You are on page 1of 6

MEASUREMENT SHEET OF OPEN AIR THEATER

GREEN ROOM
S.NO. PARTICULAR OF ITEMS NO. LENGTH(m) BREADTH(m) HEIGHT(m) QTY. UNIT
A EXCAVATION
(a) FOOTING 9 1.1 1.1 0.9 9.801
(b) SEATING SLOPE EXCAVATION 1 23.82 11.86 0.3 84.75156
( c ) FIRST STEP 1 17.6 1 0.3 5.28
TOTAL= 99.83256
TOTAL EARTHWORK= 99.83256 CUM.
B CONCRETING
(a) CONC. IN FOUNDATION BLOCK 9 1.1 1.1 0.3 3.267
(1:3:6)
(b) CONC. IN FOUNDATION SLOPE
VOLUME OF CONC. BLOCK 9 0.4 0.4 0.6 0.864
VOLUME OF TRIANGLE 9 1.1 0.7 0.6 4.158
VOLUME OF SMALL TRIANGLE 9 0.4 0.7 0.6 1.512
( c) CONC. IN COLUMN 9 0.3 0.3 2.55 2.0655
(d) CONC. IN DOOR D1 LINTEL(1:1.5:3) 2 1.1 0.13 0.15 0.0429
(e) CONC. IN DOOR D2 LINTEL 2 1.05 0.13 0.15 0.04095
(f) CONC. IN DOOR D3 LINTEL 2 0.95 0.13 0.15 0.03705
(g) CONC.IN BEAMS( LONG) 3 6.6 0.3 0.45 2.673
(i) CONC. IN BEAMS( SHORT) 3 5.5 0.3 0.45 2.2275
(J) CONC.IN PLINTH BEAMS (LONG) 3 6.6 0.35 0.5 3.465
(k) CONC. IN PLINTH BEAMS(SHORT) 3 5.5 0.35 0.5 2.8875
TOTAL= 19.0824 CUM.
(l) CONC.IN SEATING
BASE SLAB 1 23.82 11.86 0.2 56.50104
STEPS (FIRST STEP) 1 17.6 1 0.15 2.64
STEPS IN SLOPE {1/2*(L*B*H)} 12 23.82 0.7 0.15 15.0066
PASSAGE 1 {1/2*(L*B*H)} 1 21.34 1 0.15 1.6005
PASSAGE 2 {1/2*(L*B*H)} 1 27.8 1.2 0.15 2.502
TOTAL= 78.25014
TOTAL CONCRETING= 97.33254 CUM.
C BRICK WORK
(a) LONG WALL (L.W.) 2 3.5 0.23 2.55 4.1055
(b) SHORT WALL (S.W.) 4 2.85 0.23 2.55 6.6861
( c) LONG WALL (l.w.) 2 2.06 0.13 2.55 1.36578
(d) SHORT WALL (s.w.) 2 1 0.13 2.55 0.663
(e) PARTITION WALL 1 3.5 0.13 2.55 1.16025
(f) W.C. L.W. 2 1.3 0.13 2.55 0.8619
W.C. S.W. 2 1.17 0.13 2.55 0.77571
(g) STAGE ENTERANCE WALL 1 6 0.23 2.55 3.519
(h) STAGE OVERLAP WALL 1 4 0.23 3 2.76
(i) STAGE SIDE WALLS 2 3 0.23 3 4.14
(j) BRICKWORK IN DUCT L.W. 2 0.63 0.13 3 0.4914
(k) BRICKWORK IN DUCT S.W. 2 0.3 0.13 3 0.234

CUM.
(l) STEPS IN GREEN ROOM 4 2 0.3 0.185 0.444
(j) STEPS IN STAGE 4 1.5 0.3 0.185 0.333
TOTAL= 27.53964 CUM.
DEDUCTION
(a) WINDOW 2 1.5 0.23 1.5 1.035
LINTEL 2 1.7 0.23 0.15 0.1173
VENTILATOR 4 0.5 0.23 0.3 0.138
LINTEL 4 0.7 0.23 0.15 0.0966
(b) DOORS D1 2 0.9 0.13 2 0.468
LINTEL 2 1.1 0.13 0.15 0.0429
D2 2 0.85 0.13 2 0.442
LINTEL 2 1.05 0.13 0.15 0.04095
(c ) STAGE ENTERANCE OPENING 1 2.6 0.23 2.55 1.5249
( d) DUCT SHUTTER 2 0.4 0.13 2 0.208
TOTAL= 4.11365
TOTAL BRICK WORK= 23.42599 CUM.
