You are on page 1of 110

QUANTITY ESTIMATION

ITEM
NO PARTICULAR NO LENGTH(m) BREADTH(m) HEIGHT(m)

EARTHWORK EXCAVATION IN
1 FOUNDATION 1 78.1 0.8 1.25

EARTHWORK EXCAVATION IN
2 STEPS 2 1.1 0.65 0.15

TOTAL QUANTITY OF EARTWORK EXCAVATION=98.314

3 LIME CONCRETE IN FOUNDATION 1 78.1 0.8 0.2

LIME CONCRETE IN STEPS 2 1.1 0.65 0.1

TOTAL QUANTITY OF LIME CONCRETE=12.639


4 RR MASONRY IN FOUNDATION
a)FIRST FOOTING 1 79 0.6 0.6
a)SECOND FOOTING 1 79.675 0.45 0.4

TOTAL QUANTITY OF RR MASONRY=42.78m^3


2.5 cm THICK DAMP PROOF
5 1 79.675 0.45 _
COURSE
DEDUCTION:
D1 3 1 0.45 _
D2 4 0.9 0.45 _
D3 2 0.8 0.45 _
FRONT OPENING
TOTAL DEDUCTION=

TOTAL QUANTITY OF DAMP PROOF COURSE=41m^2


5 FIRST CLASS BRICKWORK IN WALLS 1 80.8 0.2 3
DEDUCTION:
a)D1 3 1 0.2 2.1
b)D2 4 0.9 0.2 2.1
c)D3 2 0.8 0.2 2.1
d)W1 8 1.5 0.2 1.5
e)W2
f)V 1 0.6 0.2 0.6
g)S
h)FRONT OPENING
i)OVER ALL LINTEL 1 80.8 0.2 0.1
TOTAL DEDUCTION=
TOTAL=

FIRST CLASS BRICKWORK IN


6 1 48.2 0.1 0.6
PARAPET

7 FIRST CLASS BRICKWORK IN STEPS


a)FRONT STEP
a) 2 1 0.6 0.2
b) 2 1 0.3 0.2
b)BACK STEP
a)
b)
TOTAL=

TOTAL QUANTITY OF FIRST CLASS BRICKWORK=427m^3


8 RCC WORK FOR LINTEL 1 80.8 0.2 0.1
9 RCC WORK FOR SUNSHADE 1 49 0.6 0.1
10 RCC WORK FOR ROOF SLAB AREA OF ROOF SLAB=131.18 0.1

11 FLOORING

a)VERANDAH 1 1.8 2.3 _


b)OFFICE BED 1 3.5 3.8 _
c)LIVING ROOM 1 3.3 3.5 _
d)BEDROOM 1 1 3.6 3.5 _
e)BEDROOM 2 1 3.5 4.5 _
f)WC 1 1.8 1.3 _
g)TOILET 1 1.9 1.8 _
h)KITCHEN 1 3.6 4.7 _
i)FRONT PORTION OF TOILET 1 1.9 1.8 _
f)FRONT PORTION OF BEDROOM2 1 1.8 3.2 _
ADDITION OF DOORS: _
a)D 3 1 0.2 _
b)D1 4 0.9 0.2 _
c)D2 2 0.8 0.2 _
d)FRONT OPENING 1 5.8 0.2 _
TOTAL QUANTITY OF FLOORING=98.54m^2
12 TOTAL QUANTITY OF TILING=98.54m^2
13 PLASTERING IN WALLS
a)OUTSIDE 1 48.2 _ 3
b)INSIDE 1 106.2 _ 3
c)CORNERS 12 _ 0.2 3
DEDUCTION:
a)D 3 1 _ 2.1
b)D1 4 0.9 _ 2.1
c)D2 2 0.8 _ 2.1
d)W 6 1.5 _ 1.5
f)V 6 0.6 _ 0.6
TOTAL DEDUCTION=
TOTAL=
14 PLASTERING IN PARAPET
a)FRONT AND BACK PORTIONS 2 48.2 _ 0.6
b)TOP PORTIONS 1 48.2 0.1 _
TOTAL=
15) PLASTERING IN STEPS

THREAD 4 1 0.3 _
RISE 4 1 _ 0.15
LOWER RISE 2 1 _ 0.2
END PORTIONS 4 (0.3*0.15)+(0.6*0.2)
TOTAL=

16) PLASTERING IN SUNSHADE


a)HORIZONTAL PORTION 2 49 0.6 _
b)VERTICAL PORTION 1 49 _ 0.1

TOTAL QUANTITY FOR PLASTERING = 443.7

16) TILING TOTAL QUANTITY OF TILING= 98.54 m^2 (SAME AS FLOOR

17) WHITE WASHING TOTAL QUANTITY OF WHITE WASHING=

18) EARTHWORK FILLING


a)VERANDAH 1 16 2.1 0.45
b)OFFICE BED 1 3.3 3.6 0.45
c)DINING HALL 1 5.3 3.3 0.45
d)BEDROOM-1 1 3.4 3.3 0.45
e)BEDROOM-2 1 3.3 4.3 0.45
f)WC 1 1.6 1.1 0.45
g)TOILET 1 1.7 1.6 0.45
h)KITCHEN 1 3.4 4.5 0.45
i)FRONT PORTION OF TOILET 1 1.7 1.6 0.45
J)FRONT PORTION OF ROOM 1 1.6 3 0.45

TOTAL QUANTITY OF EARTHWORK FILLING=52.056m^3


ATION
QUANTITY REMARKS

78.1m^3 L=81.7-9*(0.8/2)

0.214m^3

EXCAVATION=98.314

12.496m^3

0.143m^3

CONCRETE=12.639

28.44m^3 L=81.7-9*(.6/2)=79
14.44m^3 L=81.7-9*(0.45/2)=79.675

RY=42.78m^3
35.85m^2

1.35m^2
1.62m^2
0.72m^2

32.16m^2

COURSE=41m^2
48.48m^3
L=81.7-9*(0.2/2)

1.26m^3
1.52m^3
0.672m^3
3.6m^3
0.072m^3

1.616m^3
8.732m^3
39.478m^3

2.892m^3

0.24m^4
0.09m^4

0.33m^3

CKWORK=427m^3
1.616m^3
2.94m^3
13.118m^3

4.14m^2
13.3M^2
19.25m^2
12.6m^2
15.75m^2
2.34m^2
3.42m^2
16.92m^3
3.42m^2
5.76m^2

0.6m^2
0.72m^2
0.32m^2
1.16m^2
G=98.54m^2
SAME AS FLOORING

144.6m^2
318.6m^2
7.2m^2

6.3m^2
7.56m^2
3.36m^2
13.5m^2
2.16m^2
31.08*2=62.16
378.24

57.84m^2
4.82m^2
62.62m^2

1.2m^2
0.6m^2
0.4m^2
0.66m^2
2.86

58.8
4.9

FOR PLASTERING = 443.72m^2

98.54 m^2 (SAME AS FLOORING)

504.44m^2 (SAME AS PLASTERING)

15.12m^3
5.346m^3
7.8705m^3
5.049m^3
6.385m^3
0.792m^3
1.224m^3
6.885m^3
1.224m^3
2.16m^3

LLING=52.056m^3