Professional Documents
Culture Documents
CHAPTER 17
PROJECT MANAGEMENT
Solutions
1. Use the network diagrams given in the text to determine both the critical path and the expected
project duration. The critical path and the expected project duration are indicated below with an
“*”. Expected duration for each path equals the sum of the activity times on the path.
a.
Path Expected Duration
1–2–4–7–10–12 4 + 9 + 5 + 2 + 3 = 23
1–2–5–8–10–12 4 + 8 + 7 + 2 + 3 = 24
1–3–6–9–11–12 10 + 6 + 4 + 5 + 6 = 31*
d.
17-1
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-2
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
2. a. Ch Sh
Lib Sel
Out Inst
Write
Ck
Sub
Note: The answers for this problem assume that Chris will prepare the paper on the new
computer, but will prepare the outline by hand.
Start End
Sh 2.0 Sel 1.0 Inst 0.8
17-3
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
c. The paths and their expected duration times are given below. Expected duration for each path
equals the sum of the activity times on the path.
Expected
Path Duration
Ch-Lib-Out-Write-Ck-Sub 6.7 hours
Sh-Sel-Inst-Write-Ck-Sub 7.5 hours*
Conclusion: Critical path is Sh-Sel-Inst-Write-Ck-Sub and the expected duration is 7.5
hours.
d. The project could take longer than the expected duration if any activity on the critical path is
delayed or if the other activities on the parallel path (Ch-Lib-Out) are delayed by more than
0.8 hours (7.5 – 6.7).
17-4
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Activity 2 4 6 8 10 12 14 16 18 20
1-2
1-3
2-4
2-5
3-5
4-5
5-6
Activity 2 4 6 8 10 12 14 16 18
1-2
2-5
2-4
1-3
3-4
4-5
3. a. Bank location.
17-5
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Activity 2 4 6 8 10 12 14 16 18 20
1-2
1-3
2-4
2-5
3-5
4-5
5-6
Activity 2 4 6 8 10 12 14 16 18
1-2
2-5
2-4
1-3
3-4
4-5
17-6
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
4. a.
A
E
Dummy
Immediate
Predecessor
Activity
A –
B –
C A
E C
F A,B
End E,F
17-7
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
D
2
A 5
E K
End
B F H
1 3 6 8
C I
G
4 7
L 5
M
2 N
J 6 P
End
9
V
K R
1 3 7
Q W
S
4 T
8
17-8
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
A D
Start B E
End
F H
C G I
K R
S
End
Q
T
W
17-9
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
LS LF
5. a. 21
21
13 5
26
18 26
ES EF
4 7
13
L M
18
12 9 2 28
J 20
11 4 28
2
8 N P 10
4 2 3 31
7 4 11
7 28
4 24
0 8 21
19
5
26
19 26 12
1 12
19
19
12
31
0 10 6 31
0
11 25
10 3 6 5 25
10 25
10 4 25
6 9
Start 10
16 16 20
20
20
16 16 20
Summary:
Activity ES EF LS LF Slack
1–2 0 4 7 11 7
1–3 0 10 0 10 0
2–4 4 13 12 21 8
2–5 4 12 11 19 7
3–6 10 16 10 16 0
4–7 13 18 21 26 8
5–8 12 19 19 26 7
6–9 16 20 16 20 0
7–10 18 20 26 28 8
8–10 19 21 26 28 7
9–11 20 25 20 25 0
10–12 21 24 28 31 7
11–12 25 31 25 31 0
17-10
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-11
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
5. b.
Summary:
Activity ES EF LS LF Slack
1 0 5 0 5 0
2 5 23 5 23 0
3 5 18 20 33 15
4 23 26 37 40 14
5 23 33 23 33 0
6 33 37 40 44 7
7 33 44 33 44 0
8 44 53 44 53 0
9 53 55 53 55 0
Note: Slack = LS – ES or LF – EF.
LS LF
ES EF
37 40
26
5 23 4 40 44
5 37
3
2 6
23 33
18 33 4
0 5 5 44 53 53 55
5 53 55
1
10
8 9
20 33
5
33 44
3 18 9 2
7 44
13
11
17-12
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
6. The network diagram is given in Problem 1, Part a. After 12 weeks, activities 1-2, 1-3, and 2-4
have been finished; activity 2-5 is 75% finished; and activity 3-6 is 50% finished. How many
weeks after the original start date time should the project be finished. The original path expected
durations are given below:
One way of solving this problem is to look at the effects on each path:
Path 1-2-4-7-10-12:
Activities 1-2 and 2-4 were estimated to require take 4 + 9 = 13 weeks. They finished in 12
weeks. In other words, Activity 2-4 finished 1 week early. The net effect is to reduce the expected
time of this path by 1 week to 22 weeks.
