ing, Chiller & Internal Corridor - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1305 At grade Work - Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1315 At grade Work - Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1325 Terminal Building Design - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1335 Terminal Building Design - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1385 Existing Terminal Buildin g - Refurbishment Work - Submission 1 08-May-25 08-May-25
RIX.4.PW.DD.1395 Existing Terminal Buildin g - Refurbishment Work - Approval 1 09-May-25 09-May-25
RIX.4.PW.DD.1405 BHS Building - Submission 1 10-May-25 10-May-25
RIX.4.PW.DD.1415 BHS Building - Approval 1 12-May-25 12-May-25
Method Statements 92 08-May-25 25-Aug-25
First Section: Demolition of existing access ramps, construction of a temporary building & Chiller H 35 16-Jul-25 25-Aug-25
Demolition of Ramps 10 16-Jul-25 26-Jul-25
RIX.4.ME.1000 Submission 3 16-Jul-25 18-Jul-25
RIX.4.ME.1005 Approval 7 19-Jul-25 26-Jul-25
Construction of Temporary Building & Chiller House - Civil & Structural Steel works 12 19-Jul-25 01-Aug-25
RIX.4.ME.1010 Submission 5 19-Jul-25 24-Jul-25
RIX.4.ME.1015 Approval 7 25-Jul-25 01-Aug-25
Construction of Temporary Building & Chiller House - Facade & Roof Works 12 25-Jul-25 07-Aug-25
RIX.4.ME.1020 Submission 5 25-Jul-25 30-Jul-25
RIX.4.ME.1025 Approval 7 31-Jul-25 07-Aug-25
Construction of Temporary Building & Chiller House - MEP & ELV Works 12 31-Jul-25 13-Aug-25
RIX.4.ME.1030 Submission 5 31-Jul-25 05-Aug-25
RIX.4.ME.1035 Approval 7 06-Aug-25 13-Aug-25
Construction of Temporary Building & Chiller House - Elevators and Escalators 12 06-Aug-25 19-Aug-25
RIX.4.ME.1040 Submission 5 06-Aug-25 11-Aug-25
RIX.4.ME.1045 Approval 7 12-Aug-25 19-Aug-25
Construction of Temporary Building & Chiller House - Finishes 12 12-Aug-25 25-Aug-25
RIX.4.ME.1050 Submission 5 12-Aug-25 16-Aug-25
RIX.4.ME.1055 Approval 7 18-Aug-25 25-Aug-25
Refurbishment of Floor 1 corridor in Existing Terminal Building 12 16-Jul-25 29-Jul-25
RIX.4.ME.1070 Submission 5 16-Jul-25 21-Jul-25
RIX.4.ME.1075 Approval 7 22-Jul-25 29-Jul-25
Miscellaneous Works 12 30-Jul-25 12-Aug-25
RIX.4.ME.1060 Submission 5 30-Jul-25 04-Aug-25
RIX.4.ME.1065 Approval 7 05-Aug-25 12-Aug-25
Second Section: Construction of External Evacuation Routes on the North and South sides 91 08-May-25 23-Aug-25
Construction of Evacuation Routes - Civil & Structural Steel works 26 25-Jul-25 23-Aug-25
RIX.4.ME.1080 Submission 5 25-Jul-25 30-Jul-25
RIX.4.ME.1085 Approval 21 31-Jul-25 23-Aug-25
Construction of Evacuation Routes - Finishes 26 08-May-25 06-Jun-25
RIX.4.ME.1100 Submission 5 08-May-25 13-May-25
RIX.4.ME.1105 Approval 21 14-May-25 06-Jun-25
Third Section: Terminal Expansion 83 08-May-25 14-Aug-25
Construction of Terminal work-Structure, Civil & Structural Steel works 26 16-Jul-25 14-Aug-25
RIX.4.ME.1110 Submission 5 16-Jul-25 21-Jul-25
RIX.4.ME.1115 Approval 21 22-Jul-25 14-Aug-25
Construction of Terminal work-Structure-Roofing 26 08-May-25 06-Jun-25
RIX.4.ME.1120 Submission 5 08-May-25 13-May-25
Actual Work Critical Remaining Work Page 3 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1125 Approval 21 14-May-25 06-Jun-25
Construction of Terminal work-Structure-Facade 26 08-May-25 06-Jun-25
RIX.4.ME.1130 Submission 5 08-May-25 13-May-25
RIX.4.ME.1135 Approval 21 14-May-25 06-Jun-25
Construction of Terminal work-Structure-MEP & ELV 26 10-May-25 09-Jun-25
RIX.4.ME.1140 Submission 5 10-May-25 15-May-25
RIX.4.ME.1145 Approval 21 16-May-25 09-Jun-25
Installation of Airport Systems 26 10-May-25 09-Jun-25
RIX.4.ME.1150 Submission 5 10-May-25 15-May-25
RIX.4.ME.1155 Approval 21 16-May-25 09-Jun-25
BHS and Hold Baggage Security Systems 26 10-May-25 09-Jun-25
RIX.4.ME.1160 Submission 5 10-May-25 15-May-25
RIX.4.ME.1165 Approval 21 16-May-25 09-Jun-25
Finishes Works 26 08-May-25 06-Jun-25
RIX.4.ME.1170 Submission 5 08-May-25 13-May-25
RIX.4.ME.1175 Approval 21 14-May-25 06-Jun-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1180 Submission 5 08-May-25 13-May-25
RIX.4.ME.1185 Approval 21 14-May-25 06-Jun-25
Fourth Section: Demolition of the temporary building and reconstruction of the non-Schengen 26 08-May-25 06-Jun-25
Demolition of Temporary Building 26 08-May-25 06-Jun-25
RIX.4.ME.1190 Submission 5 08-May-25 13-May-25
RIX.4.ME.1195 Approval 21 14-May-25 06-Jun-25
Refurbishment of non-Schengen arrivals in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1200 Submission 5 08-May-25 13-May-25
RIX.4.ME.1205 Approval 21 14-May-25 06-Jun-25
Fifth Section: Construction of part of the Terminal Baggage Handling Building 56 08-May-25 14-Jul-25
Construction of BHS building - Structure, Civil & Structural Steel works 26 08-May-25 06-Jun-25
RIX.4.ME.1210 Submission 5 08-May-25 13-May-25
RIX.4.ME.1215 Approval 21 14-May-25 06-Jun-25
Construction of BHS building-Roofing 26 08-May-25 06-Jun-25
RIX.4.ME.1220 Submission 5 08-May-25 13-May-25
RIX.4.ME.1225 Approval 21 14-May-25 06-Jun-25
Construction of BHS building - Facade 26 08-May-25 06-Jun-25
RIX.4.ME.1230 Submission 5 08-May-25 13-May-25
RIX.4.ME.1235 Approval 21 14-May-25 06-Jun-25
Installation of MEP & ELV 26 13-May-25 11-Jun-25
RIX.4.ME.1240 Submission 5 13-May-25 17-May-25
RIX.4.ME.1245 Approval 21 19-May-25 11-Jun-25
BHS and Hold Baggage Security Systems 26 13-May-25 11-Jun-25
RIX.4.ME.1250 Submission 5 13-May-25 17-May-25
RIX.4.ME.1255 Approval 21 19-May-25 11-Jun-25
Finishes Work 26 12-Jun-25 14-Jul-25
RIX.4.ME.1260 Submission 5 12-Jun-25 17-Jun-25
RIX.4.ME.1265 Approval 21 18-Jun-25 14-Jul-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1270 Submission 5 08-May-25 13-May-25
RIX.4.ME.1275 Approval 21 14-May-25 06-Jun-25
Sixth Section: Reconstruction of the Schengen arrivals area in sector E of the Terminal and BHS 26 08-May-25 06-Jun-25
Refurbishment of Schengen arrivals area in sector E in existing terminal 26 08-May-25 06-Jun-25
Actual Work Critical Remaining Work Page 4 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1280 Submission 5 08-May-25 13-May-25
RIX.4.ME.1285 Approval 21 14-May-25 06-Jun-25
Construction of Connection to New BHS Building 26 08-May-25 06-Jun-25
RIX.4.ME.1290 Submission 5 08-May-25 13-May-25
RIX.4.ME.1295 Approval 21 14-May-25 06-Jun-25
Seventh Section: Terminal F, 1st floor reconstruction to provide service facilities 26 08-May-25 06-Jun-25
Refurbishment of 1st floor reconstruction to provide service facilities in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1300 Submission 5 08-May-25 13-May-25
RIX.4.ME.1305 Approval 21 14-May-25 06-Jun-25
Refurbishment of Departure Baggage Delivery Corridor in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1310 Submission 5 08-May-25 13-May-25
RIX.4.ME.1315 Approval 21 14-May-25 06-Jun-25
Refurbishment of Schengen Passenger Arrival Corridor in existing terminal 26 08-May-25 06-Jun-25
RIX.4.ME.1320 Submission 5 08-May-25 13-May-25
RIX.4.ME.1325 Approval 21 14-May-25 06-Jun-25
Eighth Section: Construction of an access flyover 26 08-May-25 06-Jun-25
Construction of Flyover -Structure Civil & Structural Steel works 26 08-May-25 06-Jun-25
RIX.4.ME.1330 Submission 5 08-May-25 13-May-25