S.NO. PARTICULAR OF ITEMS NO. LENGTH(m) BREADTH(m) HEIGHT(m) QTY. UNIT
D PLASTERING (INTERNAL)
(a) LONG WALL (L.W.) 2 3.64 3 21.84
(b) SHORT WALL (S.W.) 4 2.995 3 35.94
( c) LONG WALL (l.w.) 2 2.06 3 12.36
(d) SHORT WALL (s.w.) 1 1 3 3
(e) PARTITION WALL 2 3.87 3 23.22
(f) W.C. L.W. 2 1.3 3 7.8
S.W. 2 1.17 3 7.02
(g) DUCT (L.w) 2 0.63 3 3.78
(h) DUCT (s.w.) 2 0.43 3 2.58
(i) STAGE ENTERANCE WALL 2 6.6 3 39.6
(j) STAGE SIDE WALLS 2 2.7864 3 16.7184
(k) STAGE OVERLAP WALL 2 4 3 24
(l) ENTERANCE WALL SIDES 2 0.23 2.55 1.173
(m) OVERLAP WALL SIDES 2 0.3 3 1.8
TOTAL= 200.8314 SQ.M.
DEDUCTION OF PLASTERING
(a) WINDOW 2 1.5 1.5 4.5
VENTILATOR 4 0.5 0.3 0.6
(b) DOORS D1 2 0.9 2 3.6
D2 4 0.75 1.8 5.4
( c) SWITCH BOARD
S1 2 0.3 0.25 0.15
S2 2 0.25 0.12 0.06
S3 2 0.1 0.1 0.02
(d) DUCT SHUTTER 2 0.4 2 1.6
(e) STAGE ENTERANCE OPENING 2 1.15 2.55 5.865
TOTAL= 21.795 SQ.M.
ADDITION
(a) WINDOW EXTENTION 1 4 1.5 0.07 0.42
WINDOW EXTENTION 2 4 0.07 1.5 0.42
(b) VENTILATOR EXTENTION 1 8 0.5 0.07 0.28
VENTILATOR EXTENTION 2 8 0.07 0.3 0.168
( C) DOOR (D2) EXTENTION 1 4 0.75 0.035 0.105
DOOR (D2) EXTENTION 2 8 0.035 2 0.56
(d) BEAM EXTENTION( LONG) 4 5.8 0.07 1.624
BEAM EXTENTION( SHORT) 6 2.85 0.07 1.197
TOTAL= 4.774
TOTAL INTERNAL PLASTERING= 183.8104 SQ.M.
E PLASTERING (EXTERNAL)
(a) LONG WALL (L.W.) 2 6.6 3 39.6
(b) SHORT WALL (S.W.) 2 4.1 3 24.6
( C) STAGE SIDE WALLS 2 3 3 18
(d) COLUMN SIDES 2 0.3 2.55 1.53
(e) GREEN ROOM STEPS RISE 6 2 0.175 2.1
(f) GREEN ROOM STEPS TREAD 4 2 0.3 2.4
(g) STEGE STEPS RISE 6 1.5 0.175 1.575
(h) STAGE STEPS TREAD 4 1.5 0.3 1.8
TOTAL= 91.605 SQ.M.
DEDUCTION OF PLASTERING
(a) WINDOW 2 1.5 1.5 4.5
(b) VENTILATOR 4 0.5 0.3 0.6
( c ) GREEN ROOM OPENING 2 0.9 2 3.6
TOTAL= 8.7 SQ.M.
ADDITION
(a) WINDOW EXTENTION 1 4 1.5 0.07 0.42
WINDOW EXTENTION 2 4 0.07 1.5 0.42
(b) VENTILATOR EXTENTION 1 8 0.5 0.07 0.28
VENTILATOR EXTENTION 2 8 0.07 0.3 0.168
( C) DOOR EXTENTION (D1) 1 2 0.9 0.035 0.063
DOOR EXTENTION (D1) 2 4 0.035 2 0.28
TOTAL= 1.631
TOTAL EXTERNAL PLASTERING= 84.536
TOTAL PLASTERING(INTERNAL ,EXTERNAL)= 268.3464 SQ.M.