Path 1-2-5-8-10-12:
Activities 1-2 and 2-5 were estimated to require 4 + 8 = 12 weeks. Activity 2-5 is 75%
completed; therefore, 25% of the activity time (.25 * 8 = 2 weeks) remains. Activity 2-5 should
have been completed at the end of 12 weeks but is running 2 weeks late. The net effect is to
increase the expected time of this path by 2 weeks to 26 weeks.
Path 1-3-6-9-11-12:
Activities 1-3 and 3-6 were estimated to require 10 + 6 = 16 weeks. Activity 3-6 is 50%
completed; therefore, 50% of the activity time (.50 * 6 = 3 weeks) remains. This means that this
activity should be completed 1 week early because it should be completed by the end of week 15.
The net effect is to reduce the expected time of this path by 1 week to 30 weeks.
Conclusion: The longest path (1-3-6-9-11-12) is estimated to take 30 weeks. Therefore, the
expected project duration is 30 weeks. The original estimated project duration was 31 weeks. We
estimate that the project should be completed 1 week early.
17-13
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
7. a. C
5
2 E
A
3 F 6 G End
8
Start D
1
I
B
4 H 7
b. Activity te 2
A 6.00 4/36
B 8.50 9/36
C 8.17 25/36
D 12.00 36/36
E 6.33 16/36
F 6.00 4/36
G 3.50 25/36
H 4.17 1/36
I 6.83 9/36
Path A-C-E:
Standard deviation =
√ 45
36
=1.118
17-14
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path D-F-G:
Standard deviation =
√ 65
36
=1.344
Path B-H-I:
Standard deviation =
√ 19
36
=0.726
17-15
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path A-C-E:
24−20.50
z= =3.13
1.118
Path D-F-G:
24−21.50
z= =1.86
1.344
Path B-H-I:
24−19.50
z= =6.20
0.726
Path A-C-E:
17-16
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
21−20.50
z= =0.45
1.118
Path D-F-G:
21−21.50
z= =−0.37
1.344
Path B-H-I:
21−19.50
z= =2.07
0.726
17-17
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
c. Assume it is the end of the 7th day. Activities A and B have been completed while
Activity D is 50% completed. Time estimates for the completion time of Activity
D are 5, 6, and 7. Activities C and H are ready to begin. We can re-draw the network as shown
below.
Activity te 2
C 8.17 25/36
D 6.00 4/36
E 6.33 16/36
F 6.00 4/36
G 3.50 25/36
H 4.17 1/36
I 6.83 9/36
C (8.17) E (6.33)
Path C-E:
Standard deviation =
√ 41
36
=1.067
17-18
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path D-F-G:
Standard deviation =
√ 33
36
=0.957
17-19
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path H-I:
Standard deviation =
√ 10
36
=0.527
Path C-E:
24−21.50
z= =2.34
1.067
Path D-F-G:
24−22.50
z= =1.57
0.957
Path H-I:
17-20
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
24−18.00
z= =11.39
0.527
Path C-E:
21−21.50
z= =−0.47
1.067
Path D-F-G:
21−22.50
z= =−1.57
0.957
17-21
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path H-I:
21−18.00
z= =5.69
0.527
d. The partners want to shorten the project by 2 days as long as it does not cost more than
$20,000. The cost per day (in thousands) to crash activities is shown below:
Step 1:
The paths and their expected duration are shown below:
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
F $7
G $8
D $10
Activity F should be shortened 1 day because it has the lowest crashing cost ($7,000).
Path D-F-G now will be 21.50 days as shown below.
17-23
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 2:
The paths and their expected duration are shown below:
Conclusion: Total crashing cost is $7,000 + $8,000 + $8,000 = $23,000, which is $3,000
over budget. The partners have to determine whether the benefits of crashing the project
by 1 day or by 2 days are worth the extra cost.
17-24
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
8. Expected
Duration
Pat Variance Std. Dev.
h
A 10 1.21 1.100
B 8 2.00 1.414
C 12 1.00 1.000
D 15 2.89 1.700
E 14 1.44 1.200
Path A:
16−10
z= =5.45
1.100
Probability of completion ≤ 16 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path B:
16−8
z= =5.66
1.414
Probability of completion ≤ 16 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path C:
16−12
z= =4.00
1.000
Probability of completion ≤ 16 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path D:
16−15
z= =0.59
1.700
Using Appendix B Table B: Probability of completion ≤ 16 weeks = 0.7224
17-25
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path E:
16−14
z= =1.67
1.200
Using Appendix B Table B: Probability of completion ≤ 16 weeks = 0.9525
17-26
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path A:
15−10
z= =4.55
1.100
Probability of completion ≤ 15 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path B:
15−8
z= =4.95
1.414
Probability of completion ≤ 15 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path C:
15−12
z= =3.00
1.000
Using Appendix B Table B: Probability of completion ≤ 15 weeks = 0.9987
Path D:
15−15
z= =0.00
1.700
Using Appendix B Table B: Probability of completion ≤ 15 weeks = 0.5000
Path E:
15−14
z= =0.83
1.200
Using Appendix B Table B: Probability of completion ≤ 15 weeks = 0.7967
17-27
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Path A:
13−10
z= =2.73
1.100
Using Appendix B Table B: Probability of completion ≤ 13 weeks = 0.9968
Path B:
13−8
z= =3.54
1.414
Probability of completion ≤ 13 weeks = 1.0000 (z value > +3.00—treat probability of completion
as being = 1.0000)
Path C:
13−12
z= =1.00
1.000
Using Appendix B Table B: Probability of completion ≤ 13 weeks = 0.8413
Path D:
13−15
z= =−1.18
1.700
Using Appendix B Table B: Probability of completion ≤ 13 weeks = 0.1190
Path E:
13−14
z= =−0.83
1.200
Using Appendix B Table B: Probability of completion ≤ 13 weeks = 0.2033
17-28
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
9. Given:
Standard
Path Activity Mean Deviation
A C 5 1.3
D 4 1.0
B E 8 1.6
Path A:
Expected duration = 5 + 4 = 9
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to find
the variance for each activity, add the variances, and take the square root of the sum.
