Numerical 1- (by wall by wall method): -

Numerical 2- (by wall by wall method): -


Numerical 1- (by Canter line method): -
Item no Description of item No. Length Breadth Height/Depth Quantity Notes
1 Excavation 1 19.2 0.9 0.9 15.552 Total=(6.2*2+4.3*2)-(1/2*0.9*4)
2 Concrete in foundation 1 19.2 0.9 0.3 5.184
3 brickwork in foundation
1st footing 1 19.8 0.6 0.3 3.564 Total=(6.2*2+4.3*2)-(1/2*0.6*4)
2st footing 1 20 0.5 0.3 3 Total=(6.2*2+4.3*2)-(1/2*0.5*4)
plinth wall above footing 1 20.2 0.4 0.6 4.848 Total=(6.2*2+4.3*2)-(1/2*0.4*4)
Total(cu.m) 11.412
5 Brickwork in super structure 1 19.2 0.3 3.5 20.16
Total Brickwork 31.572 total brickwork=SUM(G8,G9)

Numerical 2- (by Canter line method): -


Item no Description of item No. Length Breadth Height/Depth Quantity Notes
1 Excavation 1 39 1.1 1 42.9 Lenght=(6.3*3+10.6*2)-(1/2*1.1*2)
2 Concrete in foundation 1 39 1.1 0.3 12.87 Lenght=(6.3*3+10.6*2)-(1/2*1.1*2)
3 brickwork in foundation
1st footing 1 39.3 0.8 0.2 6.288 Lenght=(6.3*3+10.6*2)-(1/2*0.8*2)
2st footing 1 39.4 0.7 0.2 5.516 Lenght=(6.3*3+10.6*2)-(1/2*0.7*2)
3st footing 1 39.5 0.6 0.1 2.37 Lenght=(6.3*3+10.6*2)-(1/2*0.6*2)
4th footing 1 39.6 0.5 0.1 1.98 Lenght=(6.3*3+10.6*2)-(1/2*0.5*2)
plinth wall above footing 1 39.7 0.4 0.8 12.704 Lenght=(6.3*3+10.6*2)-(1/2*0.4*2)
Total(cu.m) 28.858
4 DPC 39.7 0.4 0.02 0.3176 Length=(6.3*3+10.6*2)-(1/2*0.4*2)
5 Brickwork in super structure 39.8 0.3 4.2 50.148 Length=(6.3*3+10.6*2)-(1/2*0.3*2)
Total brickwork 79.006 Total=SUM(G10,G12)
After Deduction 74.608
6 Deduction for
doors 2 1.2 0.3 2.1 1.512
windows 4 1 0.3 1.5 1.8
shelves 2 1 0.2 1.5 0.6
Total(cu.m) 3.912
7 Lintels
doors 2 1.5 0.3 0.15 0.135
windows 4 1.3 0.3 0.15 0.234
shelves 2 1.3 0.3 0.15 0.117
Total(cu.m) 0.486