Professional Documents
Culture Documents
Potential threats
Impacts
Preparedness
WarningSystems
Response
Potential Threats
Terrorist attacks
Bomb Blast
Sabotage
Hostage
Vital installations
Dam
SFT and Desilting Chambers
Power House
Surge Shaft area
Valve Adit
TRT
Township
DAM
DAM
Location
Situated at Bagga on Chamba – Bharmour Road 20 Km. from Chamba.
Approached by a diversion road to the highway.
Security Arrangements
Entry is restricted through 2 nos. heavy duty Barriers forming first line of
protection followed by Pacca Morchas with DFMD of CISF wherein 3 nos. armed
men with HHMD and Trolley mirror are on duty round the clock.
Surveillance and Communication systems
One no. rotating and one no. fixed IP base Network Cameras besides Night
Vision Binoculars are provided for round the clock monitoring of vicinity of Dam
areas such as Reservoir, Dam structures, Road and nearby hills.
EPBAX ,VSAT, Mobile Communication, P&T ,VHF Set, Wakly-Talky are
available for communication.
Impacts of Potential Threats.
Damage to the various Dam Structures, Flooding, Loss of Human life.
Response
A Disaster Management Plan for handling such situations is in place and being
practiced through Mock Drills.
SFT & Desilting Chamber
Location
Situated adjacent to Dam. Approached by a diversion road to
the highway.
Security Arrangements
Entry is restricted through 1 nos. heavy duty Barriers forming
first line of protection followed by Pacca Morchas wherein 1 nos.
armed men are on duty round the clock.
Communication systems
EPBAX ,P&T, Wakly-Talky are available for communication.
Impacts of Potential Threats.
Damage to the various Equipment, Flooding, Loss of Human
life.
Response
A Disaster Management Plan for handling such situations is in
place and being practiced through Mock Drills.
Valve Chamber
Location
Situated at Jarangla on Chamba – Bharmour Road 11 Km. from Chamba.
Approached by a diversion road to the highway.
Security Arrangements
Entry is restricted through 1 nos. heavy duty Steel gate forming first line of
protection and guarded by 2 nos. Ex-service men round the clock.
Location
Situated at Jarangla on Chamba – Bharmour Road 11 Km. from Chamba.
Approached by a diversion road to the highway.
Security Arrangements
Entry is restricted through 1 nos. heavy duty Steel gate forming first line of
protection and guarded by 2 nos. Ex-service men round the clock.
Location
Situated at Karian on Chamba – Bharmour Road 4 Km. from Chamba.
Approached by a diversion road to the highway.
Security Arrangements
Entry is restricted through 1 nos. heavy duty Steel gate wherein 2 nos. ex-
service men with is on duty round the clock.
Surveillance and Communication systems
1 nos IP base Network Cameras is installed for monitoring of vicinity of nearby
areas
EPBAX is available for communication.
Impacts of Potential Threats.
Damage to the various equipments, Flooding, Loss of Human life.
Response
A Disaster Management Plan for handling such situations is in place and being
practiced through Mock Drills.
Township
Township
Location
Situated at Karian on Chamba – Bharmour Road 4 Km. from Chamba.
Approached by a diversion road to the highway.
Security Arrangements
Entry is restricted through 2 nos. heavy duty Barriers forming first line
of protection followed by Pacca Morchas with DFMD of CISF wherein
4+1 nos. armed men with HHMD are on duty round the clock..
Surveillance and Communication systems
1 nos IP base Network Cameras is installed for monitoring of vicinity of
administrative Block.EPBAX ,VSAT, Mobile Communication, P&T ,VHF
Set, Wakly-Talky are available for communication.
Impacts of Potential Threats.
Damage to the various equipments, Flooding, Loss of Human life.
Response
A Disaster Management Plan for handling such situations is in place
and being practiced through Mock Drills.
Preparedness