Variance = 1.32 +1.02=1.690+1.000=2.690
Standard deviation = √ 2.690=1.640
10−9
z= =0.61
1.640
Path B:
Expected duration = 8
Standard deviation = 1.600
10−8
z= =1.25
1.600
Using Appendix B Table B: Probability of completion ≤ 10 weeks = 0.8944
17-29
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-30
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
10. Given:
The project described below is scheduled to be completed in 11 weeks.
Standard
Path Activity Mean Deviation
A C 4 0.70
D 6 0.90
B E 3 0.62
F 9 1.90
a. If you were the manager of this project, would you be concerned? Explain.
Probability (T ≤ 11 weeks):
Path A:
Expected duration = 4 + 6 = 10
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to
find the variance for each activity, add the variances, and take the square root of the sum.
Variance = 0.702 +0.90 2=0.490+0.810=1.300
Standard deviation = √ 1.300=1.140
11−10
z= =0.88
1.140
Using Appendix B Table B: Probability of completion ≤ 11 weeks = 0.8106
Path B:
Expected duration = 3 + 9 = 12
Standard deviation:
We must find the variance of the path first by squaring the individual standard deviations to
find the variance for each activity, add the variances, and take the square root of the sum.
Variance = 0.622 +1.902=0.384 +3.610=3.994
Standard deviation = √ 3.994=1.998
17-31
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
11−12
z= =−0.50
1.998
Using Appendix B Table B: Probability of completion ≤ 11 weeks = 0.3085
17-32
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability
of incurring a penalty of at least $5,000?
This question is asking what the probability will be that the project will take at least 12 weeks
(which would be 1 week late).
Probability (T ≥ 12 weeks):
Path A:
12−10
z= =1.75
1.140
Using Appendix B Table B: Probability of completion < 12 weeks = 0.9599
Path B:
12−12
z= =0.00
1.998
17-33
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
11. Given:
We are given the following times (optimistic, most likely, and pessimistic) for each activity in the
table below.
a. Determine the expected completion time for each path and its variance.
Most
Activity Optimistic Likely Pessimistic Mean Variance
1-2 8 8 8 8.00 0/36
Path 1-2-3-8-11:
Expected completion time = 8.00 + 12.00 + 10.17 + 7.17 = 37.34
Variance = 0/36 + 4/36 + 9/36 + 25/36 = 38/36
Standard deviation =
√ 38
36
=1.027
Path 1-2-4-6-11:
Expected completion time = 8.00 + 6.00 + 18.67 + 10.33 = 43.00
Variance = 0/36 + 4/36 + 144/36 + 36/36 = 184/36
17-34
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Standard deviation =
√ 184
36
=2.261
Path 1-2-4-7-11:
Expected completion time = 8.00 + 6.00 + 13.00 + 13.00 = 40.00
Variance = 0/36 + 4/36 + 0/36 + 25/36 = 29/36
Standard deviation =
Path 1-2-5-9-10-11:
√ 29
36
=0.898
Standard deviation =
√ 45
36
=1.118
b. Determine the probability that the project will require more than 49 weeks.
Path 1-2-3-8-11:
49−37.34
z= =11.35
1.027
Probability of completion ≤ 49 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path 1-2-4-6-11:
49−43.00
z= =2.65
2.261
Using Appendix B Table B: Probability of completion ≤ 49 weeks = 0.9960
Path 1-2-4-7-11:
49−40.00
z= =10.02
0.898
Probability of completion ≤ 49 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path 1-2-5-9-10-11:
17-35
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
49−46.83
z= =1.94
1.118
Using Appendix B Table B: Probability of completion ≤ 49 weeks = 0.9738
17-36
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
c. Determine the probability that the project will be completed in 46 weeks or less.
