Professional Documents
Culture Documents
Grid Station Presentation
Grid Station Presentation
Grid standards
alka
NPTI, PSTI
Bangalore
1
CEA’s Standards for
Grid Connectvity
2
1.Transmission system Planning & Design
3
1.Transmission system Planning & Design
ii. The integrity of the regional grid is not affected under various
operating conditions including stipulated system contingencies
a. all elements of the transmission system shall be designed
taking into account the specified factors of safety in regard to
electrical, mechanical and civil aspects in the respective
standards
b. optimal system to be chosen after performing load flow, short
circuit, stability studies of the various transmission alternative
4
2. Overhead Transmission Lines
i. The transmission line proposed to be connected shall be
comply with the following
a. Tower design shall be based on the technical standards for the
construction of electrical lines specified by the authority under
section 73(b) of the Act
b. Foundation design for the tower to be developed by the
transmission licensee for various soil categories.
c. Use of multi circuit and narrow based towers wherever ROW
constraints exist
d. Each type of tower to be type tested for mechanical strength
5
3. EHV/HV Underground Cables
i. Cables proposed to be connected to the system, shall comply with the
following
a. Shall be of XLPE type corresponding to IS 7098
b. Cable conductor to be of adequate size considering continuous current,
short circuit current, voltage drop etc, & shall correspond to IS-8130
c. Cables to be provided with proper sheathing, armoring & screening
d. Prior permission from appropriate authority to be obtained for digging
trenches, precautions to be taken
e. Route maps to be kept at Substation & markers shall be fixed to trace the
cables
f. Road crossing to be carried out by providing Hume pipes or GI pipes
g. Jointing & termination to be carried out as per relevant standards
8
4. Substations
Planning and design of substations to be based on the following
xii. Power Supply to the sub station auxillaries
a. AC Supply;
2 HT supplies shall be arranged from independent sources. In
addition, a DG set of suitable capacity to be provided
b. DC Supply:
2 sets of 220 V batteries each equipped with own charger for
substations of 220 kV & above. 2 sets of 50 V batteries for
PLCC system.
for substations of 132 kV & below, 1 set of battery each to be
provided
xii. For high current, XLPE cables to be employed. For LV/MV
systems, PVC cables corresponding to IS-1554, can be
employed 9
4. Substations
Planning and design of substations to be based on the following
xiv. Reliable communication link shall be provided on all EHT
lines for voice, Fax, protection, telemetry & SCADA
xv. Substation grounding shall be done in accordance with IEEE-
80
xvi. Size and no. of ICTs to be selected such that outage of one
shouldn’t overload the remaining ICTs or the underlying
system
xvii. The stuck breaker condition in the substation shall not cause
disruption of more than 4 feeders in 132 or 220 kV system,
more than 2 feeders in 400 kV system and more than one
feeder in 765 kV system
xviii. In substations of 220 kV and above, control room, PLCC
room, Relay testing room and electronic laboratory shall be air
conditioned
10
5. Earth Fault Factor
In the event of a point in the EHT system of a transmission licensee
being earthed, the Earth fault Factor shall be less than 1.4
6. Electromagnetic Compatibility
A line or equipment in the transmission system shall not generate
excessive electromagnetic field and the RIV (radio
interference voltage) shall be within permissible limits as per
relevant standards
11
7. Insulation coordination
i. For new connections, the CTU/ STU/ transmission licensee,
shall inform the transmission users seeking connectivity, the
BIL and important parameters of the equipment and ratings of
the surge arresters in its system adjacent to the connection
point.
ii. The transmission users and licensees seeking connectivity
shall furnish to the CTU/ STU, the BIL of the proposed
system/ important items of the equipment and the rating of the
surge arresters adjacent to the connection point
iii. The CTU/ STU/ transmission licensee shall determine the
ratings of the surge arresters to be installed at the connection
point
iv. Requisite insulation coordination to be done by the CTU/
STU/ transmission licensee.
12
8. Grid standards
The transmission utility, transmission licensee and the load dispatch
center shall comply with the CEA’s Grid standards
13
Grid Standards
14
1. Short title and commencement and application
2. Definitions
•Bulk consumer – means a consumer who avails supply at
voltages of 33 kV or above
•Entity - means a Generating company or a transmission licensee
or a distribution licensee or a bulk consumer
•Voltage Unbalance – Ratio of the maximum voltage deviation of
the phase voltage from the average phase voltage to the average
phase voltage 15
3. Standards for operation and
maintenance of transmission lines
All entities
LDCs
RPCs
a) Frequency Control
Operating Range : 49.5 to 50.2 Hz or as per grid
code, except during the transient period
following tripping.