F PAINTING (INTERNAL)
(a) LONG WALL (L.W.) 2 3.64 3 21.84
(b) SHORT WALL (S.W.) 2 2.995 3 17.97
( c) LONG WALL (l.w.) 2 1.87 3 11.22
(d) SHORT WALL (s.w.) 1 1 3 3
(e) PARTITION WALL 2 3.87 3 23.22
(f) W.C. L.W. 4 1.15 3 13.8
S.W. 4 1 3 12
(g) DUCT (L.w) 2 0.63 3 3.78
(h) DUCT (s.w.) 2 0.43 3 2.58
(i) STAGE ENTERANCE WALL 2 6.6 3 39.6
(j) STAGE SIDE WALLS 2 2.7864 3 16.7184
(k) STAGE OVERLAP WALL 2 4 3 24
(l) ENTERANCE WALL SIDES 2 0.23 2.55 1.173
(m) OVERLAP WALL SIDES 2 0.3 3 1.8
SQ.M.
TOTAL= 192.7014 SQ.M.
DEDUCTION
(a) WINDOW 2 1.5 1.5 4.5
VENTILATOR 4 0.5 0.3 0.6
(b) DOORS D1 2 0.9 2 3.6
D3 4 0.75 1.8 5.4
( c) SWITCH BOARD
S1 2 0.3 0.25 0.15
S2 2 0.25 0.12 0.06
S3 2 0.1 0.1 0.02
(d) SKIRTING
LONG WALL (L.W.) 2 3.64 0.1 0.728
SHORT WALL (S.W.) 2 2.995 0.1 0.599
LONG WALL (l.w.) 2 1.87 0.1 0.374
SHORT WALL (s.w.) 1 1 0.1 0.1
PARTITION WALL 2 3.87 0.1 0.774
(e) WC TILING
LONG WALL (L.W.) 4 1.17 2 9.36
SHORT WALL (S.W.) 2 1.17 2 4.68
EXTENTION 1 2 0.32 2 1.28
EXTENTION 2 2 0.1 2 0.4
TOTAL= 32.625 SQ.M
ADDITION
(a) WINDOW EXTENTION 1 4 1.5 0.07 0.42
WINDOW EXTENTION 2 4 0.07 1.5 0.42
(b) VENTILATOR EXTENTION 1 8 0.5 0.07 0.28
VENTILATOR EXTENTION 2 8 0.07 0.3 0.168
( C) DOOR (D2) EXTENTION 1 4 0.75 0.035 0.105
DOOR (D2) EXTENTION 2 8 0.035 2 0.56
(d) BEAM EXTENTION( LONG) 4 5.8 0.07 1.624
BEAM EXTENTION( SHORT) 6 2.85 0.07 1.197
TOTAL= 4.774
TOTAL INTERNAL PAINTING = 164.8504 SQ.M
G PAINTING (EXTERNAL)
(a) LONG WALL (L.W.) 2 6.6 3 39.6
(b) SHORT WALL (S.W.) 2 4.1 3 24.6
( C) STAGE SIDE WALLS 2 3 3 18
(d) COLUMN SIDES 2 0.3 2.55 1.53
(e) GALLERY BEAMS BIDTH 3 0.3 2 1.8
TOTAL= 85.53 SQ.M.
DEDUCTION
(a) WINDOW 2 1.5 1.5 4.5
(b) VENTILATOR 4 0.5 0.3 0.6
(c ) GREEN ROOM OPENING 2 0.9 2 3.6
TOTAL= 8.7 SQ.M.
ADDITION
(a) WINDOW EXTENTION 1 4 1.5 0.07 0.42
WINDOW EXTENTION 2 4 0.07 1.5 0.42
(b) VENTILATOR EXTENTION 1 8 0.5 0.07 0.28
VENTILATOR EXTENTION 2 8 0.07 0.3 0.168
(c ) DOOR EXTENTION (D1) 1 2 0.9 0.035 0.063
DOOR EXTENTION (D1) 2 4 0.035 2 0.28
TOTAL= 1.631
TOTAL EXTERNAL PAINTING= 78.461
TOTAL INTERNAL, EXTERNAL PAINTING= 243.3114 SQ.M.
