Professional Documents
Culture Documents
LECTURE – 02
Before purchasing a equipment one must carefully analyse and answer following two
cost questions about the equipment
How much does it cost to operate a machine on a projects?
This question seeks to identify the expenses associated with productive machine work and is
commonly referred to as ownership and operating (O&O) cost
What is the optimum economic life?
This question seeks to identify the optimum point time to replace a machine
The process answering this question is known as replacement analysis
EQUIPMENT CLASSIFICATION
How to determine what kind and size of equipment seems to be most suitable for a
given project
Provide right equipment at the right time and place so work can be accomplished at
lowest cost
Specific objectives
Minimise ownership and operating cost
Increase availability
Increase utilisation
DATA ACQUISITION
Ownership cost is the cumulative results of those cash flows an owner experiences
whether or not the machine productively employed on a job
The most significant cash flow affecting ownership cost are
Purchase expenses [outflow]
Salvage value [inflow]
Major repairs and overhauls [outflow]
Property taxes [outflow]
Insurance [outflow]
EXPECTED OPERATING LIFE OF EQUIPMENT (HOURS)
Higher powder factors are required for blasting and often the material is bulky,
irregular in shape and has poor fill factors
The engine is often at full power
Tyres fail due to rock cuts and abrasions
Wear rates are high and component life is reduced
There are limited skills in the workforce causing higher repair costs
OPERATING COST ESTIMATION - INFORMATION REQUIRED
For more detailed estimates require Transportation charges and any special
following specific information requirements
The origin of the quote Erection costs including the labour and
material component
The country of origin of the equipment
and the appropriate exchange rate The delivery time including
commissioning
The price of the standard item of plant
FOB factory The payment schedule
A list of options such as training, spare The recommended spare parts holding
bucket, transformers, ropes and air
conditioning
NEED SPECIAL ARRANGEMENT TO TRANSPORT
DERIVATION OF OPERATING COST
This covers the electrical power costs required to operate the machine
This can be subdivided into an "energy component" as well as a "demand" component which
reflects the required installed capacity of the power generation facility
Demand charge comes about because of the cyclical loads of most mining machines and the
electricity authority must be able to supply high power for short periods of time
For quick estimates (a "rule of thumb“ applicable to the coal industry) the average power for
a shovel is 0.6 kW per cubic metre per hour and 1.5 kW per cubic metre per hour for a
dragline
FUEL COST
Lubrication charges are usually calculated as a percentage of the hourly fuel cost
These proportions range from 15%for equipment with a relatively low proportion of
hydraulic componentry (such as a tractor trailers) up to 30-40% for equipment with
a high proportion of hydraulic componentry (such as a hydraulic excavator)
Alternatively the consumption rate can be expressed as either litres/hour or kg/hour
which can be obtained from manufacturers or operational records
This is a more accurate method and is possibly the only method for equipment such
as draglines which consume substantial quantities of lubricants but no fuel oil
TYRES
Total tyre costs are obtained by multiplying the cost of each tyre by the number of
tyres and dividing by the hourly life, tyre manufacturers give guidelines for calculating
hourly life
The tyre life can vary from 1,500 hours to 12,000 hours depending on site conditions
This is usually a base number of hours (4,000 is a common base) multiplied by a
series of factors
These factors account for
Road and work conditions
Tyre maintenance condition
Amount of overloading
Speed
The number of curves and
Surface conditions including temperature grade
MAINTENANCE SUPPLIES
This is adjusted if the number of hours is greater than the standard operating life and
then further adjusted for job conditions
Operating supplies can also be referred to as wear parts or ground engaging tools
Wear items include bucket teeth, ripper boots, drill bits, cutting edges and so on
These are usually separately itemised as they are directly related to the ground
conditions
An approximate method is to take a factor of the capital cost which is the same logic
such as for maintenance supplies
Typical factor is 5 x 10-6
MAJOR OVERHAULS
In allocating personnel, allowance should also be made for the availability of equipment
Unavailable mobile equipment is normally not manned
Large fixed or semi-mobile production equipment is manned even when it is unavailable
OPERATING LABOUR COST
Operator ratio which refers to the number of men per operating shift required to
operate the machines
This ratio can take into account
The shift roster
Amount of absenteeism
Availability of the equipment and whether or not it is manned when it is unavailable
MAINTENANCE LABOUR
There is no easy method to estimate maintenance repair costs, and factors to allow for are
How much work is done offsite such as component exchange
Job conditions
Skill and experience of operators and maintenance personnel
Proximity of spare parts and support
Union requirements such as whether or not a tradesman assistant is required to assist the fitter on
the job
Philosophy of maintenance management
MAINTENANCE LABOUR
The maintenance ratio is the ratio of repairman hours required per machine
operating hour
This ratio can be determined from handbooks, historical records or by back
calculation from the maintenance repair costs per machine per operated hour
The ratio changes with the duty of the machine such as a dozer on ripping versus a
dozer or stockpile on duties.