RIX.4.ME.1335 Approval 21 14-May-25 06-Jun-25
Installation of External Canopy 26 08-May-25 06-Jun-25
RIX.4.ME.1340 Submission 5 08-May-25 13-May-25
RIX.4.ME.1345 Approval 21 14-May-25 06-Jun-25
Road Finishing Work 26 08-May-25 06-Jun-25
RIX.4.ME.1350 Submission 5 08-May-25 13-May-25
RIX.4.ME.1355 Approval 21 14-May-25 06-Jun-25
Miscellaneous Works 26 08-May-25 06-Jun-25
RIX.4.ME.1360 Submission 5 08-May-25 13-May-25
RIX.4.ME.1365 Approval 21 14-May-25 06-Jun-25
Ninth Section: Areas with Utilities, Road Construction 26 08-May-25 06-Jun-25
Construction of Road Works 26 08-May-25 06-Jun-25
RIX.4.ME.1370 Submission 5 08-May-25 13-May-25
RIX.4.ME.1375 Approval 21 14-May-25 06-Jun-25
Construction of Utilities Works 26 08-May-25 06-Jun-25
RIX.4.ME.1380 Submission 5 08-May-25 13-May-25
RIX.4.ME.1385 Approval 21 14-May-25 06-Jun-25
Miscelleanous Work 26 08-May-25 06-Jun-25
RIX.4.ME.1390 Submission 5 08-May-25 13-May-25
RIX.4.ME.1395 Approval 21 14-May-25 06-Jun-25
Tenth Section: Construction of a multi-storey car parking 26 11-Jun-25 12-Jul-25
Construction of MLCP - Structure & Civil 26 11-Jun-25 12-Jul-25
RIX.4.ME.1400 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1405 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Structural Steel 26 11-Jun-25 12-Jul-25
RIX.4.ME.1410 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1415 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Roofing 26 11-Jun-25 12-Jul-25
RIX.4.ME.1420 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1425 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - Facade 26 11-Jun-25 12-Jul-25
RIX.4.ME.1430 Submission 5 11-Jun-25 16-Jun-25
Actual Work Critical Remaining Work Page 5 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.4.ME.1435 Approval 21 17-Jun-25 12-Jul-25
Construction of MLCP - MEP & ELV 26 11-Jun-25 12-Jul-25
RIX.4.ME.1440 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1445 Approval 21 17-Jun-25 12-Jul-25
Car Parking Systems 26 11-Jun-25 12-Jul-25
RIX.4.ME.1450 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1455 Approval 21 17-Jun-25 12-Jul-25
Finishes Works 26 11-Jun-25 12-Jul-25
RIX.4.ME.1460 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1465 Approval 21 17-Jun-25 12-Jul-25
Miscellaneous Works 26 11-Jun-25 12-Jul-25
RIX.4.ME.1470 Submission 5 11-Jun-25 16-Jun-25
RIX.4.ME.1475 Approval 21 17-Jun-25 12-Jul-25
Procurement 440 16-Jul-25 09-Apr-27
RIX.2600 Procurement Program reaches 80% of Contract Sum 0 10-Dec-26
Phase 1 Subcontractor Finalization 120 16-Jul-25 12-Jan-26
RIX.4.PW.SUB.1000 MLCP Sub contractor finalization (Piling, Precast, MEP, Solar etc.) 110 16-Jul-25 13-Dec-25
RIX.4.PW.SUB.1010 Viaduct Sub contractor finalization (Piling, Precast, MEP, Solar etc.) 120 16-Jul-25 12-Jan-26
RIX.4.PW.SUB.1015 Demolition Sub contractor finalization 15 16-Jul-25 01-Aug-25
RIX.4.PW.SUB.1020 Temporary Building, Chiller Building, Internal Corridor & Emergency Staircase, Sub contractor finalization 53 16-Jul-25 15-Sep-25
RIX.4.PW.SUB.1030 At Grade works Sub contractor finalization (MEP, Road works, Paving, Signages) 98 16-Jul-25 14-Nov-25
Phase II Subcontractor Finalization 365 16-Jul-25 10-Dec-26
RIX.2530 Terminal Building Sub contractor finalization (Piling) 40 16-Jul-25 30-Aug-25
RIX.2540 Terminal Building Sub contractor finalization (Shell & Core works) 100 01-Sep-25 27-Feb-26
RIX.2550 Terminal Building Sub contractor finalization (MEP, Airport systems, Finishes) 100 30-Oct-25 30-Apr-26
RIX.2560 Terminal Part A Sub contractor finalization - Balance miscellaneous packages 100 30-Apr-26 29-Aug-26
RIX.2570 Terminal Part B Sub contractor finalization - Balance miscellaneous packages 75 29-Aug-26 10-Dec-26
Phase III Subcontractor Finalization 75 10-Dec-26 09-Apr-27
RIX.2580 Existing Airport refurbishment Sub contractor finalization 75 10-Dec-26 09-Apr-27
Construction 1044 11-Jun-25 06-Mar-29
Work Permit 528 11-Jun-25 21-Jun-27
RIX.4.PW.WP.1000 Work Permit for Ramp Demolition and Temporary Building/Chiller Construction 10 16-Jul-25 26-Jul-25
RIX.4.PW.WP.1010 Work Permit for Internal Corridor 13 16-Jul-25 30-Jul-25
RIX.4.PW.WP.1020 At grade Work North - Work Permit 10 16-Jul-25 26-Jul-25
RIX.4.PW.WP.1030 At grade Work South - Work Permit 10 09-Jun-27 21-Jun-27
RIX.4.PW.WP.1040 Terminal Building Part A- Work Permit 13 16-Jul-25 30-Jul-25
RIX.4.PW.WP.1045 Terminal Building Part B & BHS- Unaffected 10 17-Jul-26 29-Jul-26
RIX.4.PW.WP.1060 MLCP - Work Permit 13 11-Jun-25 27-Jun-25
Phase-1 296 02-Aug-25 23-Sep-26
Stage-1 202 02-Aug-25 03-Jun-26
Demolition Works 49 02-Aug-25 29-Sep-25
Demolition of Existing Ramp 49 02-Aug-25 29-Sep-25
RIX.8.CP1.1020 Demolition of Existing Ramp 49 02-Aug-25 29-Sep-25
Construction of Temporary Building 165 15-Sep-25 03-Jun-26
Civil, Structural Steel & Roofing works 125 15-Sep-25 15-Apr-26
RIX.8.CP1.1030 Foundation Works 40 15-Sep-25 31-Oct-25
RIX.8.CP1.1040 Superstructure Works 40 21-Oct-25 16-Jan-26
RIX.8.CP1.1050 Structural Steel Works 40 19-Dec-25 14-Mar-26
RIX.8.CP1.1055 Erection of Roof 35 03-Mar-26 15-Apr-26
Actual Work Critical Remaining Work Page 6 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
MEP Works 45 14-Mar-26 11-May-26
RIX.8.CP1.1080 PHE (Storm Water, Rain Water Pipe, UG Services Dismantling) 15 14-Mar-26 01-Apr-26
RIX.8.CP1.1090 ELV (Fire/PA, CCTV, ACS, Network, UG Services Dismantling) 20 23-Mar-26 17-Apr-26
RIX.8.CP1.1370 HVAC (Split AC) 20 26-Mar-26 21-Apr-26
RIX.8.CP1.1730 Electrical (Panel, Cable Tray, Cabli ng, Earthing, LPS, Light Fixture, Point Power Wiring) 45 14-Mar-26 11-May-26
RIX.8.CP1.1760 Firefighting (Hydrant System, Extinguisher) 15 01-Apr-26 21-Apr-26
Elevators and Escalators 30 14-Mar-26 21-Apr-26
RIX.8.CP1.1100 Elevator Installation 30 14-Mar-26 21-Apr-26
RIX.8.CP1.1110 Escalator Installation 30 14-Mar-26 21-Apr-26
Facade Works 35 26-Mar-26 11-May-26
RIX.8.CP1.1070 Facade Erection 35 26-Mar-26 11-May-26
Finishes 30 21-Apr-26 28-May-26
RIX.8.CP1.1120 Finishing Work 30 21-Apr-26 28-May-26
Miscellaneous Works 20 11-May-26 03-Jun-26
RIX.8.CP1.1130 Miscellaneous Works 20 11-May-26 03-Jun-26
Refurbishment of Floor 1 corridor in existing terminal building 100 13-Sep-25 13-Mar-26
RIX.8.CP1.1140 Refurbishment of Floor 1 corridor 100 13-Sep-25 13-Mar-26
Emergency Staircase North & South 100 16-Sep-25 16-Mar-26
RIX.2590 Erection of Emergency Staircases 100 16-Sep-25 16-Mar-26
Chiller Building 145 30-Sep-25 25-May-26
Civil, Structural Steel & Roofing works 75 30-Sep-25 25-Feb-26
RIX.8.CP1.1150 Civil, Structural Steel & Roofing works 75 30-Sep-25 25-Feb-26
MEP Works 55 26-Feb-26 07-May-26
RIX.8.CP1.1170 PHE (Rain Water Pip e, Condensate Drain) 15 26-Feb-26 17-Mar-26
RIX.8.CP1.1180 ELV (Fire/PA, CCTV, ACS, Network, BMS) 30 07-Mar-26 14-Apr-26
RIX.8.CP1.1770 HVAC (Chiller, Piping, Insulation, Pumps, AHU, Air Distribution System) 45 11-Mar-26 07-May-26
RIX.8.CP1.1780 Electrical (Panel, Cable Tray, Cabli ng, Earthing, LPS, Light Fixture, Point Power Wiring) 45 26-Feb-26 23-Apr-26
RIX.8.CP1.1790 Firefighting (Extinguisher) 7 17-Mar-26 25-Mar-26
Facade Works 35 17-Mar-26 29-Apr-26
RIX.8.CP1.1160 Facade Works 35 17-Mar-26 29-Apr-26
Finishes 35 04-Apr-26 19-May-26