16
b) Operating Voltage Limits
S.No. Normal system Maximum (kV Minimum (kV
Voltage (kV rms) rms)
rms)
1 765 800 728
5 110 121 99
6 66 72 60
7 33 36 30
17
c) Temporary over voltage range d) voltage unbalance limits
3 220 283 2
4 132 170 3
5 33 Decided by the state 3
commission in the respective
State grid code
18
e) Max fault clearance time
19
f) Grid shall with stand one of the following
contingencies without loss of stability
20
g) N-1 criteria for system stability- system shall
be stable for one of the following contingencies
Tripping of single largest generating unit
Transient SLG fault of a 765 kV line close to bus
A SLG Fault on 400 kV line and isolation of the line
A fault on one circuit of a 400 kV double circuit line in
operation
A transient SLG fault in one of the 400 kV double circuit
line when the second circuit is already under outage
A 3 ph fault in 220 kV or 132 kV line
A fault in one pole of HVDC bipolar in a HVDC
Converter station
21
h) Limits for harmonic distortion in
Transmission systems
S.No. System Voltage (kV rms) Total harmonic Individual
distortion (%) Harmonic of any
particular
frequency (%)
1 765 1.5 1.0
22
4. Operations planning
Regional Power Committee shall periodically review the
performance of the grid for the past period
RPC shall plan stable operation of the grid for future,
considering various parameters and occurrences such as
frequency profile,
voltage profile,
line loading,
grid incident,
grid disturbance,
performance of protection schemes and
protection coordination
23
5. Maintenance planning
The RPC shall prepare annual maintenance plan for
Generating stations, ISTS
Coordinate the annual maintenance plan for inter
regional transmission system
Organise monthly operating committee meetings in the
region to review and revise the coordinated generation and
transmission system plan
The SLDC shall do the above for intra-state constituents
in consultation with the concerned transmission licensees
The generating company/ transmission licensee shall
obtain approval of the appropriate LDC before actual shut
down
24
6. Coordination in operations
25
7. Operating instructions
Every generating company and transmission licensee shall
provide written operating instructions for each equipment
and operating procedure for sequence of operations of power
system equipment in their control room
26
8. RLDCs and SLDCs Instructions’ to be
recorded
27
9. Under frequency relay settings
All entities shall set their UF relays and DF/DT relays in
accordance with RPC plan to provide adequate load relief for
grid security and ensure the operation of these relays at the set
frequencies.
28
10. Islanding schemes
29
11. Categorization of Grid incident and
Grid disturbance based on severity
31
12. Reporting of events affecting grid operation
32
13. Reporting of grid disturbance
• The RLDC shall inform occurrence of the grid
disturbance to the constituents and RPC at the
earliest
37
18. Safety procedure
The entity shall prepare contingency
procedures for use of operators at each
sub-station and switchyards and these shall be
regularly updated.
38
19. Maintenance of tools and equipment
39
20. Maintenance procedures
40
21. Hot line methods
41
22. Emergency Restoration System
Each transmission licensee shall have an arrangement for
restoration of transmission lines of 400 kV and above and
strategic 220 kV lines through the use of emergency restoration
system in order to minimise the outage of the Transmission
Lines in case of tower failures.
42
23. Inspection and patrolling
• All essential parameters which indicate the
healthiness of the equipment in a sub station,
shall be inspected by the shift engineer once
in each shift and periodically by the officer in
charge.
45
26. Thermo-vision scanning
46
27. Failure Analysis
All failures of the equipment and tower collapse shall be
analyzed by the entity to avoid recurrence and a copy of the
report shall be submitted to the RPC and Authority
The authority may appoint a group of experts for investigation
and analysis and the representatives of the manufacturers may
be invited to participate in such analysis.
All relevant data which may help the group of experts in
analysing the failures shall be furnished by the respective
Entities.
The recommendations of the group of experts shall be
submitted to the authority and the recommendations accepted
by the authority shall be implemented and circulated to all
within the organisation and to other organisations to prevent
recurrence of such failures. 47
28. Inventory Control and Spare Parts
Management
48
29. Maintenance Audit
49
30. Residual Life Assessment
50
31. Disaster Management
51
32. Maintenance records
52
33. Training
• Every person involved in O&M of transmission lines shall be
trained at the induction level and at least once in a year.
54