MAINTENANCE LABOUR
If owner is considering only purchase price and expected salvage, the number argue
that the machine should not be traded
If only operating cost is examined, the owner would want to trade the machine after
first year
For correct analysis both cost must be considered
EXAMPLE REPLACEMENT ANALYSIS
A small dozer is purchased for $1 060 000. A forecast expected operating hours,
salvage value and maintenance expenses are as follows
There are three basic methods for securing a particular machine to use on a project
But ( direct ownership)
Rent
Lease
Ownership guarantees control of machine availability and mechanical condition, but
requires continuing use of equipment to pay for the machine
Ownership may force a company into using obsolete equipment
RENTAL
Consider a small wheel loader with an ownership cost of N$ 109.6 per hour. Cost is
based on assumption that the machine will work 2, 400 hours each year of its service
life. Hence yearly ownership cost is N$ 263, 040.
Checking with local renal company, the mine receives rental quotes of N$ 35580 per
month, N$11 820 per week, and N$3690 per day.
What are the breakeven working hours for all four options?
LEASE
If we borrow an amount of money, P (principal) at a fractional interest rate i (e.g. at 9 per cent, i =
Now S = P
after 1 year S = P (1+i)
after 2 years S = P (1 + i) (1 + i) = P(1 + i)2
after 3 years S = P(1 + i)3
n
after n years S = P(1 + i) (9.8)
Figure 9.3 gives a visual indication of the effects of compounding interest each year.
100
Annual rate of interest = 20 % 18
16
14
12
Value of $1 after n years
10
8
10
1
0 5 10 15 20 25 30 35
Years n
The time variation of the value of money makes it inequitable to compare two
sums that are borrowed or spent at different times
We need a common basis on which both sums can be fairly evaluated
One method of doing this is to determine what principal or capital, P, we need
to invest now in order that it will grow to a desired sum, S, in a specified
number of years
S
P=
(1+i) n
In the case of operating costs, payments must be made each year. Such future
payments may also be expressed as present values in order to compare and
compound them with other expenditures
If operating costs, So, to be constant and paid at the end of each year. Then at the end
of the first year (n = 1), present value of the first year's annual operating cost So is
S0
P0,1 =
(1+i)
Po,1 = Present value of the first year's annual operating cost So: at an interest rate of i
PRESENT VALUE OF REGULAR PAYMENTS
Similarly, the present value of the same operating cost, So, in the second year (n = 2)
is So
P0,2 =
( )
1+ i
2
It follows that the total present value, Po, of operating costs, So paid at each year-end
for n years becomes
é 1 1 1 1 ù
Po = So ê + 2 + 3 +-------+ n ú
ë (1+i ) (1+i) (1+i) (1+i) û
The term inside the bracket is a geometric progression which can be summed to give
Sé 1 ù
Po = ê1- ú
i ë (1+i)n û
EQUIVALENT ANNUAL COST
When capital is borrowed, it is often more convenient to repay it, including interest,
in equal installments each year, rather than as a lump sum paid at the end of the
complete time period
If S is the regular payment, or annual equivalent cost, to be met each year in order to
pay off the capital and interest on a borrowed amount, P. Then Equivalent Annual
Cost (EAC) is
P *i
EAC =
é 1 ù
ê1- n ú
ë (1+i ) û
REFERENCE
Peurifoy, R.L., Schexnayder, C.J., Construction Planning, Equipment and Methods, Chapter:
Equipment Economics.
Westcott, P.C., 1990, Capital and operating cost estimation for open pit mining equipment,
Conference ‘MINECOST’