RIX.8.CP1.1200 Building Finishes Work 35 04-Apr-26 19-May-26
Miscellaneous works 20 29-Apr-26 25-May-26
RIX.8.CP1.1210 Miscellaneous Works 20 29-Apr-26 25-May-26
Stage-2 81 16-Mar-26 25-Jun-26
Construction of External Evacuation Routes 81 16-Mar-26 25-Jun-26
North Side of Existing Terminal 53 16-Mar-26 21-May-26
Civil Structural Steel & MEP works 43 16-Mar-26 09-May-26
RIX.8.CP1.1220 Civil Works - North Evacuation Route 28 16-Mar-26 20-Apr-26
RIX.8.CP1.1230 MEP works (Lighting, Wiring, ACS) 15 20-Apr-26 09-May-26
Finishes 25 20-Apr-26 21-May-26
RIX.8.CP1.1250 Finishes Work 25 20-Apr-26 21-May-26
South Side of Existing Terminal 53 20-Apr-26 25-Jun-26
Civil Structural Steel & MEP works 43 20-Apr-26 11-Jun-26
RIX.8.CP1.1260 Civil Works - South Evacuation Route 28 20-Apr-26 25-May-26
RIX.8.CP1.1270 MEP works (Lighting, Wiring, ACS) 15 25-May-26 11-Jun-26
Finishes 25 25-May-26 25-Jun-26
RIX.8.CP1.1290 Finishes Works 25 25-May-26 25-Jun-26
Stage-8 262 06-Sep-25 18-Sep-26
Construction of the Viaduct 262 06-Sep-25 18-Sep-26
North Part - Viaduct 262 06-Sep-25 18-Sep-26
Actual Work Critical Remaining Work Page 7 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Foundation Works 65 06-Sep-25 13-Dec-25
RIX.8.CP1.1300 Piling & Demolition Work 40 06-Sep-25 23-Oct-25
RIX.8.CP1.1310 Pile Cap 40 07-Oct-25 13-Dec-25
Superstructure Works 157 15-Dec-25 03-Aug-26
RIX.8.CP1.1320 Pier Construction 60 15-Dec-25 07-Apr-26
RIX.8.CP1.1330 Pier Top Constructio n 50 28-Feb-26 30-Apr-26
RIX.8.CP1.1335 Beam & Slab works, Retaining Wall works 30 18-Apr-26 26-May-26
RIX.8.CP1.1340 Viaduct Construction 65 08-May-26 25-Jul-26
RIX.8.CP1.1350 Miscellaneous works 10 22-Jul-26 03-Aug-26
Electrical & Plumbing Works 175 15-Dec-25 24-Aug-26
RIX.8.CP1.1830 Existing Services Dismantling Works 30 15-Dec-25 27-Feb-26
RIX.8.CP1.1840 Installation of Drainage Pipes 20 08-Jul-26 31-Jul-26
RIX.8.CP1.1850 HDPE Containment, Power Cabling, Fibre Optic Cabling, Network Cabling 20 08-Jul-26 31-Jul-26
RIX.8.CP1.1860 Installation of Feeder Piller, Street Light Poles, JB 15 20-Jul-26 06-Aug-26
RIX.8.CP1.1870 Installation of Light Fixures, Cameras, Speakers 15 06-Aug-26 24-Aug-26
RIX.8.CP1.1880 Installation of Escalator 30 26-May-26 02-Jul-26
Finishing Works 22 24-Aug-26 18-Sep-26
RIX.8.CP1.1360 Viaduct Road Pavement & Finishes works 15 24-Aug-26 10-Sep-26
RIX.8.CP1.1380 Miscellaneous works 7 10-Sep-26 18-Sep-26
Stage-9 199 30-Oct-25 28-Aug-26
Areas with External Engineering Utility Networks 199 30-Oct-25 28-Aug-26
Construction of External Services 199 30-Oct-25 28-Aug-26
RIX.8.CP1.1750 Dismantling/Removal of Existing Services 25 30-Oct-25 29-Dec-25
RIX.8.CP1.1890 Temporary Diversion of Utilities 25 03-Dec-25 04-Feb-26
RIX.8.CP1.1895 Re-Installation of Perimeter Intrusion detection system 25 13-Jan-26 06-Mar-26
RIX.8.CP1.1900 Commissioning of Temporary diverted Utilities 25 17-Feb-26 24-Mar-26
RIX.8.CP1.1910 Installation of Fire Pipes 40 12-Mar-26 30-Apr-26
RIX.8.CP1.1920 Installation of Sewer Drain & Storm Water Drain , Installa tion of Duct Pipe/HT Cables 40 07-Apr-26 26-May-26
RIX.8.CP1.1930 Installation of Hot Water Pipes, Cold Water Supply Pipes, Irrigation pipes, Duct Pipe/LT Cables, Cable Pit 40 30-Apr-26 18-Jun-26
RIX.8.CP1.1940 Installation of HDPE Duct Pipe & Laying of FO Cable, Cu Cable, CAT 6 Cable 40 26-May-26 14-Jul-26
RIX.8.CP1.1950 Installation of Hydrant, Hose reel Cabinet 10 03-Jun-26 15-Jun-26
RIX.8.CP1.1960 Installation of Street light Poles, Feeder Piller, DB, Outdoor Racks, Cameras, Display Panel 40 11-Jun-26 30-Jul-26
RIX.8.CP1.1970 Installation of Boom Barrier, UVSS, Parking Management Machines 25 30-Jul-26 28-Aug-26
Road Construction 188 15-Nov-25 25-Aug-26
RIX.8.CP1.DIV Road and Passanger Diversion 2 29-Apr-26 02-May-26
North Side - Road 188 15-Nov-25 25-Aug-26
Main Road 91 15-Nov-25 29-Apr-26
RIX.8.CP1.1440 Excavation 21 15-Nov-25 09-Jan-26
RIX.8.CP1.1450 Subgrade Preparation 21 10-Dec-25 02-Feb-26
RIX.8.CP1.1460 Frost-resistant layer 21 08-Jan-26 25-Feb-26
RIX.8.CP1.1470 Mineral material sack 0/56 N-II 21 31-Jan-26 11-Mar-26
RIX.8.CP1.1480 Mineral material sack 0/45 N-I 21 24-Feb-26 23-Mar-26
RIX.8.CP1.1490 Asphalt concrete AC32base 70/100 S-II 21 10-Mar-26 04-Apr-26
RIX.8.CP1.1500 Asphalt concrete AC22bin 70/100 S-II 21 21-Mar-26 17-Apr-26
RIX.8.CP1.1510 Asphalt concrete AC16surf 50/70 S-I (Top Layer) 21 02-Apr-26 29-Apr-26
Paver Road below Viaduct (Centre portion) 96 09-Jan-26 01-Jun-26
RIX.8.CP1.1520 Excavation 25 09-Jan-26 05-Mar-26
RIX.8.CP1.1530 Subgrade Preparation 25 13-Feb-26 23-Mar-26
RIX.8.CP1.1540 Frost resistant layer 25 11-Mar-26 11-Apr-26
Actual Work Critical Remaining Work Page 8 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP1.1550 Mineral mat. sack 0/45 21 28-Mar-26 24-Apr-26
RIX.8.CP1.1555 Levelling layer 21 17-Apr-26 14-May-26
RIX.8.CP1.1560 concrete paving stone (Top layer) 21 07-May-26 01-Jun-26
At grade Pedestrian Road 111 05-Mar-26 20-Jul-26
RIX.8.CP1.1570 Excavation 21 05-Mar-26 30-Mar-26
RIX.8.CP1.1575 Subgrade Preparation 21 23-Mar-26 18-Apr-26
RIX.8.CP1.1580 Frost resistant layer 21 11-Apr-26 08-May-26
RIX.8.CP1.1585 Mineral material sack 0/56 21 29-Apr-26 26-May-26
RIX.8.CP1.1590 Mineral material sack 0/45 21 19-May-26 12-Jun-26
RIX.8.CP1.1595 Levelling layer 21 05-Jun-26 02-Jul-26
RIX.8.CP1.1599 Concrete paving stone (Top layer) 21 25-Jun-26 20-Jul-26
Road Finishes Work along with Footpath Works 31 20-Jul-26 25-Aug-26
RIX.8.CP1.2000 Road finishes work 31 20-Jul-26 25-Aug-26
Utilities Work 31 12-Mar-26 20-Apr-26
RIX.8.CP1.2010 Installation of Lighting, Fire fighting and Plumbing pipes 31 12-Mar-26 20-Apr-26
Stage-10 266 06-Sep-25 23-Sep-26
Construction of Multi Level Car Parking 266 06-Sep-25 23-Sep-26
Civil & Structure 206 06-Sep-25 15-Jul-26
Foundation Works 65 06-Sep-25 13-Dec-25
RIX.8.CP1.2250 Piling Work 30 06-Sep-25 11-Oct-25
RIX.8.CP1.2260 Excavation 10 07-Oct-25 17-Oct-25
RIX.8.CP1.2270 Pile Cap 30 13-Oct-25 02-Dec-25
RIX.8.CP1.2280 Backfilling 10 21-Nov-25 13-Dec-25
Floor 1 52 15-Dec-25 26-Mar-26
RIX.8.CP1.2290 Grade Slab 7 15-Dec-25 05-Jan-26
RIX.8.CP1.2300 Structural steel Columns & beam,staircases 21 06-Jan-26 23-Feb-26
RIX.8.CP1.2310 Laying Decksheet 14 22-Jan-26 23-Feb-26
RIX.8.CP1.2320 Laying of Reinforcement 21 07-Feb-26 14-Mar-26
RIX.8.CP1.2330 Laying of Concrete Floor 1 Slab 10 14-Mar-26 26-Mar-26
Floor 2 45 26-Mar-26 21-May-26
RIX.8.CP1.2340 Structural steel Columns & beam,staircases 21 26-Mar-26 21-Apr-26
RIX.8.CP1.2350 Laying Decksheet 14 04-Apr-26 22-Apr-26
RIX.8.CP1.2360 Laying of Reinforcement 21 14-Apr-26 09-May-26
RIX.8.CP1.2370 Laying of Concrete Floor 2 Slab 10 09-May-26 21-May-26
Floor 3 45 21-May-26 15-Jul-26
RIX.8.CP1.2380 Structural steel Columns & beam,staircases 21 21-May-26 15-Jun-26
RIX.8.CP1.2390 Laying Decksheet 14 29-May-26 15-Jun-26
RIX.8.CP1.2400 Laying of Reinforcement 21 06-Jun-26 03-Jul-26
RIX.8.CP1.2410 Laying of Concrete Floor 3 Slab 10 03-Jul-26 15-Jul-26
Facade & Roof Works 50 15-Jul-26 11-Sep-26
RIX.8.CP1.1600 Roof Works 45 15-Jul-26 05-Sep-26
RIX.8.CP1.1610 Facade Works 30 07-Aug-26 11-Sep-26
Installation of MEP & ELV 31 15-Jul-26 20-Aug-26
RIX.8.CP1.1620 PHE 21 27-Jul-26 20-Aug-26