H CELING PAINTING
(a) GREEN ROOMS 2 2.85 3.5 19.95
(b) GALLERY 2 2.85 2 11.4
(c) BACK STAGE 1 4 0.9 3.6
(d) ROOF SIDE EXTENSION 1 2 1.64 0.74 2.4272
ROOF SIDE EXTENSION 2 2 1 8.98 17.96
ROOF FRONT EXTENSION 3 1 4 0.74 2.96
ROOF BACK EXTENSION 4 1 8.6 1 8.6
(e) STAGE GABLE 2 1.7 2.9 9.86
TOTAL= 76.7572 SQ.M.
DEDUCTION
GREEN ROOM DUCTS 2 0.355 0.56 0.3976
W.C WALL (LONG) 2 1.3 0.13 0.338
W.C WALL (SHORT) 2 1.1 0.13 0.286
CHANGING ROOM WALL(LONG) 2 2.85 0.13 0.741
CHANGING ROOM WALL(SHORT) 2 0.93 0.13 0.2418
TOTAL= 2.0044
TOTAL PAINTING IN CELING = 74.7528 SQ.M.
I FLOORING
(a) GREEN ROOMS 2 2.995 3.64 21.8036
(b) GALLERY 1 8.6 2 17.2
( c)GREEN ROOM SIDE SPACE 2 1 5.1 10.2
(d) GREEN ROOM BACK SPACE 1 6.6 1 6.6
(e) GREEN ROOM STEPS 4 2 0.3 2.4
(f)SKIRTING
LONG WALL (L.W.) 2 3.64 0.1 0.728
SHORT WALL (S.W.) 2 2.995 0.1 0.599
LONG WALL (l.w.) 2 1.87 0.1 0.374
SHORT WALL (s.w.) 1 1 0.1 0.1
PARTITION WALL 2 3.87 0.1 0.774
GALLERY 1 10.96 0.1 1.096
(g) STAGE FLOORING
RECTANGULAR PORTION 1 1 6.6 6.84 45.144
RECTANGULAR PORTION 2 2 1.5 1.8 5.4
TRIANGULAR PORTION{1/2(B*H)} 1 5 4.33 10.825
CIRCULAR SEGMENT 1 1 5.785 1.04 1155.6
{R^2/2(ANGLE - SIN ANGLE)}
CIRCULAR SEGMENT 2 2 1.09 0.3 51.09
{R^2/2(ANGLE - SIN ANGLE)}
TOTAL= 1329.934 SQ.M.
DEDUCTION
OVERLAP WALL 1 4 0.3 1.2
STAGE SIDE WALLS 2 3 0.23 1.38
TOTAL= 2.58
TOTAL FLOORING= 1327.354 SQ.M.
J WOODWORK
i CHOWKHAT
(a) CHOWKHAT OF DOOR D1 2 4.9 0.7 0.12 0.8232
CHOWKHAT OF DOOR D2 4 4.75 0.7 0.12 1.596
(b) CHOWKHAT OF WINDOWS SILL 4 1.5 0.7 0.12 0.504
CHOWKHAT OF VERTICAL POST 4 1.5 0.7 0.12 0.504
WINDOE MULLION 2 1.5 0.7 0.12 0.252
(c ) VENTILATOR VIRTICAL POST 8 0.3 0.7 0.12 0.2016
VENTILATOR HORIZONTAL 8 0.5 0.7 0.12 0.336
(d) DUCT 2 4.4 0.7 0.12 0.7392
TOTAL= 4.956 CUM.
ii SHUTTER (40mm THICKNESS)
(e) DOOR SHUTTER D1 2 0.9 2 3.6
(f) DOOR SHUTTER D2 4 0.75 2 6
TOTAL= 9.6 SQ.M.
K ACCESSORIES
HINGES 38 38
HANDLE 26 26
SLIDING BOLT 6 6
DOOR STOPPER 6 6
LATCHES 26 26
HOOK 8 8 NO.

You might also like