Gate Building

System Test completion Date Remarks

Earthing & LA After installation completion 9 EARTH PITS OUT OF 12 CLEARED


WORK TO BE COMPLETED FOR
TESTING
HVAC SYSTEM 24/1/2020 CUTOUTS NOT MADE BY CIVIL TEAM
FOR VENTILLATION SYSTEM
ELV Security System __ __ CCTV AWITING BIAL APPROVAL FOR
LISCENCE AND STORAGE/ ACS
MATERIAL NOT RECEIVED AT SITE.

DG 31/1/2020 DG vendor applied for AEP pass


23/1/2020 load bank will reach site
by 27/1/2020
ARFF Building

System Test completion Remarks


Date

Earthing & LA After installation Installation work is pending in 16no earth pits
completion and removal of concrete from earth pits location
to complete the same

HVAC SYSTEM 27/1/2020 CUTOUTS NOT MADE BY CIVIL TEAM FOR


VENTILLATION SYSTEM as markinf done by T&C
Team

ELV Security System __ __ CCTV AWITING BIAL APPROVAL FOR LISCENCE


AND STORAGE/ ACS MATERIAL NOT RECEIVED AT
SITE.

Fire Alarm System Vendor is not available @site .


CCR N34/35

System Test completion Date Remarks

HVAC 28/1/2020 TESTING HAS STARTED ON 21/2/2020 STILL 17.5


TR 2 UNITS TO BE STARTED BY VENDOR, BATTERY
ROOM AC WIRK PENDING
LT PANELS 27/1/2020 SYNTAX ERROR IN REPORT LAKSHYA TO SUBMIT
ACCURATE REPORTS WITHOUT ERRORS

LIGHTING & POWER 24/1/2020 UPS ROOM LIGHTING FIXTURES NOT FIXED IR
REJECTED BY BIAL(CCR 35 3 ROOMS AND DG YARD
LIGHTING NOT FIXED)
UPS & Batteries VENDOR APPLIED FOR AEP PASS ON 22/01/2020

PHE (Internal & External) 25/1/2020 TOILET FLUSH BUTTON,ISOLATION


VALVE,OVERFLOW LINE PENDING IN TERRACE.
CCR N34/35

System Test completion Date Remarks

Fire Protection System FIRE EXTINGUISHERS NOT INSTALLED AS PER


APPROVED DRAWINGS

Fire Alarm System SIEMENS VENDOR NOT AVAILABLE @ SITE


T&C Status

TESTING FINISHED TEST REPORTS SUBMITTED

57% 42%
Factors Affecting T&C

• Installation work Incomplete.

• Vendor Co operation .( Lakshya, Promace, etc..)

• Civil team Co operation regarding HVAC and Earth Pits.

• AEP Pass issues in L&T time office and BIAL.


HVAC

• Gate Building Ventillation System testing


and commissioning pending due to trap
door not provided improper location to
access panels and dampers same
condition in ARFF building. Also civil
team not responding since one month of
follow up.
• CCR buildings N34 started testing .N35
Installation work still pending .
EARTHING

• Gate house 9 out of 12 earth pits are


visible but not properly installed .

• ARFF 9 out of 16 earth pits are visible


and that too filled with concrete civil
team is informed regarding this issue and
still no proper response after continuously
following up. Testing
Fire Protection System

1 Switch Gear Room Right side -3 DCP-10KG 1 No


1 Switch Gear Room Right side -3 DCP-10KG 1 No 2 ,, DCP-25KG 1 No
2 DCP-25KG 1 No 3 ,, CO2-6.5KG 1 No
4 Mechanical Foam Type Extinguisher Foam-50LTR 1 No
3 CO2-6.5KG 1 No
5 Unassigned Room DCP-4KG 1 No
4 Mechanical Foam Type Extinguisher Foam-50LTR 1 No 6 ,, DCP-6KG 1 No
7 ,, CO2-4.5KG 1 No
8 ,, CO2-6.5KG 1 No
Required Total = 04 Nos Required Total = 8 Nos

CCR N34
CCR N35 1 Fire Extinguisher CO2-6.5KG 1 No
CO2 - 6.5KG
2 Fire Extinguisher = 09 Nos
3 Fire Extinguisher DCP - 4KG= 02 Nos
CO2 - 4.5KG
4 Fire Extinguisher = 01 No
Required
5 Fire Extinguisher Total = 12 Nos
6 Fire Extinguisher CO2-6.5KG 1 No
7 Fire Extinguisher CO2-6.5KG 1 No

ARFF BUILDING
Pump Room

Installation work incomplete.


Fire pump installation incomplete in
both Pump room and ARFF buildings.
Which is affecting Fire protection system
commissioning .
PHE

• ARFF building Installation work in


progress
• CCR N34 /N35 flush buton accessories
not installed over flow line not provided
• Also installation as per approved
drawing not done and client is not
accepting for testing.