RIX.8.CP1.1630 ELV 21 21-Jul-26 14-Aug-26
RIX.8.CP1.1800 HVAC 20 23-Jul-26 15-Aug-26
RIX.8.CP1.1810 Electrical 30 15-Jul-26 19-Aug-26
RIX.8.CP1.1820 Firefighting 20 27-Jul-26 19-Aug-26
Finishes Works 25 19-Aug-26 17-Sep-26
RIX.8.CP1.1640 Finishes Works 25 19-Aug-26 17-Sep-26
Actual Work Critical Remaining Work Page 9 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Miscellaneous Works 5 17-Sep-26 23-Sep-26
RIX.8.CP1.1650 Miscellaneous Works 5 17-Sep-26 23-Sep-26
Phase-2 846 15-Aug-25 14-Sep-28
RIX.8.CP2.TO Terminal Opening 0 10-May-28
Stage-3 - Construction of New Terminal 834 15-Aug-25 31-Aug-28
Construction of New Terminal Part - A 396 15-Aug-25 17-Mar-27
Structure Works 396 15-Aug-25 17-Mar-27
Foundation Works 155 15-Aug-25 20-Apr-26
RIX.8.CP2.2090 Piling Work 30 15-Aug-25 18-Sep-25
RIX.8.CP2.2100 Excavation 45 19-Sep-25 22-Nov-25
RIX.8.CP2.2110 Pile Cap 50 24-Nov-25 13-Mar-26
RIX.8.CP2.2120 Backfilling 20 13-Mar-26 08-Apr-26
RIX.8.CP2.2340 Substructure Waterproofing 10 08-Apr-26 20-Apr-26
Floor 1 112 20-Apr-26 02-Sep-26
RIX.8.CP2.2130 Grade Slab 45 20-Apr-26 13-Jun-26
RIX.8.CP2.2140 Structural steel, Columns, beam & Staircases 45 13-Jun-26 07-Aug-26
RIX.8.CP2.2150 Laying Decksheet 10 07-Aug-26 19-Aug-26
RIX.8.CP2.2160 Laying of Reinforcement 10 19-Aug-26 31-Aug-26
RIX.8.CP2.2165 Laying of Concrete Floor 1 Slab 2 31-Aug-26 02-Sep-26
Floor 2 31 02-Sep-26 09-Oct-26
RIX.8.CP2.2170 Structural steel, Columns, beam & Staircases 20 02-Sep-26 26-Sep-26
RIX.8.CP2.2180 Laying Decksheet 5 26-Sep-26 02-Oct-26
RIX.8.CP2.2190 Laying of Reinforcement 5 02-Oct-26 08-Oct-26
RIX.8.CP2.2200 Laying of Concrete Floor 2 Slab 1 08-Oct-26 09-Oct-26
Floor 3 67 09-Oct-26 30-Jan-27
RIX.8.CP2.2210 Structural steel, Columns, beam & Staircases 45 09-Oct-26 17-Dec-26
RIX.8.CP2.2220 Laying Decksheet 10 17-Dec-26 09-Jan-27
RIX.8.CP2.2230 Laying of Reinforcement 10 09-Jan-27 27-Jan-27
RIX.8.CP2.2240 Laying of Concrete Floor 3 Slab 2 27-Jan-27 30-Jan-27
Floor 4 31 30-Jan-27 17-Mar-27
RIX.8.CP2.2250 Structural steel, Columns, beam & Staircases 20 30-Jan-27 04-Mar-27
RIX.8.CP2.2260 Laying Decksheet 5 04-Mar-27 10-Mar-27
RIX.8.CP2.2270 Laying of Reinforcement 5 10-Mar-27 16-Mar-27
RIX.8.CP2.2280 Laying of Concrete Floor 4 Slab 1 16-Mar-27 17-Mar-27
Construction of New Terminal Part - B Unaffected 377 29-Jul-26 06-Dec-27
Structure Works 377 29-Jul-26 06-Dec-27
Foundation Works 136 29-Jul-26 13-Feb-27
RIX.8.CP2.1000 Piling Work 30 29-Jul-26 02-Sep-26
RIX.8.CP2.1010 Excavation 31 02-Sep-26 09-Oct-26
RIX.8.CP2.1020 Pile Cap 45 09-Oct-26 17-Dec-26
RIX.8.CP2.1030 Backfilling 20 17-Dec-26 27-Jan-27
RIX.8.CP2.2350 Substructure Waterproofing 10 27-Jan-27 13-Feb-27
Floor 1 112 13-Feb-27 06-Jul-27
RIX.8.CP2.1040 Grade Slab 45 13-Feb-27 14-Apr-27
RIX.8.CP2.1050 Structural steel, Columns, beam & Staircases 45 14-Apr-27 08-Jun-27
RIX.8.CP2.1060 Laying Decksheet 10 08-Jun-27 19-Jun-27
RIX.8.CP2.1070 Laying of Reinforcement 10 19-Jun-27 03-Jul-27
RIX.8.CP2.1075 Laying of Concrete Floor 1 Slab 2 03-Jul-27 06-Jul-27
Floor 2 31 06-Jul-27 11-Aug-27
RIX.8.CP2.1080 Structural steel, Columns, beam & Staircases 20 06-Jul-27 29-Jul-27
Actual Work Critical Remaining Work Page 10 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1090 Laying Decksheet 5 29-Jul-27 04-Aug-27
RIX.8.CP2.1100 Laying of Reinforcement 5 04-Aug-27 10-Aug-27
RIX.8.CP2.1110 Laying of Concrete Floor 2 Slab 1 10-Aug-27 11-Aug-27
Floor 3 67 11-Aug-27 29-Oct-27
RIX.8.CP2.1120 Structural steel, Columns, beam & Staircases 45 11-Aug-27 04-Oct-27
RIX.8.CP2.1130 Laying Decksheet 10 04-Oct-27 15-Oct-27
RIX.8.CP2.1140 Laying of Reinforcement 10 15-Oct-27 27-Oct-27
RIX.8.CP2.1150 Laying of Concrete Floor 3 Slab 2 27-Oct-27 29-Oct-27
Floor 4 31 29-Oct-27 06-Dec-27
RIX.8.CP2.1160 Structural steel, Columns, beam & Staircases 20 29-Oct-27 23-Nov-27
RIX.8.CP2.1170 Laying Decksheet 5 23-Nov-27 29-Nov-27
RIX.8.CP2.1180 Laying of Reinforcement 5 29-Nov-27 04-Dec-27
RIX.8.CP2.1190 Laying of Concrete Floor 4 Slab 1 04-Dec-27 06-Dec-27
Permanent Utility Diversion through the Precast Tunnel 100 29-Jul-26 07-Dec-26
RIX.8.CP1.1420 Utility Diversion - UG Precast Tunnel, Storm Water Drain, Sewer, Water Supply, Hydrant & Hot Water System 100 29-Jul-26 07-Dec-26
Construction of New Terminal Part - B Affected 377 07-Dec-26 05-Apr-28
Structure Works 377 07-Dec-26 05-Apr-28
Foundation Works 136 07-Dec-26 19-Jun-27
RIX.8.CP2.3020 Piling Work 30 07-Dec-26 03-Feb-27
RIX.8.CP2.3030 Excavation 31 03-Feb-27 19-Mar-27
RIX.8.CP2.3040 Pile Cap 45 19-Mar-27 15-May-27
RIX.8.CP2.3050 Backfilling 20 15-May-27 08-Jun-27
RIX.8.CP2.3220 Substructure Waterproofing 10 08-Jun-27 19-Jun-27
Floor 1 112 19-Jun-27 01-Nov-27
RIX.8.CP2.3060 Grade Slab 45 19-Jun-27 13-Aug-27
RIX.8.CP2.3070 Structural steel, Columns, beam & Staircases 45 13-Aug-27 06-Oct-27
RIX.8.CP2.3080 Laying Decksheet 10 06-Oct-27 18-Oct-27
RIX.8.CP2.3090 Laying of Reinforcement 10 18-Oct-27 29-Oct-27
RIX.8.CP2.3230 Laying of Concrete Floor 1 Slab 2 29-Oct-27 01-Nov-27
Floor 2 31 01-Nov-27 08-Dec-27
RIX.8.CP2.3100 Structural steel, Columns, beam & Staircases 20 01-Nov-27 25-Nov-27
RIX.8.CP2.3110 Laying Decksheet 5 25-Nov-27 01-Dec-27
RIX.8.CP2.3120 Laying of Reinforcement 5 01-Dec-27 07-Dec-27
RIX.8.CP2.3130 Laying of Concrete Floor 2 Slab 1 07-Dec-27 08-Dec-27
Floor 3 67 08-Dec-27 29-Feb-28
RIX.8.CP2.3140 Structural steel, Columns, beam & Staircases 45 08-Dec-27 03-Feb-28
RIX.8.CP2.3150 Laying Decksheet 10 03-Feb-28 15-Feb-28
RIX.8.CP2.3160 Laying of Reinforcement 10 15-Feb-28 26-Feb-28
RIX.8.CP2.3170 Laying of Concrete Floor 3 Slab 2 26-Feb-28 29-Feb-28
Floor 4 31 29-Feb-28 05-Apr-28
RIX.8.CP2.3180 Structural steel, Columns, beam & Staircases 20 29-Feb-28 23-Mar-28
RIX.8.CP2.3190 Laying Decksheet 5 23-Mar-28 29-Mar-28
RIX.8.CP2.3200 Laying of Reinforcement 5 29-Mar-28 04-Apr-28
RIX.8.CP2.3210 Laying of Concrete Floor 4 Slab 1 04-Apr-28 05-Apr-28
Structural Steel Roof Erection 133 29-Feb-28 10-Aug-28
Roof Truss Erection Works 60 29-Feb-28 13-May-28
RIX.8.CP2.1220 Roof Truss Erection Works 60 29-Feb-28 13-May-28
Periphery Columns 73 13-May-28 10-Aug-28
RIX.8.CP2.2500 Base Plate Installation for Slanting Columns 13 13-May-28 29-May-28
RIX.8.CP2.2510 Erection of Slanting Columns 20 29-May-28 21-Jun-28
Actual Work Critical Remaining Work Page 11 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.2520 Peripheral Cantilever Roof Installation 20 21-Jun-28 18-Jul-28
RIX.8.CP2.2530 Connection to Main Roof 20 18-Jul-28 10-Aug-28
Roofing 60 29-Feb-28 13-May-28
Roof Sheeting Work 60 29-Feb-28 13-May-28
RIX.8.CP2.1230 Roof Sheeting Work 60 29-Feb-28 13-May-28
Roof Cladding Works 45 29-Feb-28 24-Apr-28
RIX.8.CP2.1240 Roof Cladding Works 45 29-Feb-28 24-Apr-28
Facade & Skylight Works 60 29-May-28 10-Aug-28
Framing 60 29-May-28 10-Aug-28
RIX.8.CP2.1200 Framing Work 60 29-May-28 10-Aug-28
Glazing Work 60 29-May-28 10-Aug-28
RIX.8.CP2.1210 Glazing Work 60 29-May-28 10-Aug-28
RIX.8.CP2.1215 Installation of Sky Lighting 45 29-May-28 24-Jul-28
MEP & Electronic Communication Systems 512 02-Sep-26 27-Jun-28
Electrical Work 428 09-Oct-26 21-Apr-28
RIX.8.CP2.1250 First fix works (Conduit fixing, Wiring, Earthing, Concealed Items) 90 09-Oct-26 08-Mar-27
