24.BILL OF QUANTITY
No. work Discription Unit
item unit Quantity cost Total cost
1 Head work maintenance
1.1 C-20 mass concrete 1:3:6 m3 94 -
Sub total -(1 -
2 Silt excluder construction
2.1 Normal soil excavetion m3 123.35 -
2.2 Hard core m3 15.5 -
24.BILL OF QUANTITY
No. work Discription Unit
item unit Quantity cost Total cost
1 Head work
1.1.1 site clearing m2 600 -
1.1.2 excation of ordinary soil m3 722.9
1.1.3 selected material filling and compaction m3 262.5
1.1.4 Hard core m3 198
1.1.5 C-20 mass concrete (1:3:6 m3 129
1.1.6 Masonry 1:3 mix m3 129.16
1.1.7 plastering m2 51.2
1.1.8 pointing m2 56
1.1.9 Gate installetion spindle (intake gate 1
1.2 River traning wall at down stream
1.2.1 Excavetion of ordinary soil m3 180 -
1.2.2 Masonry 1:3 mix m3 157.44 -
1.2.3 compacted back fill m3 33.6 -
1.2.4 plastering m2 76.8 -
Sub total -(1 -
2 lined main canal construction m 1000
2.1 site clearing m2 2000 -
2.2 Excavetion of ordinary soil m3 1938 -
2.3 Hard core m3 334.95 -
2.4 Masonry 1:3 mix m3 680 -
2.5 Plastering mix ratio (1:3 m2 1722.6 -
2.6 pointing m2 957 -
2.7 compacted back fill m3 287.1 -
2.8 C-15 lean concrete (1:2:4 m3 200.97 -
Sub total -(2 -
3 construction of man hole No 3
3.1 Masonry 1:3 mix m3 55 -
3.2 C-20 mass concrete (1:3:6 m3 5.5 -
installetion man hole coverage gate by
3.3 metal sheet 4mm thick No 3 -
Rieinforcement bars dia 6 mm,dia 10
3.4 mm and dia 12 mm kg 410 -
sub total -3 -
4 Turn outs construction No 20 -
4.1 Excavetion of ordinary soil m3 180 -
4.2 Hard core m2 55 -
4.3 Masonry 1:3 mix m3 84 -
4.4 plastering 1:3 ( mix mortar m2 100 -
4.5 pointing (1:3 mortar m2 27.6 -
4.6 Backfill and compaction m3 10.35 -
4.7 Gate with sliding (0.3m x0.3 m No 40 -
Sub total -(4 -
5 Division boxes No 1
5.1 Excavation m3 5 -
5.2 Hard core (20 cm m2 3.1 -
5.3 Masonry 1:3 mix m3 2.5 -
5.4 plastering 1:3 ( mix mortar m2 26 -
3 mm thick double framed with angle
iron gate works supply and installation
5.5 with chain tied on it No 2 -
Sub total -(5 -
sum of sub -total -
VAT-15% -
Grand total project cost -