Probability (T ≤ 46 weeks):
Path 1-2-3-8-11:
46−37.34
z= =8.43
1.027
Probability of completion ≤ 46 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path 1-2-4-6-11:
46−43.00
z= =1.33
2.261
Using Appendix B Table B: Probability of completion ≤ 46 weeks = 0.9082
Path 1-2-4-7-11:
46−40.00
z= =6.68
0.898
Probability of completion ≤ 46 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path 1-2-5-9-10-11:
46−46.83
z= =−0.74
1.118
Using Appendix B Table B: Probability of completion ≤ 46 weeks = 0.2296
17-37
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
12. Given:
We are given the following times (optimistic, most likely, and pessimistic) for each activity in the
table below.
Most
Activity Optimistic Likely Pessimistic Mean Variance
A 2 4 6 4.00 16/36
D 6 8 10 8.00 16/36
E 7 9 12 9.17 25/36
H 2 3 5 3.17 9/36
F 3 4 8 4.50 25/36
G 5 7 9 7.00 16/36
B 2 2 3 2.17 1/36
I 2 3 6 3.33 16/36
J 3 4 5 4.00 4/36
K 4 5 8 5.33 16/36
C 5 8 12 8.17 49/36
M 1 1 1 1.00 0/36
N 6 7 11 7.50 25/36
O 8 9 13 9.50 25/36
End
3 I 7 J 10 O
C
17-38
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
M N 11
4 8
17-39
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. The project manager will receive a bonus of $1,000 if the project is finished within 26 weeks.
P (T ≤ 26):
Path A-D-E-H:
Expected completion time = 4.00 + 8.00 + 9.17 + 3.17 = 24.34
Variance = 16/36 + 16/36 + 25/36 + 9/36 = 66/36
Standard deviation =
√ 66
36
=1.354
26−24.34
z= =1.23
1.354
Using Appendix B Table B: Probability of completion ≤ 26 weeks = 0.8907
Path A-F-G:
Expected completion time = 4.00 + 4.50 + 7.00 = 15.50
Variance = 16/36 + 25/36 + 16/36 = 57/36
Standard deviation =
√ 57
36
=1.258
26−15.50
z= =8.35
1.258
Probability of completion ≤ 26 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path B-I-J-K:
Standard deviation =
√ 37
36
=1.014
26−14.83
z= =11.02
1.014
Probability of completion ≤ 26 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path C-M-N-O:
Expected completion time = 8.17 + 1.00 + 7.50 + 9.50 = 26.17
17-40
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Standard deviation =
√ 99
36
=1.658
26−26.17
z= =−0.10
1.658
Using Appendix B Table B: Probability of completion ≤ 26 weeks = 0.4602
17-41
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
The project manager will receive a bonus of $500 if the project is finished within 27 weeks.
P (T ≤ 27):
Path A-D-E-H:
27−24.34
z= =1.96
1.354
Using Appendix B Table B: Probability of completion ≤ 27 weeks = 0.9750
Path A-F-G:
27−15.50
z= =9.14
1.258
Probability of completion ≤ 27 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path B-I-J-K:
27−14.83
z= =12.00
1.014
Probability of completion ≤ 27 weeks = 1.0000 (z value > +3.00—treat probability of
completion as being = 1.0000)
Path C-M-N-O:
27−26.17
z= =0.50
1.658
Using Appendix B Table B: Probability of completion ≤ 27 weeks = 0.6915
17-42
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
13. Given:
We have the following list of activities for a project and crashing costs:
Top A 5 $8 $10
B 6 $7 $9
C 3 $14 $15
Middle D 3 $9 $11
E 7 $8 $9
C 3 $14 $15
G 5 $11 $13
H 5 $12 $14
Determine which activities should be crashed to shorten the project by 3 weeks as cheaply as
possible. Draw the precedence diagram first.
17-43
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
B
2
4
C
A E
7
D
3
11
H
F
G
5
17-44
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 1:
The paths and their expected duration are shown below:
G $11
H $12
Activity F should be shortened 1 week because it has the lowest crashing cost ($10). Path
F-G-H now will be 14 weeks as shown below.
Activities crashed to this point: Step 1: F (first crash).
Step 2:
The paths and their expected duration are shown below:
17-45
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
C $14
F-G-H G $11
H $12
F $15
17-46
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
17-47
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Activity H should be shortened 1 week because it has the lowest crashing cost ($12) on
Path F-G-H.
Paths A-B-C, D-E-C, and F-G-H will decrease to 12 weeks.
Activities crashed to this point: Step 1: F (first crash). Step 2: B (first crash) & G (first
crash). Step 3: C (first crash) & H (first crash).
17-48
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
F $10 B $7 C $14
G 11 H 12
$18 $26
Conclusion: Expected project duration = 12 weeks. Total crashing cost = $10 + $18 + $26 = $54.