RIX.8.CP2.1260 Second Fix Works (Cable Tray, Cabling, Above False Ceiling Fixtures) 120 21-Oct-26 26-Apr-27
RIX.8.CP2.1270 Substation 2050 works (TR, HT/LT Panels, RMU, Bus Duct, HT/LT Cables) 60 01-Nov-27 15-Jan-28
RIX.8.CP2.1280 Special Systems (Lighting Automation, UPS) 60 09-Feb-28 21-Apr-28
RIX.8.CP2.1285 Final Fix Works (Installation of light Fixtures, Switches & Other Exposed Items) 60 09-Feb-28 21-Apr-28
Plumbing Works 141 02-Sep-26 02-Apr-27
RIX.8.CP2.1290 Cold & Hot Water Piping Work 120 02-Sep-26 06-Mar-27
RIX.8.CP2.1300 Sewerage Pipe Works 90 21-Oct-26 19-Mar-27
RIX.8.CP2.1310 Siphonic Roof Drainage / Condensate Drain Piping Works 90 02-Nov-26 02-Apr-27
RIX.8.CP2.1320 Installation of Sanitary fixtures 45 16-Jan-27 24-Mar-27
RIX.8.CP2.1330 Pumps & Panels 60 06-Nov-26 26-Feb-27
HVAC Works 100 02-Sep-26 03-Feb-27
RIX.8.CP2.1340 Chilled water pipeline 60 02-Sep-26 19-Nov-26
RIX.8.CP2.1350 Ducting Works 75 14-Sep-26 07-Jan-27
RIX.8.CP2.1360 Insulation Works 75 26-Sep-26 25-Jan-27
RIX.8.CP2.1370 Installation of AHUs,VAV ,fans etc 60 08-Oct-26 16-Jan-27
RIX.8.CP2.1380 Chillers & chilled water pumps 60 20-Oct-26 03-Feb-27
ELV (FAS, PA, ACS, CCTV, IIDS, SAS, Monitor, PRM, PFMS, ASSD, Master Clock, BMS, ECS Active Passive) 471 21-Oct-26 27-Jun-28
RIX.8.CP2.1390 Conduit, Concealed Items 60 21-Oct-26 04-Feb-27
RIX.8.CP2.1400 Cable Tray, Race Ways, Network, Communication Cables 90 26-Apr-27 13-Aug-27
RIX.8.CP2.1410 Rack, Panels, Switches, Deductors, Sensors, Modules, Speakers, Controller, Reader, IO Face Plate, Master clock 45 11-Apr-28 07-Jun-28
RIX.8.CP2.1411 Software, Server, Monitor Installation 15 07-Jun-28 27-Jun-28
Fire Fighting Works 448 21-Oct-26 29-May-28
RIX.8.CP2.1440 Piping Works (Sprinkler and Hydrant) 120 21-Oct-26 26-Apr-27
RIX.8.CP2.1445 Pumproom Works (Technical Room) 45 06-Nov-26 30-Jan-27
RIX.8.CP2.1450 Clean Agent System Works 90 09-Feb-28 29-May-28
RIX.8.CP2.1460 Installation of Sprinklers, Landing Valve, Fire Hose Reels and Hose Cabinets 60 09-Feb-28 21-Apr-28
Elevator 60 19-Jun-28 31-Aug-28
RIX.8.CP2.3010 Installation of Elevators 60 19-Jun-28 31-Aug-28
Escalator 60 19-Jun-28 31-Aug-28
RIX.8.CP2.3000 Installation of Escalators 30 19-Jun-28 27-Jul-28
RIX.8.CP2.3260 Installation of Escalators in Existing Terminal Building 30 27-Jul-28 31-Aug-28
Finishes Works 337 06-Jul-27 17-Aug-28
Floor 1 160 06-Jul-27 15-Jan-28
RIX.8.CP2.1610 Plastering Works 20 06-Jul-27 29-Jul-27
Actual Work Critical Remaining Work Page 12 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1620 Flooring Works 20 29-Jul-27 21-Aug-27
RIX.8.CP2.1630 Partition Works 20 21-Aug-27 14-Sep-27
RIX.8.CP2.1640 Wall Finishes Works 20 14-Sep-27 08-Oct-27
RIX.8.CP2.1650 Ceiling works 20 08-Oct-27 01-Nov-27
RIX.8.CP2.1660 Signages Works 20 01-Nov-27 25-Nov-27
RIX.8.CP2.1670 Rest room finishes 20 25-Nov-27 18-Dec-27
RIX.8.CP2.1680 Furniture & Fixtures 20 18-Dec-27 15-Jan-28
Floor 2 160 11-Aug-27 21-Feb-28
RIX.8.CP2.1690 Plastering Works 20 11-Aug-27 03-Sep-27
RIX.8.CP2.1700 Flooring Works 20 03-Sep-27 28-Sep-27
RIX.8.CP2.1710 Partition Works 20 28-Sep-27 21-Oct-27
RIX.8.CP2.1720 Wall Finishes Works 20 21-Oct-27 13-Nov-27
RIX.8.CP2.1730 Ceiling works 20 13-Nov-27 08-Dec-27
RIX.8.CP2.1740 Signages Works 20 08-Dec-27 05-Jan-28
RIX.8.CP2.1750 Rest room finishes 20 05-Jan-28 28-Jan-28
RIX.8.CP2.1760 Furniture & Fixtures 20 28-Jan-28 21-Feb-28
Floor 3 160 29-Oct-27 13-May-28
RIX.8.CP2.1770 Plastering Works 20 29-Oct-27 23-Nov-27
RIX.8.CP2.1780 Flooring Works 20 23-Nov-27 16-Dec-27
RIX.8.CP2.1790 Partition Works 20 16-Dec-27 13-Jan-28
RIX.8.CP2.1800 Wall Finishes Works 20 13-Jan-28 05-Feb-28
RIX.8.CP2.1810 Ceiling works 20 05-Feb-28 29-Feb-28
RIX.8.CP2.1820 Signages Works 20 29-Feb-28 23-Mar-28
RIX.8.CP2.1830 Rest room finishes 20 23-Mar-28 18-Apr-28
RIX.8.CP2.1840 Furniture & Fixtures 20 18-Apr-28 13-May-28
Floor 4 208 06-Dec-27 17-Aug-28
RIX.8.CP2.1850 Plastering Works 21 06-Dec-27 04-Jan-28
RIX.8.CP2.1860 Flooring Works 21 04-Jan-28 28-Jan-28
RIX.8.CP2.1870 Partition Works 21 28-Jan-28 22-Feb-28
RIX.8.CP2.1880 Wall Finishes Works 21 22-Feb-28 17-Mar-28
RIX.8.CP2.1890 Ceiling works 21 17-Mar-28 11-Apr-28
RIX.8.CP2.1900 Signages Works 21 24-Jul-28 17-Aug-28
Reconstruction of Existing Terminal 240 29-Jul-27 16-May-28
Reconstruction of Custom Room 105 29-Jul-27 01-Dec-27
RIX.8.CP2.1910 Reconstruction of Custom Room 105 29-Jul-27 01-Dec-27
Reconstruction of L&F Room 90 01-Dec-27 20-Mar-28
RIX.8.CP2.1920 Reconstruction of L&F Room 90 01-Dec-27 20-Mar-28
Installation of Elevator and Escalators 45 20-Mar-28 16-May-28
RIX.8.CP2.1930 Installation of Elevators 45 20-Mar-28 16-May-28
RIX.8.CP2.1940 Installation of Escalators 45 20-Mar-28 16-May-28
MEP Works 40 20-Mar-28 10-May-28
RIX.8.CP2.1945 MEP Works 40 20-Mar-28 10-May-28
Stage-5 BHS Building 609 29-Jul-26 14-Sep-28
Construction of New BHS Building 609 29-Jul-26 14-Sep-28
Structure 269 29-Jul-26 30-Jul-27
Foundation Works 135 29-Jul-26 11-Feb-27
RIX.8.CP2.1950 Piling Work 30 29-Jul-26 02-Sep-26
RIX.8.CP2.1955 Excavation 30 02-Sep-26 08-Oct-26
RIX.8.CP2.1957 Construction of BHS - Tunnel 23 08-Oct-26 06-Nov-26
RIX.8.CP2.1960 Pile Cap 45 08-Oct-26 15-Dec-26
Actual Work Critical Remaining Work Page 13 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.8.CP2.1965 Backfilling 30 15-Dec-26 11-Feb-27
Floor 1 82 11-Feb-27 28-May-27
RIX.8.CP2.1970 Grade Slab Work 30 11-Feb-27 24-Mar-27
RIX.8.CP2.1980 Structural steel, Columns, beam & Staircases 30 24-Mar-27 30-Apr-27
RIX.8.CP2.1990 Laying of deck sheet 10 30-Apr-27 14-May-27
RIX.8.CP2.2000 Laying of Reinforcement 10 14-May-27 26-May-27
RIX.8.CP2.2010 Laying of Concrete Floor 1 Slab 2 26-May-27 28-May-27
Floor 2 52 28-May-27 30-Jul-27
RIX.8.CP2.2360 Structural steel, Columns, beam & Staircases 30 28-May-27 05-Jul-27
RIX.8.CP2.2370 Laying of deck sheet 10 05-Jul-27 16-Jul-27
RIX.8.CP2.2380 Laying of Reinforcement 10 16-Jul-27 28-Jul-27
RIX.8.CP2.2390 Laying of Concrete Floor 2 Slab 2 28-Jul-27 30-Jul-27
Roofing 60 30-Jul-27 09-Oct-27
RIX.8.CP2.2030 Erection of Roofing Work 60 30-Jul-27 09-Oct-27
Installation of MEP & ELV 252 06-Nov-26 18-Oct-27
RIX.8.CP2.1281 DG - DRUPS Standby Power System (Incl HSD Yard, Exhaust Strut, Piping, Insulation, Bus Duct, Panel, Fuel Piping, 120
Tank)06-Nov-26 12-May-27
RIX.8.CP2.2040 PHE 30 30-Jul-27 03-Sep-27
RIX.8.CP2.2050 ELV 45 11-Aug-27 04-Oct-27
RIX.8.CP2.2060 HVAC 40 23-Aug-27 09-Oct-27
RIX.8.CP2.2290 Electrical 40 31-Aug-27 18-Oct-27
RIX.8.CP2.2300 Firefighting 30 07-Sep-27 13-Oct-27
Installation of BHS 392 28-May-27 14-Sep-28
Sequence 1 120 28-May-27 19-Oct-27
RIX.8.CP2.2061 Dismantling of Existing Structures 10 28-May-27 09-Jun-27
RIX.8.CP2.2071 Mechanical erection 20 05-Jul-27 28-Jul-27
RIX.8.CP2.2081 Equipment Installstion 20 28-Jul-27 20-Aug-27
RIX.8.CP2.2091 Electrical Cabling Work 20 20-Aug-27 13-Sep-27
RIX.8.CP2.2101 Unitory/Overall Test 25 13-Sep-27 13-Oct-27
RIX.8.CP2.2111 Preliminary Reception Test 5 13-Oct-27 19-Oct-27
Sequence 2 185 05-Jul-27 12-Feb-28
RIX.8.CP2.3280 Mechanical erection 90 05-Jul-27 19-Oct-27
RIX.8.CP2.3300 Electrical Cabling Work 90 22-Jul-27 05-Nov-27
