Professional Documents
Culture Documents
Session 3 - Project Schedule and Cost Planning
Session 3 - Project Schedule and Cost Planning
ADM 6260-E00
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 2
Planning: Project
Schedule Management
Develop Schedule (cont’d)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 4
Resource Optimization
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 5
Resource Optimization (cont’d)
• Resource Leveling:
– Resolves over-allocation of resources by delaying a
task until the assigned resource is available to
work on it. Produces a resource-limited schedule.
– Results in more stable number of resources used
during the project.
– In resource levelling, you check if all resources are
loaded around 100%. If someone is above 100%,
then you will have to either extend the schedule
or move some tasks to other resources.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 6
Resource Optimization (cont’d)
• Resource Smoothing:
– Constraint on the total duration of the project.
– Resources are leveled only within the limits of the
float of their activities, so the completion dates
are not delayed.
– Only activities on noncritical paths are shifted.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 7
Resource Smoothing Example: Consider the below time-constrained project (i.e., project
duration fixed and resources flexible). Assume that a maximum of 3 programmers can
work each week throughout the project duration. Is there a resource over-allocation? If
so, even out the resource allocation so that the resource constraint is met.
A, Drtn=10 B, Drtn=5
Start E, Drtn=15 Finish
C, Drtn=10 D, Drtn=12
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 8
A, Drtn=10 B, Drtn=5
ES=0, LS=7 ES=10, LS=17
Start E, Drtn=15 Finish
Day=0 ES=22, LS=22 Day=37
C, Drtn=10 D, Drtn=12
ES=0, LS=0 ES=10, LS=10
Weeks
Task
1 2 3 4 5 6 7 8
A 1P 2P
B 2P
C 1P 2P
D 1P 1P 2/5=0.4P
E 3/5=0.6P 1P 1P 2/5=0.4P
Total 2P 4P 3P 1P 1P 1P 1P 0.4P
Draw the network with ES and LS on it. Load the resource table for each week
based on ES.
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 9
A, Drtn=10 B, Drtn=5
ES=0, LS=7 ES=10, LS=17
Start E, Drtn=15 Finish
Day=0 ES=22, LS=22 Day=37
C, Drtn=10 D, Drtn=12
ES=0, LS=0 ES=10, LS=10
Weeks
Task
1 2 3 4 5 6 7 8
A 1P 2P
B 2P
C 1P 2P
D 1P 1P 2/5=0.4P
E 3/5=0.6P 1P 1P 2/5=0.4P
Total 1P 3P 3P 3P 1P 1P 1P 0.4P
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 10
Resource Smoothing Example
A network with the following activity durations and
manpower requirement is given. Analyze the project
from point of view of resource constraints (11 people)
and take the necessary steps for resource smoothing.
Activity A B C D E F J G H K I
Duration 2 3 4 2 4 3 6 6 5 4 4
No. of men 4 3 3 5 3 4 3 6 2 2 9
C, Drtn=4
F, Drtn=3 H, Drtn=5 I, Drtn=4
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 11
Resource Smoothing Example
A network with the following activity durations and
manpower requirement is given. Analyze the project
from point of view of resource constraints (11 people)
and take the necessary steps for resource smoothing.
Activity A B C D E F J G H K I
Duration 2 3 4 2 4 3 6 6 5 4 4
No. of men 4 3 3 5 3 4 3 6 2 2 9
B, Drtn=3 D, Drtn=2 J, Drtn=6
ES=2, LS=5 ES=5, LS=8 ES=7, LS=10
Start A, Drtn=2 E, Drtn=4 G, Drtn=6 K, Drtn=4 Finish
0 ES=0, LS=0 ES=6, LS=6 ES=10, LS=10 ES=16, LS=16 20
C, Drtn=4
ES=2, LS=2
F, Drtn=3 H, Drtn=5 I, Drtn=4
ES=6, LS=8 ES=9, LS=11 ES=14, LS=16
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 12
Resource Smoothing Example (cont’d)
Resource Allocation Table (per Day)
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A
B
C
D
E
F
J
G
H
K
I
Total
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 13
Resource Smoothing Example (cont’d)
Resource Allocation Table (per Day)
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A 4 4
B 3 3 3
C 3 3 3 3
D 5 5
E 3 3 3 3
F 4 4 4
J 3 3 3 3 3 3
G 6 6 6 6 6 6
H 2 2 2 2 2
K 2 2 2 2
I 9 9 9 9
Total 4 4 6 6 6 8 12 10 10 8 11 11 11 8 15 15 11 11 2 2
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 14
Resource Smoothing Example (cont’d)
The Load Histogram.
No. of Resources
16
14
12
10
8
6
4
2
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 15
Resource Smoothing Example (cont’d)
Resource Allocation Table (per Day)
Activity 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
A 4 4
B 3 3 3
C 3 3 3 3
D 5 5
E 3 3 3 3
F (4th step) 4 4 4
J (3rd step) 3 3 3 3 3 3
G 6 6 6 6 6 6
H (2nd step) 2 2 2 2 2
K 2 2 2 2
I (1st step) 9 9 9 9
Total 4 4 6 6 6 8 8 7 7 7 9 11 11 11 11 11 11 11 11 11
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 16
Planning: Project Cost
Management
Monitoring &
Initiating Planning Executing Closing
Controlling
Integration
Scope Scope
Schedule Schedule
Cost Cost
Quality
Resources
Communications
Risk
Procurement
Stakeholders
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 18
Project
Planning
Process
Group
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 19
Budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 20
Warning!
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 21
Cost Management Process
Estimate Costs
Determine Budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 22
Plan Cost Management
Plan Cost
Managemen
t
Estimate
Costs
Determine
Budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 23
Estimate Costs
• Direct Costs: directly associated with project work-
labor, material, training, computers, project
manager’s time, expenses for physical office spaces
used directly for project, costs of quality efforts, costs
of risk efforts, etc.
• Indirect Costs: overhead costs or costs incurred for
the benefit of more than one project, taxes, janitorial
services, etc. Plan Cost
Managemen
t
Estimate
Costs
Determine
Budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 24
Example
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 25
Estimate Costs (cont’d)
• Top-Down Budgeting
– Collective judgement of senior / middle
management based on similar past projects.
– Estimate the costs of major tasks, next lower level
of managers split it up among the tasks under
their control
• Bottom-Up Estimating
– Creating detailed estimates for each activity in
Schedule/work package in WBS and then roll up.
– By people responsible for executing them
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 26
Advantages and Disadvantages
Advantages Disadvantages
Top-Down 1- Fairly accurate overall budget 1- Substantial error in activity cost
Budgeting cost estimations
2- The good chance that some 2- Not suitable for progress
small but important tasks was monitoring and performance
overlooked does not usually measurement
cause a serious budgetary 3- Requires considerable experience
problem. to do
3- Fast and cheap 4- Conflict over gaining biggest piece
of the budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 27
Accuracy of Estimates
Estimate
Costs
Determine
Budget
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 29
Determine Budget (cont’d)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 30
Typical Monthly Budget for a Real Estate Project
(Partial)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 31
Project Budget by Task and Month
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 32
Improving Estimates and Forecasts
• Learning Curves
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 33
Learning Curves
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 34
Learning Curves (cont’d)
Tn T1n r
where
Tn = the time required to complete the nth unit
T1 = the time required to complete the first unit
r = log(learning rate)/log(2)
From Project Management Absolute Beginner's Guide, 4/e by Gregory M. Horine (0789756757) Copyright
© 2017 Pearson Education, Inc. All rights reserved 35