17-49
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
14. Given:
B A 14 $10 $10
C --- 10 $5 $5
D C 17 $20 $21
E C 18 $16 $18
F C 12 $12 $15
G D 15 $24 $24
H E 8 --- ---
I F 7 $30 ---
J I 12 $25 $25
K B 9 $10 $10
M G 3 --- ---
N H 11 $40 ---
P H, J 8 $20 $20
End K, M, N, P
A K
Start
End
C M
G 17-50
D N P
Copyright © 2015 McGraw-Hill Education.
E All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
H Education.
F
J
I
Chapter 17 - Project Management
17-51
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Determine a minimum-cost crashing schedule that will shave five weeks off the project length:
Step 1:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 45
C-E-H-N 47
C-E-H-P 44
C-F-I-J-P 49
Critical path is C-F-I-J-P.
Rank critical activities according to crash costs:
Cost per Week
Activity to Crash
C $5
F $12
P $20
J $25
I $30
Activity C should be shortened 1 week because it has the lowest crashing cost ($5).
Paths C-D-G-M, C-E-H-N, C-E-H-P, and C-F-I-J-P all will decrease 1 week as shown below.
Activities crashed to this point: Step 1: C (first week).
Step 2:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 44
C-E-H-N 46
C-E-H-P 43
C-F-I-J-P 48
Critical path is C-F-I-J-P.
17-52
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
F $12
P $20
J $25
I $30
Activity C should be shortened 1 week because it has the lowest crashing cost ($5).
Paths C-D-G-M, C-E-H-N, C-E-H-P, and C-F-I-J-P all will decrease 1 week.
Activities crashed to this point: Step 1: C (first week). Step 2: C (second week).
Step 3:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 47
Critical path is C-F-I-J-P.
P $20
J $25
I $30
Activity F should be shortened 1 week because it has the lowest crashing cost ($12).
Path C-F-I-J-P will decrease 1 week as shown below.
Activities crashed to this point: Step 1: C (first week). Step 2: C (second week). Step 3: F (first
week).
17-53
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 4:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 46
Critical path is C-F-I-J-P.
P $20
J $25
I $30
Activity F should be shortened 1 week because it has the lowest crashing cost ($15).
Path C-F-I-J-P will decrease 1 week as shown below.
Activities crashed to this point: Step 1: C (first week). Step 2: C (second week). Step 3: F (first
week). Step 4: F (second week).
17-54
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
A-B-K 35
C-D-G-M 43
C-E-H-N 45
C-E-H-P 42
C-F-I-J-P 45
Critical paths are C-E-H-N and C-F-I-J-P.
N $40
C-F-I-J-P P $20
J $25
I $30
Activity E should be shortened 1 week because it has the lowest crashing cost ($16) on Path C-E-
H-N. Paths C-E-H-N and C-E-H-P each will decrease 1 week.
Activity P should be shortened 1 week because it has the lowest crashing cost ($20) on Path C-F-
I-J-P. Paths C-E-H-P and C-F-I-J-P each will decrease 1 week as shown below.
Activities crashed to this point: Step 1: C (first week). Step 2: C (second week). Step 3: F (first
week). Step 4: F (second week). Step 5: E (first week) & P (first week).
17-55
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-56
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Length after Length after Length after Length after Length after
crashing 1 crashing 2 crashing 3 crashing 4 crashing 5
Path Initial week weeks weeks weeks weeks
time
Step 1 Crashing Step 2 Crashing Step 3 Crashing Step 4 Crashing Step 5 Crashing
Activity Cost Activity Cost Activity Cost Activity Cost Activity Cost
P 20
$36
Conclusion: Expected project duration = 44 weeks. Total crashing cost = $5 + $5 + $12 + $15 + $36 =
$73(000) = $73,000.
17-57
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
15. Given:
We have the following activities and crashing costs ($000):
Crashing Costs ($000)
First Second Third
Activity Week Week Week
17-58
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
1-2 $18
2-5 $24
5-7 $30
11-13 $30
Activity 7-11 should be shortened 1 week because it has the lowest crashing cost ($15) and
this cost is ≤ $40.
Path 1-2-5-7-11-13 will decrease 1 week as shown below.
Activities crashed to this point: Step 1: 7-11 (first week).
Step 2:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 34
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33
Critical path is 1-2-5-7-11-13.
Rank critical activities according to crash costs:
17-59
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
7-11 $20
2-5 $24
5-7 $30
11-13 $30
Activity 1-2 should be shortened 1 week because it has the lowest crashing cost ($18) and
this cost is ≤ $40. Path 1-2-5-7-11-13 will decrease 1 week as shown below.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week).
Step 3:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 33
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 33
Critical paths are 1-2-5-7-11-13 & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 7-11 $20
1-2 $22
2-5 $24
5-7 $30
11-13 $30
1-4-6-10-12-13 6-10 $5
4-6 $8
1-4 $10
10-12 $14
17-60
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
12-13 $26
Activity 7-11 should be shortened 1 week because it has the lowest crashing cost ($20) on
Path 1-2-5-7-11-13, which will decrease 1 week as shown below.