RIX.8.CP2.3305 Screening Machine Installation 7 28-Oct-27 05-Nov-27
RIX.8.CP2.3310 Unitory/Overall Test 75 05-Nov-27 07-Feb-28
RIX.8.CP2.3320 Preliminary Reception Test 5 07-Feb-28 12-Feb-28
Sequence 3 26 12-Feb-28 14-Mar-28
RIX.2310 Dismantling 7 12-Feb-28 21-Feb-28
RIX.2320 Mechanical erection 7 21-Feb-28 29-Feb-28
RIX.2330 Unitory/Overall Test 7 29-Feb-28 08-Mar-28
RIX.2340 Preliminary Reception Test 5 08-Mar-28 14-Mar-28
Sequence 4 44 14-Mar-28 09-May-28
RIX.2350 Dismantling 7 14-Mar-28 22-Mar-28
RIX.2360 Mechanical Erection 15 22-Mar-28 08-Apr-28
RIX.2370 Electrical Cabling Work 15 22-Mar-28 08-Apr-28
RIX.2380 Screening Machine Installation 7 08-Apr-28 19-Apr-28
RIX.2390 Unitory Overall Test 10 19-Apr-28 02-May-28
RIX.2400 Preliminary Reception Test 5 02-May-28 09-May-28
Sequence 5 33 09-May-28 16-Jun-28
RIX.2410 Dismantling 7 09-May-28 17-May-28
Actual Work Critical Remaining Work Page 14 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.2420 Mechanical Erection 7 17-May-28 25-May-28
RIX.2430 Electrical Cabling Work 7 25-May-28 02-Jun-28
RIX.2440 Unitory Overall Test 7 02-Jun-28 10-Jun-28
RIX.2450 Preliminary Reception Test 5 10-Jun-28 16-Jun-28
Sequence 6 44 16-Jun-28 10-Aug-28
RIX.2460 Dismantling 7 16-Jun-28 27-Jun-28
RIX.2470 Mechanical Erection 15 27-Jun-28 15-Jul-28
RIX.2480 Electrical Cabling Work 15 27-Jun-28 15-Jul-28
RIX.2490 Screening Machine Installation 7 15-Jul-28 24-Jul-28
RIX.2500 Unitory Overall Test 10 24-Jul-28 04-Aug-28
RIX.2510 Preliminary Reception Test 5 04-Aug-28 10-Aug-28
System Performance & Integration 30 10-Aug-28 14-Sep-28
RIX.2520 System Performance & Integration 30 10-Aug-28 14-Sep-28
Facade 45 09-Oct-27 02-Dec-27
RIX.8.CP2.2020 Erection of Facade 45 09-Oct-27 02-Dec-27
Finishes Works 31 01-Nov-27 08-Dec-27
RIX.8.CP2.2070 Finishes Works 31 01-Nov-27 08-Dec-27
Miscellaneous Work 15 01-Dec-27 18-Dec-27
RIX.8.CP2.2080 Miscellaneous Works 15 01-Dec-27 18-Dec-27
South Part - Viaduct 456 24-Oct-25 10-Aug-27
Foundation Works 65 24-Oct-25 12-Mar-26
RIX.8.CP1.1660 Piling Work 40 24-Oct-25 23-Jan-26
RIX.8.CP1.1670 Pile Cap 40 15-Dec-25 12-Mar-26
Superstructure Works 310 12-Mar-26 05-May-27
RIX.8.CP1.1680 Pier Construction 75 12-Mar-26 12-Jun-26
RIX.8.CP1.1690 Pier Top Constructio n 60 12-Jun-26 24-Aug-26
RIX.8.CP1.1695 Beam & Slab works, Retaining Wall works 30 24-Aug-26 29-Sep-26
RIX.8.CP1.1700 Viaduct Construction 75 29-Sep-26 28-Jan-27
RIX.8.CP1.1705 Vertical connection Building and Foot bridge - Structure works 30 28-Jan-27 15-Mar-27
RIX.8.CP1.1710 External Canopy Works 30 15-Mar-27 21-Apr-27
RIX.8.CP1.1715 Miscellaneous works 10 21-Apr-27 05-May-27
Electrical & Plumbing Works 90 15-Mar-27 05-Jul-27
RIX.8.CP1.2420 Existing Services Dismantling Works 30 15-Mar-27 21-Apr-27
RIX.8.CP1.2430 Installation of Drainage Pipes 30 21-Apr-27 28-May-27
RIX.8.CP1.2440 HDPE Containment, Power Cabling, Fibre Optic Cabling, Network Cabling 30 21-Apr-27 28-May-27
RIX.8.CP1.2450 Installation of Feeder Piller, Street Light Poles, JB 15 28-May-27 15-Jun-27
RIX.8.CP1.2460 Installation of Light Fixures, Cameras, Speakers 15 15-Jun-27 05-Jul-27
Finishing Works 31 05-Jul-27 10-Aug-27
RIX.8.CP1.1720 Viaduct Road Pavement & Finishes works 21 05-Jul-27 29-Jul-27
RIX.8.CP1.1740 Miscellaneous works 10 29-Jul-27 10-Aug-27
South Side - Road 329 21-Jun-27 26-Jul-28
Main Road 189 21-Jun-27 05-Feb-28
RIX.8.CP1.2040 Excavation 25 21-Jun-27 22-Jul-27
RIX.8.CP1.2050 Subgrade Preparation 25 22-Jul-27 20-Aug-27
RIX.8.CP1.2060 Frost-resistant layer 25 20-Aug-27 18-Sep-27
RIX.8.CP1.2070 Mineral material sack 0/56 N-II 21 18-Sep-27 14-Oct-27
RIX.8.CP1.2080 Mineral material sack 0/45 N-I 21 14-Oct-27 08-Nov-27
RIX.8.CP1.2090 Asphalt concrete AC32base 70/100 S-II 21 08-Nov-27 03-Dec-27
RIX.8.CP1.2100 Asphalt concrete AC22bin 70/100 S-II 21 03-Dec-27 30-Dec-27
RIX.8.CP1.2110 Asphalt concrete AC16surf 50/70 S-I (Top Layer) 30 30-Dec-27 05-Feb-28
Actual Work Critical Remaining Work Page 15 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
Paver Road below Viaduct (Centre portion) 138 18-Sep-27 04-Mar-28
RIX.8.CP1.2120 Excavation 25 18-Sep-27 19-Oct-27
RIX.8.CP1.2130 Subgrade Preparation 25 19-Oct-27 17-Nov-27
RIX.8.CP1.2140 Frost resistant layer 25 17-Nov-27 17-Dec-27
RIX.8.CP1.2150 Mineral mat. sack 0/45 21 17-Dec-27 15-Jan-28
RIX.8.CP1.2160 Levelling layer 21 15-Jan-28 09-Feb-28
RIX.8.CP1.2170 concrete paving stone (Top layer) 21 09-Feb-28 04-Mar-28
At grade Pedestrian Road 159 17-Nov-27 31-May-28
RIX.8.CP1.2180 Excavation 25 17-Nov-27 17-Dec-27
RIX.8.CP1.2190 Subgrade Preparation 25 17-Dec-27 20-Jan-28
RIX.8.CP1.2200 Frost resistant layer 25 20-Jan-28 18-Feb-28
RIX.8.CP1.2210 Mineral material sack 0/56 21 18-Feb-28 14-Mar-28
RIX.8.CP1.2220 Mineral material sack 0/45 21 14-Mar-28 07-Apr-28
RIX.8.CP1.2230 Levelling layer 21 07-Apr-28 06-May-28
RIX.8.CP1.2240 Concrete paving stone (Top layer) 21 06-May-28 31-May-28
Road Finishes Work along with Footpath Works 45 31-May-28 26-Jul-28
RIX.8.CP1.2020 Road finishes work 45 31-May-28 26-Jul-28
Utilities Work 31 01-Sep-27 08-Oct-27
RIX.8.CP1.2030 Installation of Lighting, Fire fighting and Plumbing pipes 31 01-Sep-27 08-Oct-27
Phase-3 250 10-May-28 06-Mar-29
Stage-4 165 21-Aug-28 06-Mar-29
RIX.8.CP3.1000 Refurbishment of Area D South - Dismantling of Existing non-Shengen Arrival Corridor 15 21-Aug-28 07-Sep-28
RIX.8.CP3.1010 Refurbishment of Area D South - Refurbishment of Existing non-Shengen Arrival Corridor 60 07-Sep-28 16-Nov-28
RIX.8.CP3.1020 Refurbishment of Area D South - BHS Area 60 16-Nov-28 30-Jan-29
RIX.8.CP3.1180 Integration with Existing Facilities 30 30-Jan-29 06-Mar-29
Stage-6 190 10-May-28 22-Dec-28
RIX.8.CP3.1030 Refurbishment of Area E Central - Temporary Shengen Arrival Corridor, 1st Portion of New Passport Control 15 10-May-28 27-May-28
RIX.8.CP3.1040 Refurbishment of Area E Central - New Shengen Arrival Corridor 15 28-Jun-28 17-Jul-28
RIX.8.CP3.1190 Integration with Existing Facilities 30 17-Jul-28 21-Aug-28
Refurbishment of Area E Central - Connection with Existing BHS 105 21-Aug-28 22-Dec-28
RIX.8.CP3.1050 Step-1 : Installation of all componants of New BHS 10 21-Aug-28 01-Sep-28
RIX.8.CP3.1070 Step-2: Install a temporary transit pier connected to the EDS3 10 01-Sep-28 13-Sep-28
RIX.8.CP3.1080 Step-3: Shifting EDS1 from existing no-Schengen transits to the new position 10 13-Sep-28 25-Sep-28
RIX.8.CP3.1090 Step-4: T & C of EDS-1 5 25-Sep-28 30-Sep-28
RIX.8.CP3.1100 Step-5: Connection of The first Check-in island and one of the new no-Sch transit lines to EDS1 10 30-Sep-28 12-Oct-28
RIX.8.CP3.1110 Step-6: Connection of The second Check-in island and the other new no-Sch transit line to EDS1 10 12-Oct-28 24-Oct-28
RIX.8.CP3.1120 Step-7: Move the EDS2 from existing to the new position 10 24-Oct-28 04-Nov-28
RIX.8.CP3.1130 Step-8: T & C of EDS-2 5 04-Nov-28 10-Nov-28
RIX.8.CP3.1140 Step-9: Connection of Three Check-in islands and no-Sch transit lines to EDS1 and EDS2 10 10-Nov-28 23-Nov-28
RIX.8.CP3.1150 Step-10: Connection of all the check-in islands and no-Sch transit lines to EDS1 and EDS2 10 23-Nov-28 05-Dec-28
RIX.8.CP3.1160 Step-11: Move the EDS3 from existing to the new position 10 05-Dec-28 16-Dec-28