Activity 6-10 should be shortened 1 week because it has the lowest crashing cost ($5) on
Path 1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $25 and is ≤ $40.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week).
17-61
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 4:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 32
1-3-8-11-13 32
1-3-9-12-13 20
1-4-6-10-12-13 32
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $30
11-13 $30
8-11 $40
1-4-6-10-12-13 4-6 $8
1-4 $10
6-10 $12
10-12 $14
12-13 $26
Activity 11-13 should be shortened 1 week on Paths 1-2-5-7-11-13 & 1-3-8-11-13 because it
has the lowest crashing cost ($30) to shorten both paths. Both paths will decrease 1 week as
shown below.
Activity 4-6 should be shortened 1 week because it has the lowest crashing cost ($8) on Path
1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $38 and is ≤ $40.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week). Step 4: Activity 11-13 (first week) & Activity 4-6
(first week).
17-62
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-63
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
Rank critical activities according to crash costs:
Cost per Week
Path Activity to Crash
1-2-5-7-11-13 1-2 $22
2-5 $24
5-7 $30
11-13 $33
11-13 $33
8-11 $40
6-10 $12
4-6 $13
10-12 $14
12-13 $26
Activity 11-13 could be shortened 1 week on Paths 1-2-5-7-11-13 & 1-3-8-11-13 because it
has the lowest crashing cost ($33) to shorten both paths. Both paths would decrease 1 week.
Activity 1-4 could be shortened 1 week because it has the lowest crashing cost ($10) on Path
1-4-6-10-12-13, which would decrease 1 week.
The combined crashing cost = $43 and is > $40. Stop.
The marginal cost of crashing > marginal benefit of crashing. We stop crashing after Step 4.
17-64
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
1-2-5-7-11-13 35 34 33 32 31
1-3-8-11-13 32 32 32 32 31
1-3-9-12-13 20 20 20 20 20
1-4-6-10-12-13 33 33 33 32 31
6-10 $ 5 4-6 $ 8
$25 $38
b. Plot the total-cost curve that describes the least expensive crashing schedule that will reduce
the project length by 6 weeks:
In Part a of this problem, we reduced the project length by 4 weeks. We must decrease the
project length by 2 more weeks. We will start with Step 5 from Part a above.
17-65
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-66
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 31
1-3-8-11-13 31
1-3-9-12-13 20
1-4-6-10-12-13 31
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
2-5 $24
5-7 $30
11-13 $33
11-13 $33
8-11 $40
6-10 $12
4-6 $13
10-12 $14
12-13 $26
Activity 11-13 should be shortened 1 week on Paths 1-2-5-7-11-13 & 1-3-8-11-13 because it
has the lowest crashing cost ($33) to shorten both paths. Both paths will decrease 1 week as
shown below.
Activity 1-4 should be shortened 1 week because it has the lowest crashing cost ($10) on
Path 1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $43.
17-67
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week). Step 4: Activity 11-13 (first week) & Activity 4-6
(first week). Step 5: Activity 11-13 (second week) & Activity 1-4 (first week).
17-68
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 6:
The paths and their expected duration are shown below:
Path Expected Duration
1-2-5-7-11-13 30
1-3-8-11-13 30
1-3-9-12-13 20
1-4-6-10-12-13 30
Critical paths are 1-2-5-7-11-13, 1-3-8-11-13, & 1-4-6-10-12-13.
2-5 $24
5-7 $30
11-13 $36
11-13 $36
8-11 $40
4-6 $13
10-12 $14
1-4 $15
12-13 $26
Activity 1-2 should be shortened 1 week because it has the lowest crashing cost ($22) on
Path 1-2-5-7-11-13, which will decrease 1 week as shown below.
Activity 1-3 should be shortened 1 week because it has the lowest crashing cost ($12) on
Path 1-3-8-11-13, which will decrease 1 week as shown below.
Activity 6-10 should be shortened 1 week because it has the lowest crashing cost ($12) on
Path 1-4-6-10-12-13, which will decrease 1 week as shown below.
The combined crashing cost = $46.
Activities crashed to this point: Step 1: 7-11 (first week). Step 2: 1-2 (first week). Step 3: 7-
11 (second week) & 6-10 (first week). Step 4: Activity 11-13 (first week) & Activity 4-6
17-69
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
(first week). Step 5: Activity 11-13 (second week) & Activity 1-4 (first week). Step 6:
Activity 1-2 (second week), Activity 1-3 (first week), & Activity 6-10 (second week).
17-70
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
1-2-5-7-11-13 35 34 33 32 31 30 29
1-3-8-11-13 32 32 32 32 31 30 29
1-3-9-12-13 20 20 20 20 20 20 20
1-4-6-10-12-13 33 33 33 32 31 30 30
Activity Cost Activity Cost Activity Cost Activity Cost Activity Cost Activity Cost
7-11 $15 1-2 $18 7-11 $20 11-13 $30 11-13 $33 1-2 $22
$46
Total crashing cost = $15 + $18 + $25 + $38 + $43 + $46 = $185.
The table below summarizes the cumulative crashing cost, indirect cost, and total cost for
project lengths of 35, 34, 33, 32, 31, 30, and 29 weeks:
17-71
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Crash Cost
Weeks
Length Shortened ($000) ($000) ($000)
17-72
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
1,400
Total
Cost
($000)
1,300
0 3031 32333435
29
Project Length
(weeks)
17-73
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
16. Given:
We have the following crashing costs for activities:
M
L P Z
Start K Q Y
End
N J
Develop a crashing schedule given that Mr. T wants delivery in 32 weeks or he will impose a
penalty of $375 for each week his yacht is late:
We will crash as long as the crash cost at a step ≤ $375.
17-74
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 1:
The paths and their expected duration are shown below:
L $125
Q $200
M $300
K $410
K-N-J-Q-P-Z N $45
J $50
Z $90
Q $200
K $410
Activity Z should be shortened 1 week because it has the lowest crashing cost ($90) to crash
both critical paths, which both will decrease by 1 week as shown below. This cost is ≤ $375.
Activities crashed to this point: Step 1: Activity Z (1 st week).
17-75
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 2:
The paths and their expected duration are shown below:
Q $200
M $300
K $410
K-N-J-Q-P-Z N $45
J $50
Q $200
K $410
Activity L should be shortened 1 week because it has the lowest crashing cost ($125) on Path
K-L-M-Q-P-Z, which will decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week as shown
below.
Activity N should be shortened 1 week because it has the lowest crashing cost ($45) on Path
K-N-J-Q-P-Z, which will decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week as shown
below.
Combined crashing cost = $170. This cost is ≤ $375.
Activities crashed to this point: Step 1: Activity Z (1 st week). Step 2: Activity L (1st week) &
Activity N (1st week).
17-76
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 3:
The paths and their expected duration are shown below:
M $300
K $410
K-N-J-Q-P-Z N $45
J $50
Q $200
K $410
Activity Q should be shortened 1 week because it has the lowest crashing cost ($200) to
crash both critical paths. This cost is ≤ $375. All four paths will decrease by 1 week as shown
below.
Activities crashed to this point: Step 1: Activity Z (1 st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week).
17-77
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 4:
The paths and their expected duration are shown below:
M $300
K $410
K-N-J-Q-P-Z N $45
J $50
Q $225
K $410
Activity Q should be shortened 1 week because it has the lowest crashing cost ($225) to
crash both critical paths. This cost is ≤ $375. All four paths will decrease by 1 week as shown
below.
Activities crashed to this point: Step 1: Activity Z (1 st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week). Step 4: Activity Q (2nd week).
17-78
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 5:
The paths and their expected duration are shown below:
K $410
K-N-J-Q-P-Z N $45
J $50
K $410
Activity M should be shortened 1 week because it has the lowest crashing cost ($300) on
Path K-L-M-Q-P-Z, which will decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week as
shown below.
Activity N should be shortened 1 week because it has the lowest crashing cost ($45) on Path
K-N-J-Q-P-Z, which will decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week as shown
below.
Combined crashing cost = $345. This cost is ≤ $375.
Activities crashed to this point: Step 1: Activity Z (1 st week). Step 2: Activity L (1st week) &
Activity N (1st week). Step 3: Activity Q (1st week). Step 4: Activity Q (2nd week). Step 5:
Activity M (1st week) & Activity N (2nd week).
17-79
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Step 6:
The paths and their expected duration are shown below:
K $410
K-N-J-Q-P-Z J $50
K $410
Activity M could be shortened 1 week because it has the lowest crashing cost ($350) on Path
K-L-M-Q-P-Z, which would decrease Paths K-L-M-Q-P-Z & K-L-M-Q-Y 1 week.
Activity J could be shortened 1 week because it has the lowest crashing cost ($50) on Path
K-N-J-Q-P-Z, which would decrease Paths K-N-J-Q-P-Z & K-N-J-Q-Y 1 week.
However, combined crashing cost = $400. This cost is > $375. Stop.
17-80
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
K-L-M-Q-P-Z 39 38 37 36 35 34
K-L-M-Q-Y 32 32 31 30 29 28
K-N-J-Q-P-Z 39 38 37 36 35 34
K-N-J-Q-Y 32 32 31 30 29 28
Activity Cost Activity Cost Activity Cost Activity Cost Activity Cost
N $ 45 N $ 45
$170 $345
17-81
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-82
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17. Given:
Top A 4 5 6
B 7 8 10
C 3 5 9
Bottom D 7 8 11
E 2 3 4
F 1 4 6
2 B 4
A C
Start 1 End
F
D
3 E 5
Standard
Deviation
Path Activity Optimistic Most Likely Pessimistic Mean
17-83
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
B 7 8 10 8.17 9/36
C 3 5 9 5.33 36/36
E 2 3 4 3.00 4/36
F 1 4 6 3.83 25/36
Path A-B-C:
Expected completion time = 5.00 + 8.17 + 5.33 = 18.50
Variance = 4/36 + 9/36 + 36/36 = 49/36
Path D-E-F:
Expected completion time = 8.33 + 3.00 + 3.83 = 15.16
Variance = 16/36 + 4/36 + 25/36 = 45/36
17-84
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
b. Determine the probability that the project will take at least 18 days.