RIX.8.CP3.1170 Step-12: T & C of EDS-3 5 16-Dec-28 22-Dec-28
Stage-7 110 27-May-28 06-Oct-28
RIX.8.CP3.1060 Refurbishment of Area F North - 2nd Portion of Passport Control 80 27-May-28 01-Sep-28
RIX.8.CP3.1200 Integration with Existing Facilities 30 01-Sep-28 06-Oct-28
Testing & Commissioning 838 03-Jun-26 23-Apr-29
Phase - 1 118 03-Jun-26 22-Oct-26
Stage 1 56 03-Jun-26 10-Aug-26
Standalone Testing 15 03-Jun-26 20-Jun-26
Actual Work Critical Remaining Work Page 16 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1105 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 03-Jun-26 15-Jun-26
RIX.1115 PHE/FPS (Hydro Test) 7 03-Jun-26 11-Jun-26
RIX.1125 HVAC (Pipe Hydro Test, Air Leakage Test, Chemical Flushing) 15 03-Jun-26 20-Jun-26
RIX.1145 ELV (Cont/Inspection Test) 7 03-Jun-26 11-Jun-26
RIX.1155 Elevator & Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 7 03-Jun-26 11-Jun-26
Power & Water Availability 2 29-Jun-26 01-Jul-26
RIX.1107 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 29-Jun-26 30-Jun-26
RIX.1109 Water Availability (Tapping from near by existing header) 1 30-Jun-26 01-Jul-26
Precommissioning 20 30-Jun-26 23-Jul-26
RIX.1110 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 20 30-Jun-26 23-Jul-26
RIX.1130 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 2 01-Jul-26 03-Jul-26
RIX.1160 HVAC (Powering of Eqpts, No Load test, Eqpt Test, Wild Air Cooling) 15 30-Jun-26 17-Jul-26
RIX.1190 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 15 30-Jun-26 17-Jul-26
RIX.1220 Elevator & Escalator (Panel Charging, Slow Speed, Visual Inspection) 7 30-Jun-26 08-Jul-26
Commissioning 32 03-Jul-26 10-Aug-26
RIX.1120 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing) 15 23-Jul-26 10-Aug-26
RIX.1250 PHE/Fire Protection (Integration with existing system, Physical Check) 3 03-Jul-26 08-Jul-26
RIX.1280 HVAC (Water & Air Balancing, Independent System Commissioning) 15 17-Jul-26 04-Aug-26
RIX.1310 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 15 17-Jul-26 04-Aug-26
RIX.1340 Elevator & Escalator (Full Load Test, Normal Speed Operatio n) 7 08-Jul-26 16-Jul-26
Stage 2 38 11-Jun-26 28-Jul-26
Standalone Testing 10 11-Jun-26 25-Jun-26
RIX.1450 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 11-Jun-26 25-Jun-26
RIX.1480 ELV (Cont/Inspection Test) 7 11-Jun-26 19-Jun-26
Power & Water Availability 1 07-Jul-26 08-Jul-26
RIX.1440 Permanent Power 1 07-Jul-26 08-Jul-26
Precommissioning 10 08-Jul-26 20-Jul-26
RIX.1420 Electrical (DB Meggering, Power Stability Check) 10 08-Jul-26 20-Jul-26
RIX.1530 ELV (Network-uplink, Controller Powerup, Field Devices Check) 7 08-Jul-26 16-Jul-26
Commissioning 10 16-Jul-26 28-Jul-26
RIX.1430 Electrical (DB Meggering, Power Stability Check) 7 20-Jul-26 28-Jul-26
RIX.1570 ELV (Network-uplink, Controller Powerup, Field Devices Check) 7 16-Jul-26 24-Jul-26
Stage 8 46 02-Jul-26 25-Aug-26
Standalone Testing 10 02-Jul-26 14-Jul-26
RIX.1780 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 02-Jul-26 14-Jul-26
RIX.1810 ELV (Cont/Inspection Test) 10 02-Jul-26 14-Jul-26
RIX.1820 Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 7 02-Jul-26 10-Jul-26
Power & Water Availability 1 31-Jul-26 01-Aug-26
RIX.1770 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 31-Jul-26 01-Aug-26
Precommissioning 10 01-Aug-26 13-Aug-26
RIX.1760 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 10 01-Aug-26 13-Aug-26
RIX.1860 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 10 01-Aug-26 13-Aug-26
RIX.1870 Escalator (Panel Charging, Slow Speed, Visual Inspection) 7 01-Aug-26 10-Aug-26
Commissioning 13 10-Aug-26 25-Aug-26
RIX.1880 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 10 13-Aug-26 25-Aug-26
RIX.1910 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 10 13-Aug-26 25-Aug-26
RIX.1920 Escalator (Full Load Test, Normal Speed Operation) 7 10-Aug-26 18-Aug-26
Stage 9 39 25-Aug-26 10-Oct-26
Standalone Testing 10 25-Aug-26 05-Sep-26
RIX.1950 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 10 25-Aug-26 05-Sep-26
Actual Work Critical Remaining Work Page 17 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1960 PHE/FPS (Hydro Test) 10 25-Aug-26 05-Sep-26
RIX.1970 HVAC (Pipe Hydro Test, Chemical Flushing) 10 25-Aug-26 05-Sep-26
RIX.1980 ELV (Cont/Inspection Test) 10 25-Aug-26 05-Sep-26
Power & Water Availability 2 14-Sep-26 16-Sep-26
RIX.1940 Permanent Power (Taping from Existing Power Substation 204A) 1 14-Sep-26 15-Sep-26
RIX.2000 Water Availability (Tapping from near by existing header) 1 15-Sep-26 16-Sep-26
Precommissioning 11 15-Sep-26 29-Sep-26
RIX.1930 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 10 15-Sep-26 28-Sep-26
RIX.2010 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 10 16-Sep-26 29-Sep-26
RIX.2030 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 10 15-Sep-26 28-Sep-26
Commissioning 11 28-Sep-26 10-Oct-26
RIX.2050 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 10 28-Sep-26 09-Oct-26
RIX.2060 PHE/Fire Protection (Integration with existing system, Physical Check) 10 29-Sep-26 10-Oct-26
RIX.2080 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 10 28-Sep-26 09-Oct-26
Stage 10 46 28-Aug-26 22-Oct-26
RIX.1375 Standalone Testing 3 28-Aug-26 01-Sep-26
RIX.1377 Temporary/Permanent Power & Water Availability 1 01-Sep-26 03-Sep-26
RIX.1380 Precommissioning 12 23-Sep-26 08-Oct-26
RIX.1390 Commissioning 12 08-Oct-26 22-Oct-26
Phase - 2 314 18-Dec-27 05-Jan-29
Stage 3 199 10-May-28 05-Jan-29
Standalone Testing 108 10-May-28 16-Sep-28
RIX.1610 Electrical (Cold Test-Cont Test, Megger, Res Test, Insulation Test) 30 10-May-28 14-Jun-28
RIX.1620 PHE/FPS (Hydro Test) 7 29-May-28 06-Jun-28
RIX.1630 HVAC (Pipe Hydro Test, Air Leakage Test, Chemical Flushing) 15 10-May-28 27-May-28
RIX.1640 ELV (Cont/Inspection Test) 60 27-Jun-28 06-Sep-28
RIX.1650 Elevator & Escalator (Mech/Elect Components' Connectivity Checks, Earthing) 14 31-Aug-28 16-Sep-28
Power & Water Availability 2 04-Jul-28 06-Jul-28
RIX.1600 Permanent Power (Taping from Existing Power Substation 204A/Existing Panel FP17) 1 04-Jul-28 05-Jul-28
RIX.1660 Water Availability (Tapping from near by existing header) 1 05-Jul-28 06-Jul-28
Precommissioning 98 05-Jul-28 28-Oct-28
RIX.1580 Electrical (SAT, Charging Panels, Powering Eqpts, Functionality Tests) 45 05-Jul-28 28-Aug-28
RIX.1670 PHE/Fire Protection (Physical Inspection of Existing Eqpts) 15 06-Jul-28 25-Jul-28
RIX.1680 HVAC (Powering of Eqpts, No Load test, Eqpt Test, Wild Air Cooling) 30 05-Jul-28 10-Aug-28
RIX.1690 ELV (Panel Loops Tests, Network-uplink, Controller Powerup, Field Devices Check) 45 06-Sep-28 28-Oct-28
RIX.1700 Elevator & Escalator (Panel Charging, Slow Speed, Visual Inspection) 14 16-Sep-28 03-Oct-28
Commissioning 137 25-Jul-28 05-Jan-29
RIX.1710 Electrical (Relay Coordination, Tripping Sequence, Full Load Testing, LAS, UPS, Integration of DG with S/S) 55 28-Aug-28 31-Oct-28
RIX.1720 PHE/Fire Protection (Integration with existing system, Physical Check) 30 25-Jul-28 29-Aug-28
RIX.1730 HVAC (Water & Air Balancing, Independent System Commissioning) 54 10-Aug-28 12-Oct-28
RIX.1740 ELV (Panel Programming, Logics & Commissioning of Softwares, Core Switch Programming & Field uplink) 55 28-Oct-28 05-Jan-29
RIX.1750 Elevator & Escalator (Full Load Test, Normal Speed Operatio n) 14 03-Oct-28 19-Oct-28
Stage 5 261 18-Dec-27 31-Oct-28
RIX.1225 Standalone Testing 3 18-Dec-27 22-Dec-27
RIX.1227 Temporary/Permanent Power & Water Availability 1 22-Dec-27 27-Dec-27
RIX.1230 Precommissioning 20 14-Sep-28 07-Oct-28
RIX.1240 Commissioning 20 07-Oct-28 31-Oct-28
Phase - 3 135 06-Oct-28 17-Mar-29
Stage 4 10 06-Mar-29 17-Mar-29
Actual Work Critical Remaining Work Page 18 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.1195 Testing & Commissoining 10 06-Mar-29 17-Mar-29
Stage 6 10 22-Dec-28 06-Jan-29
RIX.1255 Testing & Commissoining 10 22-Dec-28 06-Jan-29
Stage 7 10 06-Oct-28 18-Oct-28
RIX.1285 Testing & Commissoining 10 06-Oct-28 18-Oct-28
Final Integration 90 05-Jan-29 23-Apr-29
RIX.2090 HVAC System Integrated with BMS 90 05-Jan-29 23-Apr-29
RIX.2100 HVAC-CPM Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2110 Energy/BTU meter integration wth BMS if any 90 05-Jan-29 23-Apr-29
RIX.2120 VFD Panel Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2130 Pumps Integration with the CPM & BMS 90 05-Jan-29 23-Apr-29
RIX.2140 AHU/Fans & Other HVAC Equipments with BMS 90 05-Jan-29 23-Apr-29
RIX.2150 Fire Alarm System Integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2160 Elevator & Escalator integration with Fire Alarm 90 05-Jan-29 23-Apr-29
RIX.2170 Elevator & Escalator integration with BMS 90 05-Jan-29 23-Apr-29
RIX.2180 Fire Damper integration with BMS & Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2190 PA System integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2200 Clean Agent system integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2210 ASSD Integration with Fire Alarm System 90 05-Jan-29 23-Apr-29
RIX.2220 Lighting Management System integration with the Fire & BMS 90 05-Jan-29 23-Apr-29
RIX.2230 CCTV integration with the BHS 90 05-Jan-29 23-Apr-29
RIX.2240 BHS integration with PA, Fire Alarm 90 05-Jan-29 23-Apr-29
RIX.2250 Access Control System Integration with Fire Alarm, Elevator, Doors, Intrusion Detection 90 05-Jan-29 23-Apr-29
RIX.2260 BHS Integrated with FIDS 90 05-Jan-29 23-Apr-29
RIX.2270 ICT/ECS system integration with Existing Server/Switch 90 05-Jan-29 23-Apr-29
RIX.2280 PFMS Integration with Existing Server 90 05-Jan-29 23-Apr-29
RIX.2290 BHS Integration with AODB, DCS & CDM 90 05-Jan-29 23-Apr-29
RIX.2300 Overall System Performance of Integration 90 05-Jan-29 23-Apr-29
Reporting 1035 02-Aug-25 17-Apr-29
RIX.5.RP.1000 Submission of Monthly Progress Report - 1 1 02-Aug-25 02-Aug-25
RIX.5.RP.1010 Submission of Monthly Progress Report - 2 1 06-Sep-25 08-Sep-25
RIX.5.RP.1020 Submission of Monthly Progress Report - 3 1 13-Oct-25 13-Oct-25
RIX.5.RP.1030 Submission of Monthly Progress Report - 4 1 08-Dec-25 09-Dec-25
RIX.5.RP.1040 Submission of Monthly Progress Report - 5 1 20-Feb-26 21-Feb-26
RIX.5.RP.1050 Submission of Monthly Progress Report - 6 1 01-Apr-26 02-Apr-26
RIX.5.RP.1060 Submission of Monthly Progress Report - 7 1 13-May-26 14-May-26
RIX.5.RP.1070 Submission of Monthly Progress Report - 8 1 15-Jun-26 15-Jun-26
RIX.5.RP.1080 Submission of Monthly Progress Report - 9 1 22-Jul-26 23-Jul-26
RIX.5.RP.1090 Submission of Monthly Progress Report - 10 1 27-Aug-26 28-Aug-26
RIX.5.RP.1100 Submission of Monthly Progress Report - 11 1 03-Oct-26 03-Oct-26
RIX.5.RP.1110 Submission of Monthly Progress Report - 12 1 10-Nov-26 11-Nov-26
RIX.5.RP.1120 Submission of Monthly Progress Report - 13 1 11-Jan-27 12-Jan-27
RIX.5.RP.1130 Submission of Monthly Progress Report - 14 1 04-Mar-27 04-Mar-27
RIX.5.RP.1140 Submission of Monthly Progress Report - 15 1 09-Apr-27 10-Apr-27
RIX.5.RP.1150 Submission of Monthly Progress Report - 16 1 19-May-27 20-May-27
RIX.5.RP.1160 Submission of Monthly Progress Report - 17 1 25-Jun-27 25-Jun-27
RIX.5.RP.1170 Submission of Monthly Progress Report - 18 1 30-Jul-27 31-Jul-27
RIX.5.RP.1180 Submission of Monthly Progress Report - 19 1 06-Sep-27 07-Sep-27
Actual Work Critical Remaining Work Page 19 of 20 10-Feb-25
Remaining Work
Activity ID Activity Name Original Start Finish Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q Q
Duration N D J FM AM J J A S N D J FM A M J J A S ON D J FM AM J J A S ON D J FM AM J J A S ON D J F
RIX.5.RP.1190 Submission of Monthly Progress Report - 20 1 09-Oct-27 09-Oct-27
RIX.5.RP.1200 Submission of Monthly Progress Report - 21 1 13-Nov-27 15-Nov-27
RIX.5.RP.1210 Submission of Monthly Progress Report - 22 1 21-Dec-27 22-Dec-27
RIX.5.RP.1220 Submission of Monthly Progress Report - 23 1 31-Jan-28 31-Jan-28
RIX.5.RP.1230 Submission of Monthly Progress Report - 24 1 04-Mar-28 06-Mar-28
RIX.5.RP.1240 Submission of Monthly Progress Report - 25 1 11-Apr-28 12-Apr-28
RIX.5.RP.1250 Submission of Monthly Progress Report - 26 1 22-May-28 22-May-28
RIX.5.RP.1260 Submission of Monthly Progress Report - 27 1 28-Jun-28 29-Jun-28
RIX.5.RP.1270 Submission of Monthly Progress Report - 28 1 04-Aug-28 05-Aug-28
RIX.5.RP.1280 Submission of Monthly Progress Report - 29 1 08-Sep-28 08-Sep-28
RIX.5.RP.1290 Submission of Monthly Progress Report - 30 1 13-Oct-28 14-Oct-28
RIX.5.RP.1300 Submission of Monthly Progress Report - 31 1 21-Nov-28 22-Nov-28
RIX.5.RP.1310 Submission of Monthly Progress Report - 32 1 27-Dec-28 27-Dec-28
RIX.5.RP.1320 Submission of Monthly Progress Report - 33 1 01-Feb-29 02-Feb-29
RIX.5.RP.1330 Submission of Monthly Progress Report - 34 1 09-Mar-29 10-Mar-29
RIX.5.RP.1340 Submission of Monthly Progress Report - 35 1 17-Apr-29 17-Apr-29
Handing Over / Employers Taking Over 822 16-Jul-26 17-May-29
RIX.10.HO.1000 Handing Over - Stage 1 10 16-Jul-26 28-Jul-26
RIX.10.HO.1010 Handing Over - Stage 2 15 24-Jul-26 11-Aug-26
RIX.10.HO.1020 Handing Over - Stage 3 15 05-Jan-29 23-Jan-29
RIX.10.HO.1030 Handing Over - Stage 4 15 17-Mar-29 06-Apr-29
RIX.10.HO.1040 Handing Over - Stage 5 15 31-Oct-28 17-Nov-28
RIX.10.HO.1050 Handing Over - Stage 6 15 06-Jan-29 24-Jan-29
RIX.10.HO.1060 Handing Over - Stage 7 15 18-Oct-28 04-Nov-28
RIX.10.HO.1070 Handing Over - Stage 8 15 10-Aug-27 27-Aug-27
RIX.10.HO.1080 Handing Over - Stage 9 15 09-Oct-26 27-Oct-26
RIX.10.HO.1090 Handing Over - Stage 10 15 22-Oct-26 12-Nov-26
RIX.10.HO.1100 Final Handover 19 23-Apr-29 17-May-29
Start of Warranty Period 779 28-Jul-26 06-Apr-29
RIX.11.WP.1000 Start of Warrenty Period - Stage 1 0 28-Jul-26
RIX.11.WP.1010 Start of Warrenty Period - Stage 2 0 11-Aug-26
RIX.11.WP.1020 Start of Warrenty Period - Stage 3 0 23-Jan-29
RIX.11.WP.1030 Start of Warrenty Period - Stage 4 0 06-Apr-29
RIX.11.WP.1040 Start of Warrenty Period - Stage 5 0 17-Nov-28
RIX.11.WP.1050 Start of Warrenty Period - Stage 6 0 24-Jan-29
RIX.11.WP.1060 Start of Warrenty Period - Stage 7 0 04-Nov-28
RIX.11.WP.1070 Start of Warrenty Period - Stage 8 0 27-Aug-27
RIX.11.WP.1080 Start of Warrenty Period - Stage 9 0 27-Oct-26
RIX.11.WP.1090 Start of Warrenty Period - Stage 10 0 12-Nov-26
Demobilization 0 17-May-29 17-May-29
RIX.12.DM.1000 Site Demobilization 0 17-May-29
Actual Work Critical Remaining Work Page 20 of 20 10-Feb-25
Remaining Work