Probability (T ≥ 18):
Path A-B-C:
Standard deviation =
√ 49
36
=1.167
18−18.50
z= =−0.43
1.167
Using Appendix B Table B: Probability of completion < 18 days = 0.3336
Path D-E-F:
Standard deviation =
√ 45
36
=1.118
18−15.16
z= =2.54
1.118
Using Appendix B Table B: Probability of completion < 18 days = 0.9945
17-85
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
18. Given:
We are given the events, probabilities, and costs in the table below:
1 .25 15
2 .35 25
3 .20 55
4 .80 10
5 .10 77
6 .40 55
7 .60 50
Create a risk matrix for this project. Use a vertical scale of $0 to $80.
$80
5
17-86
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
19. Given:
We are given the events, probabilities, and costs in the table below:
$200
2
$150
Cost $100
5
6
$50
4
17-87
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Probability of Occurring
The weather problems (4) and funding delays (5) are placed using the highest probabilities
because we are conservative (i.e., we will assume the worst case).
Conclusion: The manager should be most concerned about Event 2 (vendor is late with key
segment) due to its greater than 50% probability and its high cost.
17-88
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
17-89
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Expected Standard
Path Duration (weeks) Deviation
A 10 4
B 14 2
C 13 2
Project duration for Smitty to include in the proposal for a 5% risk of not delivering the project on
time:
This means we would like a 0.9500 probability of completion within the specified time. When we take the
probability of completion within the specified time for each path and multiply these probabilities, we
need to obtain a joint probability of at least 0.9500.
Next, we can analyze the length of each path if we use this corresponding z value (1.645):
We know that we need all three probabilities to be > 0.9500; therefore we can start by focusing on the
longest path (Path B) and specify the project completion time as 17.29 days as a starting point.
17-90
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
We can set up a spreadsheet in Excel to automate our calculations. To find a probability for a z value
using Excel, we enter the following formula: =NORMSDIST(z), where z = the cell where we have
calculated z.
Column
Row A B C D E
2 A 10 4 1.8225 0.9658
3 B 14 2 1.645 0.9500
4 C 13 2 2.145 0.9840
5 Completion = 17.29
As shown above, the probability of completing the project within 17.29 days is 0.9028, which is less than
0.9500.
From here, we can experiment by entering project completion times greater than 17.29 days until the
value in Cell E6 is close to 0.9500. An alternate approach would be to create a simple Excel Solver model
to solve this. Note: We will carry the project completion time to two decimals.
After experimentation, a project completion time of 18.02 days gives us a probability of project
completion of 0.9501 as shown in the table below.
Column
Row A B C D E
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
2 A 10 4 2.005 0.9775
3 B 14 2 2.01 0.9778
4 C 13 2 2.51 0.9940
5 Completion = 18.02
17-92
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
Project duration for Smitty to include in the proposal for a 10% risk of not delivering the project
on time:
This means we would like a 0.9000 probability of completion within the specified time.
We know that when we started with a project completion of 17.29 days above, the probability of
completion was 0.9028 (just above 0.9000).
We can lower the project completion time from 17.29 until the value in Cell E6 is close to 0.9000. As
shown in the table below, a project completion time of 17.26 days provides a probability of completion of
0.9002.
Column
Row A B C D E
2 A 10 4 1.815 0.9652
3 B 14 2 1.63 0.9484
4 C 13 2 2.13 0.9834
5 Completion = 17.26
Project duration for Smitty to include in the proposal for a 15% risk of not delivering the project
on time:
This means we would like a 0.8500 probability of completion within the specified time.
We know that when we used a project completion of 17.26 days above, the probability of completion was
0.9002.
We can lower the project completion time from 17.26 until the value in Cell E6 is close to 0.8500. As
shown in the table below, a project completion time of 16.78 days provides a probability of completion of
0.8506.
Column
Row A B C D E
2 A 10 4 1.695 0.9550
17-93
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.
Chapter 17 - Project Management
3 B 14 2 1.39 0.9177
4 C 13 2 1.89 0.9706
5 Completion = 16.78
The pros of quoting project times aggressively are the ability to secure new business or to win project
approval.
The cons of quoting project times aggressively are the increased probability of missing the deadline,
which could lead to severe consequences for the project manager.
The pros of quoting project times conservatively are the increased probability of meeting the deadline.
The cons of quoting project times conservatively are the reduced likelihood of being able to secure new
business or to gain project approval.
17-94
Copyright © 2015 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill
Education.